CITY OF SHAKOPEE
Memorandum
CASE NO.: NA
TO: Mayor and City Council
Mark McNeill, City Administrator
FROM: R. Michael Leek, Community Development Director
SUBJECT: Request of Ryan Companies, U.s., Inc. for Waiver of Construction Start
Time
MEETING DATE: August 10, 2004
REVIEW PERIOD: NA
INTRODUCTION:
City Code Sec. 10.60, Subd. 3, D. restricts the start time for construction activities to 7 a.m. on
weekdays and 9 a.m. on weekends. Because of a change in the method of creating and placing
concrete panels, by letter dated and received August 5th, Ryan requested a waiver of that provision
to allow a 4 a.m. start on 8/09 -8/11/2004 to ensure placement and cure of concrete slab for the
Challenge Printing site. The site is located in Valley Green Business Park, and is not adjacent to
any residential areas.
ALTERNATIVES:
1. Approve the waiver requested to allow a 4 a.m. start time for concrete placement and curing
for 3 consecutive days during the week of August 9, 2004
2. Deny the waiver requested to allow a 4 a.m. start time for concrete placement and curing for
3 consecutive days during the week of August 9, 2004
ACTION REQUESTED:
If the Council is amenable to the request, offer and approve a. motion approving the waiver
requested to allow a 4 a.m. start time for concrete placement and curing for 3 consecutive days
during the week of August 9,2004
R. Michael Leek
Community Development Director
08/05/2004 13:05 RYAN COMPANIES ? 99522333801 NO. 371 [;102
RYAN COMPANIES US, INC &RYAN
so South Tenth SUCct, Suite 300
WWW.RYANCOMPANIES.COM MinneApolis, MN 55403.2012
aUILOINS ....STINS AEL4T,ONSIlI'$
612-492.4000 t<<
612-492-3000fix
August 5, 2004
aty of Shakopee
.Mr. Jim Grampre
129 Holmes Street South
Shakopee, MN 55379
Regarding: Challenge Printing
Sbakopee,~esota
Dear:Mr. Grampre:
This pwpose of this correspondence is to request a variance for Start time of cODStruction activity.
Oment Gtyordinance States merior constlucnon activities Start aI'ter 7am. Ryan Campanies is requesting an
early construction activity start time of 4 am for 8/9/04, S/ 10/04, and 8/11/04 weacller pending. We would
like to have OUf concrete crew ste'Ut at 4 am to eDSure ncccssaryplacement and cure of our.concrete slab. We
realize we are requesting quick response without proceeding through proper approval channels and greatly
appreciate any help.
We look forward to the contll-lUed positive worlmtg relationship Mth the Gty of Shakopec, and to the successful
completion of this project.
Sincerely,
R1ioP'fNC
Nate Pearson
Project Manager
cc: Mark Ford
3.6,
CITY OF SHAKO PEE
Memorandum
CASE NO.: NA
TO: Mayor and City Council
Mark McNeill, City Administrator
FROM: R. Michael Leek, Community Development Director
SUBJECT: Request of Ryan Companies, U.S., Inc. for Waiver of Construction Start
Time
MEETING DATE: August 10, 2004
REVIEW PERIOD: NA
INTRODUCTION:
City Code Sec. 10.60, Subd. 3, D. restricts the start time for construction activities to 7 a.m. on
weekdays and 9 a.m. on weekends. Because of a change in the method of creating and placing
concrete panels, by letter dated and received August 5th, Ryan requested a waiver ofthat provision
to allow a 4 a.m. start on 8/09 -8/11/2004 to ensure placement and cure of concrete slab for the
Challenge Printing site. The site is located in Valley Green Business Park, and is not adjacent to
any residential areas.
ALTERNATIVES:
1. Approve the waiver requested to allow a 4 a.m. start time for concrete placement and curing
for 3 consecutive days during the week of August 9, 2004
2. Deny the waiver requested to allow a 4 a.m. start time for concrete placement and curing for
3 consecutive days during the week of August 9, 2004
ACTION REQUESTED:
Ifthe Council is amenable to the request, offer and approve a motion approving the waiver
requested to allow a 4 a.m. start time for concrete placement and curing for 3 consecutive days
during the week of August 9, 2004
R. Michael Leek
Community Development Director
'08:;05:;2004 RYAN COMPANIES ? 99522333801 No.371 [;102
\'..;.'-
! RYAN COMPANIES US,INC IYAN
SO South Temh SucC't, Suite 300
WWW.RYANCOMPANIES.COM MiImeApolis. MN 55403.2012
aUILO'NS ....STINll DE....'l"O~SIlIP$
612.0\-92.4000 t<<
612-492-3000fix
i
l
i August 5,2004
I
I
i aty of Shakopee
i .Mr. Jim Grampre
I 129 Holmes Street South
Shakopeo, MN 55379
I
Regarding: Challenge Printing
.
I Sbakopee, Minnesota
I
I
.
, Dear:Mr. Grampre:
!
I
[ TIlls pwpose of this correspondence is to request a vanance for Start time of CODStnlction activity.
!
Oment Gtyordinance states eXterior consuuctionactivities Stalt after 7am. Ryan Campanies is requesting an
early construction activity start time of 4 am for 8/9/04, SIt 0104, and. 8/11/04 weather pending. We would
like to have OUf concrete crew st.'Ut at 4 am to el1SU.re nccessaryplacellJellt and. cme of our concrete slab. We
~alize we are requesting quick response without proceeding throu.gh proper approval channels and greatly
appreciate any help.
We look forward to the continued positive working relationship vvith the Gty of Shakopec, and to the successful
completion of this project.
Sincerely,
R1~p~mc
Nate Pearson
ProjeCt Manager