HomeMy WebLinkAbout15.B.3. Extension Agreement to Update the Blus Lake Hydrologic/Hydraulic Model
..
.. .~
IS: 13. 3
\
CITY OF SHAKOPEE
Memorandum
TO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
SUBJECT: Consider Authorizing an Extension Agreement to
Update the Blue Lake Hydrologic/Hydraulic Model
DATE: July 6, 2004
INTRODUCTION:
Attached is a proposal to update the Blue Lake Hydrologic/Hydraulic Model from WSB
& Associates, Inc. and for Council consideration to approve this proposal.
BACKGROUND:
The City of Shakopee has been working with the Prior Lake-Spring Lake Watershed
District and the City of Prior Lake to revise the Joint Powers Agreement for the Prior
Lake outlet channel for the past three years. Included in the Prior Lake channel is the
Blue Lake Watershed, which includes drainage areas from the City of Prior Lake,
Shakopee Mdewakanton Sioux Community and the City of Shakopee, from Pike Lake
Trail to the west and south. Staff has been working with PLSL WD staff to revise the
Joint Powers Agreement, which would include cost sharing of various reaches of the
improved channel based on low participation of each government entity. In order to
continue with a revised Joint Powers Agreement and cost participation formulas, staff is
requesting additional work to be done to the Blue Lake Hydrologic/Hydraulic Model to
help in the preparation of the Joint Powers Agreement.
This proposal will analyze the pre-development conditions of the Blue Lake Watershed
and determine pre-development discharge rates to the Shakopee Mdewakanton Sioux
property at C.R. 83 and also to the Prior Lake-Spring Lake outlet channel. Also included
in this proposal is to revise the existing hydrologic model to appropriate watershed
boundary changes, stormwater volume and discharge restrictions that have been put in
place as part of recent developments and to have a more accurate model representing
these changes. The result of this study will then be presented to the PLSL WD and City
Council at future meetings to assist in the preparation of a revised Joint Powers
Agreement.
Included with this memo is an e-mail from Shannon Lotthammer, District Administrator
ofthe PLSLWD, stating that the District has a goal to revise the Joint Powers Agreement
this year. Also included is a letter and map from Todd Hubmer, of WSB & Associates,
Inc., showing some of the drainage changes in the Blue Lake Watershed as well as a map
showing the Blue Lake channel and Prior Lake outlet channel.
The cost of this proposal isnot-to~exceed $3,800.00 and staff is recommending that this
work be authorized to provide the additional information and a revised model for
analyzing the stormwater from the Blue Lake channel to the Prior Lake channel.
ALTERNATIVES:
1. Approve a motion authorizing the appropriate City officials to execute the
extension agreement with WSB & Associates, Inc. for an update to the Blue Lake
Hydrologic/Hydraulic Model not-to-exceed $3,800.00.
2. Do not authorize this proposed extension agreement.
3. Table for additional information.
RECOMMENDATION:
Staff would recommend Alternative No.1, in order to provide a more current model in
working with the PLSL WD and the City of Prior Lake for a revised Joint Powers
Agreement.
ACTION REQUESTED:
Approve a motion authorizing appropriate City officials to execute an extension
agreement with WSB & Associates, Inc. to update the Blue Lake Hydrologic/Hydraulic
Model at a cost not-to-exceed $3,800.00.
~~
Public Works Director
BUpmp
ENGRlEMPLOYEEFOLDERlPPENNINGTON/COUNCIUHYDMODEL
Page I of 1
Bruce Loney
N^V,O
From: Shannon Lotthammer [slotthammer@plslwd.org]
Sent: Tuesday, June 08, 2004 11 :50 AM
To: Bruce Loney
Subject: JPA goal info.
Hi Bruce -
Thanks for the call this morning. I'm glad to hear that you received a proposal from Todd and it's going to your
Council for approval soon. Should I plan on attending that Council meeting in case there are any questions I can
help with? Just let me know...
As for documentation of the JPA being a stated goal of the Watershed District, the District's approved Water
Resources Management Plan, which was adopted in January 1999, includes the completion of a new/revised
Joint Powers Agreement as an overall goal of the District. In addition, the Prior Lake Outlet Channel and Lake
Volume Management Study completed in May 2003 identifies the need to complete a new/revised JPA. Finally,
the completion of the JPA was included by the PLSLWD Board of Managers as an overall goal and Work Plan
element for 2004.
Is the above enough documentation for your Council report? If you need more details, let me know and I'd be
happy to send you something more.
Thanks, and have a great week!
Shannon
Shannon Lotthammer, District Administrator
Prior Lake-Spring Lake Watershed District
15815 Franklin Trail SE
Prior Lake, MN 55372
slotthammer@plslwd.org
952-447-4166; ~plslw(:tQfg
6/30/2004
'1.'" - .6..
WSB & ASSOC. Inc. e
WSB
4150 Olson Memorial Highway, #300
Minneapolis, MN 55422
(763) 541-4800
& Associates, Inc. (763) 541-1700 (fax)
May II, 2004
Mr. Bruce Loney
City of Shakopee
129 Holmes Street S.
Shakopee,~ 55379
Re: Review of the Drainage Areas Tributary to the Northwest Quadrant
of the Intersection of County Road 83 and Valley View Road
Dear Mr. Loney:
Attached please find a Figure showing the pre-development and post-development drainage areas
tributary to the northwest quadrant of the intersection County Road 83 and Valley View Road in the City
of Shakopee. The drainage area tributary to this location has been reduced by 369 acres, through the
development of Pheasant Run and others which have directed stormwater away from this intersection,
north to the 169 drainage system and the Upper Valley Drainageway.
There remains approximately 405 acres tributary to the northwest corner of County Road 83 and Valley
View Road. However, it should be noted that both the Greenfield Addition and the Park Meadows
developments have been designed to provide stormwater ponding and infiltration of the 100-year critical
storm event, with no discharge currently allowed to their eastern boundaries. These two developments
are effectively landlocked for the 100-year storm event, with only emergency flows which could be
directed to the east in extreme storm events. The remaining 148 acres currently is undeveloped and
drains to the northwest quadrant of this intersection.
The total volume of stormwater runoff directed to this quadrant of the intersection has been reduced for
the I-year, lO-year, and lOO-year storm events by 9 acre-feet, 48 acre-feet, and 124-acre feet,
respectively.
If you have any questions, please call me at 763-287-7182.
Sincerely,
WSB & Associates, Inc.
Todd Hubmer, P.E.
cc: Jeff Weyandt - City of Shakopee
Joe Swentek - City of Shakopee
G:\EMPLOYEE FOLDERS\JSWENTEKlDEVELOPMENT.REVIEWSIPLA T.REVIEWIP ARKMEADOWS (GONYEAPROP)\051I Q4-BL-EMAIL.DOC
I ~~?j:rt#J$ijJt,,~jj 1 ~ T/ 1\
~ 7k:;:::: ill'~ 'r ~
~ ~~~~~~~:~~---
~L-J--~ ~ ~ _ ~ "
1.- ~ -~ =-( '~
I ~
o 750 1500 ~ "-. Y--
~/ ~Silm ~
~~:; e!:~:~:: PRE-DEVELOPMENT POST-DEVELOPMENT
T filIIlflJlllI 1ll\Y1\i\~GlIli: + r- DRAlNAGE BOUNDARYrDRAINAGE BOUNDARY
~ il ~~
f-W/ / ~:~
~c<:: V T
:/ ./ 0 R-24r R VOL.
I):::. m OYR-2 HR VOL. ~)RJ GE
'I X ~ ~ STO AGE,
II \.: \ \ J \
-r. r\ II 'AV -'i' ~~
'< 1 ,/.
'7 .
III ~
~~ f; ~
0! J]~ ///)>f/;
- ~ / /~ ~
-~ !U~ ~~~~ i
J HJ D ,/V A / / / .L.~YVI~ BbAD \.\. "
/ \ ( ",- ""'-Ii ..( / ~ ..- ~ ___
~ ~"I ~ - A: wrmKO DTSCHAROE IN lOO-YEAREVENT.
M'.)J~ ~~ PRE & POST DEVELOPMENT DRAINAGE SUMMARY
f\ _ FOR THE NW QUAD OF CR 83 & VALLEY VIEW ROAD
\ DRAINAGE AREA 1-YEAR to-YEAR tOO-YEAR
~51 I 1 '"~''''''''''' "'~~ ,,~ "" ,~~
<l .4... v \ / POST DEVELOPED 405 Acres 2 AF 11 M' 25 AF
) ~ I / []lJC~ Approximately 369 Acres directed north to the Upper Valley Drainage way.,
Greenfield and Park Meadows Developments contain storm water ponds
:::;::::::::n 1 \ and Inmlration adequate to hold the 10G-Year storm event on-site with no discharge.
,\
WSB Project No. Date: May 11, 2004
... 4150 Olson Memorial HI.ghway PRE & POST DEVELOPMENT City Project No.
.... SUite 300 .
IAf~D Minneapofis MN 55422 DRANAGE AREA MAP TO
YY wQ 763-541-4300 NW QUAD OF CR 83 & VALLEY VIEW ROAD
& Assodt11es. int:. FAX 763-541-1700
.1~I:I;:"~'I:.lIf""J:.t:u'....~[til~I~~:...."''':i.''~I~l:l:+-' SHAKO PEE., MINNESOTA
-- ---------,,- --
.---------- -- -------.---
~
(])
;.....
0
-- - -. - bO
.-
---~- ~
~
..
if!'
i
~,- I~ "
I. I ~ ~
a ~~ ~ ~
~. ,0 c. \... ~ N
z
~ .
; ~ 8
.. ~ ~ !
~rdli LAKE ~ 2
59 cfs ~
S MPH.' .. ~r~i a:Cl2
~::ri.::>
~F iia~
., ~~W . ~
BL E2B ~~~ w ~
. ~
':;;:'5:i ~ -
~~~~ "
z
~-~~~ ffi @
;~~~ ~ ~
17 cIs ~ "
~~~~ i
o~" a. _
26 cfs g~~a '" ~
>-~>-'t: w ~
'" ~ ," ~ ~
:;;:~o...
] \j~<~
~[!!
~~g~ c
9 cfs
E-<<
UE-<
~~O
BL Cl -OCl'.l
~~~
CZlE-<~
Uz
;;;~ ~
LAKE IX) ~
~~~
~~! . BLC/ LEGEND ~~~
CZl00
:j-,:J,.:ir- rf~~",.,'::(~i _t~-f{;f, U~~
~~ . I,~= --_.7-'.T'~=.:= -,~. -=0 ->>- PROPOSED STORM ~CI'.l
>
~ SEWER SYSTEM ....
" BLC3 <[(~)]) DIRECTLY BENEFITTED WATERSHEDS
BL Dl1 ..----- SUB-WATERSHED BOUNDARY
MPA2 SUB-WATERSHED IDENTIFICATION
STORM WATER ROUTING
I 1. l.IlNNHOTA CT. STREET NAMES
>'0 N 0 0
MYSTIC LAKE ~ CITY LIMITS ~g~ ~ ~ .
.L:1UlI) ,....,....
BLD6 fP NWI WETLANDS :f=5 z ~ ~ -
mCf.l ~ co:2 .
.C . ,...,....
PEAK CHANNEL FLOW E ~ ~
4 cis " "-
FOR 100 YEAR EVENT ::; gj
c c
,~~ o .s
t:f~ . SPECIAL OUTLET STRUCTURES ~ ::; .
"),.'\;- () 0
0
~ :'1 "'
~ r:- STORMWATER STORAGE POND ~
BL 017 t,.J.;t" ~r
c BLUE LAKE WATERSHED WITHIN
'" ~~ !:
i u ..
.-; '250 625 0 1250 2500 THE CITY OF SHAKOPEE
" : , , , I
/' "'. SCALE IN FEET
0 ~
U
/'
'"
'" SHAKOPEE
~
::;
..
Prior Lake Outlet Channel Feasibility Study ... '1150 Olson Memo.ial Highway
Suite 30U
<m> WSB Minneapolis, MN 55422
Segment Breakdown 763..041-4000
MONTGOMERY WATSON ~ SD- Z & !L(.f,X'ia~w. 111~. FAX 763-.5<11-1700
Figure 1 11"lilr.J..l.'IU.MIIIU=--"'iI~It'lI"I:iI:U~"''''~''~'i:'I:I''rf.'
A /5 f5 3
WSB May 27,2004
~-
& Associates, Inc,
Mr. Bruce Loney, P .E.
Public Works Director/City Engineer
City of Shakopee
129 Holmes Street South
Shakopee, MN 55379-1376
Re: Proposal to Update the Blue Lake Hydrologic/Hydraulic Model
Dear Mr. Loney:
According to our Agreement for Professional Services with the City of Shako pee and Section I-C-2
(Major Projects), this extension agreement is written to provide you with an estimate of costJor
engineering services for the above-referenced project. We are proposing to complete the work, as
described herein:
We propose to update the City of Shakopee's Blue Lake Model to incorporate the ch,anges in drainage
boundaries, peak discharge rates, and storage volumes associated with new development tributary to
the Prior LakelDean Lake outlet channel.
This work is anticipated to consist of the following task:
1. Prepare a predevelopment conditions, hydrologic model that provides pre-development
discharge rates to the Mdewakanton Sioux property and to the Prior Lake/Spring Lake
outlet channel.
2. Revise the existing HydroCad model for the City of Shakopee to incorporate the
watershed boundary changes, storm water volume, and discharge restrictions put in place
as part of recent developments.
3. Provide necessary support, documentation, and attendance to at least two meetings in
regards to discharge rates to the Prior Lake/Spring Lake outlet channel.
We anticipate the cost of this effort not to exceed $3,800.
Ifthis agreement meets with your approval, please sign below and return one copy to our office.
Sincerely,
WSB & Associates,Jllc.
~~ City Administrator
Todd E. Hubmer, P.E.
Associate
4150 Olson
Memorial Highway City Clerk
Suite 300
Minneapolis
Minnesota Mayor
55422
763.541.4800 Date
763.541-1700 FAX Minneapolis. St. Cloud. Equal Opportunity Employer P:\Shakopee\052704 bLdoc