TO: Mayor and City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
DATE: 04/02/2013
SUBJECT: Approval of a Storm Water Utility Justification Study by WSB & Associates, Inc. (E)
Action Sought
Approve a motion authorizing the appropriate City Officials to execute an extension agreement with WSB &
Associates, Inc. for a Storm Water Utility Justification Study.
Background
A Storm Water Utility was established by Ordinance No. 176 on August 8, 1985. Since that time, many changes
have occurred in the storm water management area especially in the area of water quality and quantity.
Staff has budgeted in the surface drainage account, funds to revisit the theory behind the rate structure and analyzed
the rate with actual storm water needs.
The attached proposal has three major tasks to be done in the 90 days from authorization of the proposal as follows:
1. Review the Existing Storm Water Utility
2. Define Activities to be Funded by the Utility
3. Finalize Fee Structure /Proposed Rates
The Finance Director and I are supportive in moving forward with this proposal.
Recommendation
Approve a motion authorizing the appropriate City Officials to execute the Extension Agreement with WSB &
Associates, Inc. for a Storm Water Utility Justification Study.
Budget Impact
This study will be funded from the Surface Drainage Fund and sufficient funds are available.
Relationship to Vision
This supports Goal E: Deliver effective and efficient public services by a staff of well trained, caring, and
professional employees.
Requested Action
Approve a motion authorizing the appropriate City Officials to execute the Extension Agreement with WSB &
Associates, Inc. for a Storm Water Utility Justification Study.
Attachments: Proposal -Storm Water Utility Justification
WSB
Engineering ■ Planning ■ Environmental ■ Construction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 - 541 -4800
Fax: 763 -541 -1700
March 26, 2013
Mr. Bruce Loney, PE
Director of Public Works /City Engineer
Public Works Department
500 Gorman Street
Shakopee, MN 55379
Re: Proposal for a Storm Water Utility Justification Study
City of Shakopee, MN
Dear Mr. Loney:
WSB & Associates, Inc. (WSB) is pleased to submit this proposal to complete a Storm Water
Utility Fee Justification Report. Attached to this letter is Exhibit A — Scope of Work which .
provides a description of the work to be completed.
Compensation for services to complete the project will be in accordance with the hour estimates
outlined in Exhibit B, and according to WSB's agreement for professional services with the City
of Shakopee.
Understanding
Shakopee developed its existing rate structure in the 1980's. Since that time, storm water
management has evolved to emphasize water quality as much as flood control. Additionally, the
City established 0.1 and 0.3 cfs /acre rate control requirements in the late 2000's. This rate
control policy eliminates some of the water quantity distinction between more and less
impervious land uses. These changes warrant that the theory behind the rate be revisited and that
the City re- aligns the rate with actual storm water needs.
WSB Project Team
• Bob Barth — Project Manager
• Jacob Newhall, PE — Project Engineer
• Ted Witkowski — Engineering Specialist
• Bryan Pittman — GIS Specialist
WSB proposes to submit a draft Utility Fee Justification report within 90 days of receiving
notice to proceed and will work with the City of Shakopee to complete a document that best
reflects the needs of the City. This letter proposal represents our understanding of the project
scope.
1 O1Jd1. 3f.O J rou,r r,. a'YNOPA 1,>,i.•NOJMlJ.i'l1Y'.Mr xwrx+,rpn..
Mr. Bruce Loney, PE
March 26, 2013
Page 2
The City of Shakopee agrees to reimburse WSB & Associates, Inc. for these services in
accordance with Section IV of the Agreement for Professional Services. If this agreement meets
your approval, please sign below and return one copy to our office. Thank you for your
consideration.
Sincerely,
WSB & Associates, Inc.
Ao r
Bob Barth
Senior Project Manager
ACCEPTED BY:
City Administrator
Mayor
Date
A'. 013.N,IdiI,HMunf<wm «rl'g0Ph 1....Oi 61,0111uugir,uuw.
EXHIBIT A
SCOPE OF WORK
Task 1— Review the Existing Storm Water Utility
This task consists of reviewing the existing Storm Water Utility for the City of Shakopee. This
review generally consists of the following activities:
Review Policy and Parameters Used to Calculate Fee
We will review the Storm Water Utility Drainage policy and how that policy translates
into actual property charges. We will review the quality and application of parameters
that actually determine a charge: acreage, land use, design rainfall event, impervious
surface coverage, anticipated discharge rates, anticipated runoff volumes, etc. This task
will include collection of background data used for the existing rate structure. Data may
include existing and future land use mapping, aerial photography, City parcel records,
GIS shapefiles, existing zoning and land use regulations, etc.
Determine an Equitable Rate Structure
We will review the financial contribution of each land use against its relative use or burden to
the system under the current rates. Use or burden might differ for water quality, water
quantity, and compliance (MS4) so a three tiered system may be justified. We will develop
side by side comparisons of up to two new rate structures, in addition to the existing rate
structure, for consideration by staff. A "test of reasonableness" will be provided for the
recommended fee structure. This "test of reasonableness" will include a survey of how other
Metro communities divide their utility rates among different land uses. This task culminates
in a recommendation for a rate structure.
Review Existing Ordinance
The existing Storm Water Utility Ordinance will be reviewed and updated to reflect any
modifications made to parameters and rate structures from previous activities. WSB will
attend one Council work session and one City Council meeting to present the updated
ordinance to the City Council for adoption if changes are needed.
Task 2 — Define Activities to be Funded by the Utility
As part of this task, City activities to be funded by storm water utility fees will be defined. This
activity will attempt to quantify all storm water management expenses that will occur in the City
in the coming 10± years and allow the City to determine how funding for these activities will be
divided among various revenue sources. WSB will utilize the City's comprehensive plan, capital
improvement plan, maintenance plans, and other background information to develop a list of
activities and costs that are anticipated to be funded by the Utility.
Development of Pond Database
Maintaining existing storm water basins is a significant expense and is important to
consider when reviewing storm water utility rates. We will use 2007 delineated
subwatersheds and identified storm water basins and associate the following parameters
with individual basins:
• Drainage area
• Drainage area impervious (generic based on land use)\
• Pond year built (provided by staff or based on development era)
• Assumed pond volume (based on design standards applicable to year built)
Exhibit A _. Scope of Work
March 26, 2013
Page 2
WSB's Storm Water Asset Management Program (SWAMP) builds off this primary
input by applying loading factors, managed depth criteria, basin aging, estimated
treatment, and other input parameters to derive output results such as a priority
maintenance schedule and cost/benefit calculation, to name two. Here we will work with
City staff to implement the first part of what could turn into a SWAMP program at some
later date. We will load the pond based on a solids loading rate and pond age. If a
significant portion of pond volume is utilized this pond becomes an inspection and
maintenance priority. In this way we get a feel for whether current funding for pond
inspections and maintenance is adequate for future obligations.
Task 3 — Finalize Fee Structure/Proposed Rates
Based on information collected as part of previous tasks, the utility fee structure and estimated
rates will be finalized based on amount of revenues that must be generated to meet the
anticipated storm water utility expenses. The rate methodology, comparison of options,
ordinance revisions, activities to be funded, and revised policy document will be compiled into a
Storm Water Utility Fee Justification Report.
CITY'S TASKS
The City's tasks related to this project will include:
• Designate a contact person
• Assist in prioritizing activities to be funded
• Provide the necessary GIS information relating to the pond inventory
• Attend meetings to discuss utility fee justification report
A' Al 1tl1-1 MsLlwnl. f' rnuvrcrl'N(If'- h:..wrwlt3.bl3� 11T'.luvipnn «m.do-.
EXHIBIT B
FEE ESTIMATE
WSB's fee estimate appears on the attached spreadsheet.
F: 111117.36().MMna ' M1 lomet.0. 041.i.g11 ln .maw dot
ESTIMATE OF HOURS AND COST
1 PROFESSIONAL SERVICES TO COMPLETE .
A SB STORM WATER UTILITY FEE JUSTIFICATION
SHAKOPEE
Labor Category and Estimated Hours per Task
Description Project Project Engineering GIS Clerical Total Total Labor
Task Manager Engineer Specialist Specialist Hours Cost
1 Review Existing Storm Water Utility 16 4 2 22 $ 2,834.00
2 Define Activities to be Funded by the Utility 4 8 8 6 26 $ 2,628.00
3 ,Finalize Fee Structure /Proposed Rates 20 4 4 4 8 40 $ 4,496.00
Total Estimated Hours 40 16 12 6 14 88
Hourly Billing Rate $ 142.00 $ 101.00 $ 110.00 $ 79.00 $ 62.00
Total Cost by Labor Classification $ 5,680.00 $ 1,616.00 $ 1,320.00 $ 474.00 $ 868.00 $ 9,958.00