HomeMy WebLinkAbout9.C. Proposed Assessments for Vierling Drive from CSAH 15 to Orchard Park West PUD, 2002-4-Res. No. 6141
9aC
,
CITY OF SHAKOPEE
Memorandum
TO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
SUBJECT: Assessment Hearing for 2003 Vierling Drive Improvements,
Project No. 2002-4
DATE: November 3,2004
INTRODUCTION:
Attached is Resolution No. 6141, a resolution which adopts the assessment for the above
referenced project.
BACKGROUND:
On October 15, 2002, City Council adopted Resolution No. 5796, a resolution ordering
the improvement of Vierling Drive, from County Road 15 to Orchard Park West. On
February 4, 2003, the City Council reviewed alternatives of roadway alignment and
selected an alignment which would allow a fire station to be built in Lion's Park. The
City also later sold approximately 2 acres, north of Vierling Drive to Pat Link
Construction. Plans were approved by the Council on July 15, 2003 by adopting
Resolution No. 5911. A contract was awarded to S.M. Hengtes & Sons, Inc. on August
19,2003 and the work done in 2003 and 2004.
This project has essentially been completed and all project costs identified. The final
project cost IS $835,550.15, which consists of construction costs and
engineering/administration costs. A breakdown ofthe project costs are as follows;
Description Amount
City Costs (State Aid) . $101,975.77
City Costs (Storm Sewer Fund) $167,263.06
Assessments $545,717.30
SPUC $ 20,594.02
TOTAL PROJECT COSTS $835,550.15
The local street equivalent was assessed to benefiting properties, as per the feasibility
report. The City costs are for the widening of the road to a collector street, bituminous
trail and the box culvert. SPUC's participation is for the trunk oversizing of the
';:A:
,
The City also is receiving an assessment of $105,265.00 for future Lion's Park fire
station. Other properties assessed included the area purchased by Pat Link Construction
from the City, north of Vierling Drive and an undeveloped 24 acre parcel south of
Vierling Drive. Property was assessed based on benefiting property front footage that
would benefit from the improvements.
Attached to this memo is a funding summary of the project, assessment roll and
assessment map showing the benefiting areas.
Also attached is a letter from Cal Haaskens, Sharon Haaskens, Christy Haaskens Schuler
and Chad Haaskens objecting to the assessment to their parcel.
A presentation of the project costs and assessments will be made at the public hearing.
AL TERNA TIVES:
1. Adopt Resolution No. 6141.
2. Deny Resolution No. 6141.
3. Table Resolution No. 6141 for specific reasons.
RECOMMENDATION:
Staff recommends Alternative No. 1.
ACTION REQUESTED:
Offer Resolution No. 6141, A Resolution Adopting Assessments for 2003 Vierling Drive
Improvements, Vierling Drive, from County Road 15 to Orchard Park West Plat Line,
Project No. 2002-4 and move it adoption.
aney
Public Works Dire
BUpmp
ENGRl2002PROJECTNIERLNGDRlWORDlMEM6141
RESOLUTION NO. 6141
A Resolution Adopting Assessments
For 2003 Vierling Drive Improvements,
Vierling Drive, From County Road 15
To Orchard Park West Plat Line
Project No. 2002-4
WHEREAS, pursuant to proper notice duly given as required by law, the City Council of
the City of Shako pee met and heard and passed upon all objections to the proposed assessments of:
Vierling Drive, from County Road 15 to Orchard Park West Plat Line for reconstruction
and any appurtenant work.
NOW, THEREFORE, BE IT RESOL YED BY THE CITY COUNCIL OF THE CITY OF
SHAKOPEE, MINNESOTA:
1. That such proposed assessment together with any amendments thereof, a copy of which
is attached hereto and made a part hereof, is hereby accepted and shall constitute. the special
assessment against the lands named herein and each tract therein included is hereby found to be
benefitted by the proposed improvements in the amount of the assessments levied against it.
2. Such assessments shall be payable in equal annual installments extending over a period
often years, the fIrst installment to be payable on or before the first Monday in January, 2005, and
shall bear interest at the rate of 5.25 percent per annum from the date of the adoption of this
assessment resolution. To the first installment shall be added the interest on the entire assessment
from the date of this resolution until December 31, 2005 and to each subsequent installment when
due shall be added the interest for one year on all unpaid installments.
3. The owner of any property so assessed may, at any time prior to certification of the
assessment to the County Auditor, pay the whole of the assessment on such property, with interest
accrued to the date of payment, to the City Treasurer, except that no interest shall be charged if the
entire assessment is paid within thirty (30) days from the adoption of this resolution; the owner
may thereafter pay to the County Treasurer the installment and interest in process of collection on
the current tax list, and may pay the remaining principal balance of the assessment to the City
Treasurer.
4. The Clerk shall file the assessment rolls pertaining to this assessment in her offIce and
shall certify annually to the County Auditor on or before November 30th of each year the total
amount of installment~ and interest On assessments on each parcel of land which are to become due
in the following year.
Adopted in session of the City Council of the City of
Shakopee, Minnesota, held this day of ,2004.
Mayor of the City of Shakopee
ATTEST:
City Clerk
Assessment Roll
City of Shakopee
Vierling Drive
From County Road 15 to Orchard Park West
October, 2004
P.I.D. Property Total
Owner Assessment
Cal & Sharon Haasken
279120500 413 Chestnut St. $250,452.30
Chaska, MN 55318
Link Construction Inc,
279120271 12756 N. Shannon Dr. $190,000.00
Shakopee, MN 55379
279120270 City of Shako pee $105,265.00
$545,717.30 I
Prepared by JWeyandt 10/28/2004 Page 1
October 25, 2004
City of Shakopee
Judith S. Cox
:j?.e: ~n)igcf Alo. dCCld-1
To Whom It May Concern:
As the owners of the property located at the West lh of the SW~, Section 12,
Township 115, Range 23, Scott County, Minnesota, We hereby exercise our right to
appeal this assessment per the Minnesota Statues Section 429. 081. We feel that there is
no way that this said parcel has increased in value of$250.452.30 per these
improvements. Let this serve as our notice of our intentions to appeal these assessments.
Sincerely: ___
.-, ~.. I
/"/ /I .(J . · . . . .
L'0G( Cu. d~ll-<f{~
Cal Haasken Sharon A. Haasken
~~~vb4iL ~~~-
Christy . Haas n'Schuler Chad M. Haasken
~r~::E8L,
! i
i . \
\ t('T 27 J",.'.(! \
I U '1 :...,;_.~!
Ii
L; _.-.....-...1
~---~-_...-.-
CITY or; s; \::.;l"f~:'~E~ j
I Ii
i
i
!
I
i I
I
I
LIONS PARK ---
!
I
i
j
I
i
1
;
I
I
I
_._~ LINK
CONSTRUCTION
-............",....."..,,~~... PROPERTY
BEGIN
CONSTRUCTION
END CONSTRUCTION
ORCHARD PARK WEST
HAASKEN PROPERTY
)( ASSESSMENT BY
PROPOSED VIERLING DRIVE ~
ADJUSTED FRONT
CR 15 TO ORCHARD PARK WEST PLATLINE FOOTAGE SHAKOPJEE
CXMoUlIIYPllDlSINCII1III7
Vierling Drive Assessment Summary
Construction Cost Project Cost Total Cost
Street Assessment $ 250,682.13 $ 79,183.02 $ 329,865,15
Street Oversizing $ 69,896.84 $ 22,078.33 $ 91,975.16
Lighting City Cost $ 7,600.00 $ 2,400.61 $ 10,000.61
Lighting Assessable $ 7,600.00 $ 2,400.61 $ 10,000.61
SPUC Conduit $ 965.00 $ 304.81 $ 1,269.81
Sanitary Sewer Assessment $ 10,564.42 $ 3,336.99 $ 13,901.41
Watermain Assessment $ 73,074.15 $ 23,081.95 $ 96,156.10
Watermain Oversizing $ 14,685.50 $ 4,638.71 $ 19,324.21
Storm Sewer Assessment $ 72,799.00 $ 22,995.03 $ 95,794.03
Box Culvert (Storm Trunk) $ 127,112.13 $ 40,150.93 $ 167,263.06
Total $ 634,979.17 $ 200,571.00 $ 835,550.17
Actual Project Costs
Assessed Cost $ 545,717.30
City Cost $ 269,238.83
SPUC Cost $ 20,594.02
Total = $ 835,550.15 Actual
Feasibility Study Costs
Assessed Costs $ 530,176.68
City Cost $ 325,065.51
SPUC Cost $ 9,345.88
Total = $ 864,588.07 Feasibility