HomeMy WebLinkAbout15.A.1. Authorize Reimbursement Agreement with Tollefson Development and an Extension Agreement with WSB & Associates I 5, ff, / ~ CITY OF SHAKOPEE Memorandum TO: Mayor & City Council Mark McNeill, City Administrator FROM: Bruce Loney, Public Works Director SUBJECT: Authorize Reimbursement Agreement with Tollefson Development, Inc. and Authorize an Extension Agreement with WSB & Associates, Inc. for the Design ofC.R. 77 & C.R. 79, from T.H. 169 to 2000 Feet South of 1 ih Avenue DATE: January 18,2005 INTRODUCTION: Attached is a reimbursement agreement between Tollefson Development, Inc. and the City of Shakopee for the design of c.R. 77 & C.R. 79, from T.R. 169 to 2000 feet south of 17th A venue, as prepared by the City Attorney. Also attached is an extension agreement from WSB & Associates, Inc..for the preparation of plans for C.R. 77 & c.R. 79. These agreements are for Council consideration in moving forward with the design to complete the roadway design associated with the Countryside Development by Tollefson Development and the new high school and possible secondary school for Independent School District (IS D) #720. BACKGROUND: Tollefson Development, Inc. has submitted a preliminary plat for their 170 acres of land abutting 17th Avenue, from CSAH 15 to C.R. 79 and abutting C.R. 77 & C.R. 79, from T.R. 169 to 2000 feet south of 17th Avenue. An EA W has been prepared for this proposed development, which consists of single-family residential land use. Also adjacent to C.R. 77 & C.R. 79, is a proposed new high school by ISD #720. In meetings with the developer, school district, staff and their design teams for the new high school, staff is recommending that C.R. 77 & C.R. 79 be designed by a City consultant, WSB & Associates, Inc. A set of plans would be done to meet State Aid requirements, Scott County and MnlDOT approval, coordination with Shakopee Public Utilities Commission (SPUC) and the City of Shakopee, as well as coordinate the design between the, two developments being Countryside Development and the new high school for ISD #720. During the design phase and also during the platting stage of the proposed development, a reimbursement agreement within the developer's agreement will need to address participating costs between the City and Tollefson Development for the construction of c.R. 77 & c.R. 79, from T.R. 169 for 2000 feet south of 17th Avenue. The City will also then enter into an agreement between the City and the County for cost participation of work associated with C.R. 77 & C.R. 79 improvements. The extension agreement, that is attached from WSB & Associates, Inc., does describe the approach and tasks associated with the design of the improvements and the coordination needed between the City, County, SPUC, developer, MnlDOT and ISD #720. Part of this process is cost split calculation for funding sources participation between the City, County and developer. It is proposed that the City consultant will design this roadway and the developer will construct the roadway with their financing and their contractor. The City will then enter into a developer's agreement and/or reimbursement agreement with the developer on cost sharing for 1 ih Avenue. The exact cost participation between the developer, City and County will be worked on as part of the design proposal and will be brought back to the City Council at a future Council meeting. ALTERNATIVES: 1. Authorize the appropriate City officials to enter into a reimbursement agreement with Tollefson Development, Inc. and the City of Shakopee for the design of C.R. 77 & C.R. 79, from T.H. 169 to 2000 feet south of 17th Avenue. 2. Do not enter into a reimbursement agreement with the developer at this time. 3. Authorize the appropriate City officials to enter into an extension agreement with WSB & Associates, Inc. for the design of C.R. 77 & c.R. 79, from T.H. 169 to 2000 feet south of 1 ih Avenue. 4. Do not enter into an extension agreement with WSB & Associates, Inc. 5. Table for additional information. RECOMMENDATION: Staff recommends Alternative No. 1 and No.3, as the developer has agreed to have the City's consultant design c.R. 77 & C.R. 79 and agreed to pay all costs. Theseroadway designs are necessary for development to be completed and to meet the time line and schedules for the construction ofthe new high school by ISD #720. ACTION REQUESTED: 1. Authorize the appropriate City officials to enter into a reimbursement agreement with Tollefson Development, Inc. and the City of Shakopee for the design of C.R. 77 & C.R. 79, from T.H. 169 to 2000 feet south of 17th Avenue. 2. Authorize the appropriate City officials to enter into an extension agreement with WSB & Associates, Inc. for the design of C. R. 77 & C.R. 79, from T.R. 169 to 2000 feet south of 1 ih Avenue. ~n~ Public Works Director BUpmp ENGR/2005PROJECT/C.R 77&79/WORD/DESIGN . REIMBURSEMENT AGREEMENT This Agreement is entered into as of January -' 2005, by and between the City of Shakopee (HCity") and Tollefson Development Inc. ("Tollefson"). RECITALS A. Tollefson has submitted a proposed development, known as Countryside Addition, ("Development") pursuant to which Tollefson proposes to develop approximately 172 acres of residential property located between CSAH 15 and County Road 77 and County Road 79 and south of Trunk Highway 169. ' B. In order to meet the infrastructure needs for the Development, the following Public Improvements need to be constructed: (1) reconstruction of County Road 77 and County Road 79, from T.H., 169 to 2000 feet south with the extension of sanitary sewer, storm drainage and watermain systems. C. Tollefson has requested that the City proceed with engineering and design of the Public Improvements and Tollefson is willing to reimburse the City for the costs incurred by the City in the design ofthe Public Improvements. Tollefson acknowledges that but for its agreement toreimbuise the City for these costs, the City would not be proceeding with the design ofthe Public Improvements. E. Tollefson has also proposed to provide the easements necessary to construct the Public Improvements within the Development. , F. The estimated cost for the. design work for the Public Improvements is $120,000. In consideration of the mutual covenants conditions and provisions in this Agreement, the City and Tollefson agree as folloWs: 1. The Recitals are true and correct and are incorporated by reference into this Agreement. 2. The City is authorized to retain WSB & Associates to design the Public Improvements. 3. Tollefson agrees to reimburse the City for 100% of the project costs incurred by the City in designing the Public Improvements. For the purposes of this Agreement, the term "project costs" includes all costs incurred by the City, including engineering and legal fees, and any administrative expenses. Tollefson shall make payment to the City within ten days after the City has provided a written invoice to Tollefson. '~~..<,,-..." -"'>'" ""4. Simultaneously with executingthis Agreement, TolTefson shall submit to the City $120,000 in cash or a certified letter of credit approved by the City Attorney made payable to the City upon which the City may draw if Tollefson defaults in any of its obligations under this Agreement. JJT-251836vl SH155.23 1 v 5. This Agreement is binding on the parties and their respective successors and assigns and shall be govemed by the laws of the State of Minnesota. 6. Tollefson may terminate this Agreement for any reason by providing written notice of termination to the City, provided however that Tollefson will be responsible for reimbursing the City for all project costs incurred up to the date that the City receives written notice of termination. 7. The invalidity or unenforceability of any provision in this Agreement shall not in any way affect the validity or enforceability of any other provision, and this Agreement shall be construed in all respects as if such invalid or unenforceable provisions had never been part of the Agreement. 8. This Agreement constitutes the entire agreementhetween the parties ,congerning the engineering and design ofthe project, and unless otherwise:pfovidecl)lhhisAgreement, any other agreements or understandings, whether oral or written; withrespectto such'matters are superseded and revoked. This Agreement may not be modified oI aITlended except by a writing signed by each party. - . . CITY OFSHAKOPEE,< '. ' By Its Mayor By Its' City Adirtinistrator By Its City Clerk TOLLEFSON DEVELOPMENT INC. By -., -, };:':";:'~~:;~~:-:;,-~,'_; > ;;o....,_c';::_'.;. ~ ." Its ',,--,'- _..- "....,-'.....,<'- '.'-.., JJT-251836vl SH155-23 2 A \' WSB & Associates, Inc. Infrastructure I Engineering I Planning I Construction 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 December 30,2004 Mr. Bruce Loney, P .E. Public Works Director/City Engineer City of Shakopee 129 Holmes Street South Shakopee,1fN 55379-1376 Re: .... Extension Agreement forProfessional Services EstimakofCost to Provide Engineering Services . County Road 77 and County Road 79 Reconstruction ~froMTH 169 to 2000 Feet South of 17th Avenue WSJ3Project No. 1566-06 ;, D~~r'Mt.'t8n.ey: According to our Agreement for Professional Services within the City of Shakopee and Section I-C-2 (Major Projects), this extension agreement is written to provide you with all estimate of cost for erigineeringservices for the above-referenced project. We are proposing to complete the work ,asdet,tiled on the attached Scope of Services, Exhibit A. ,The,J;lJtached work plan describes the approach and tasks proposed to be completed by WSB. It should be noted that the work plan includes engineering design for roadway plans, storm sewer plans, sanitary sewer plans, and water main plans, along with project coordination and right-of-way parcel drawings and descriptions. This cost assumes that the majority of the design survey work is complete and no Feasibility Report will be required. Soils infoffilation will be provided by Tollefson Development. the School District, and from previous adjacent construction projects. Any additional soil borings will be considered additional services. WSB will collect additional topographic infOlmation from the adjacent developers for development of base maps. It is further understood that the City of Shakopee will provide the construction observation and material testing during construction. Weare proposing to complete this work as described in the scope of design services herein attached on a cost-reimbursable basis in accordance.. with our current fee schedule. Payment of services for the design ph~se is estimated betweetitt15,OOO to $120,000. It is proposed that all work under the design portion of the contract would be considered complete after the preconstruction conference. Construction management and construction survey services are extra services and could be initiated after the preconstruction conference if so requested by the City. Minneapolis I St. Cloud Equal Opportunity Employer F:\WPWIM/566-061LTR-b/-/22304.doc ,. Mr. Bruce Loney. P .E. December 30. 2004 Page 2 Weare available to begin work as soon as authorized by the City, and we anticipate to complete the project according to the following schedule, assuming that we receive the notice to proceed on January 4, 2005. We would propose to complete the project according to a tentative schedule noted as follows: Approval extension agreement..... .......... ........................... ........... ...... ......... .......... January 4, 2005 Commence work .............. ...................... ......... .., ........... .............. ..... ........... ..... ..... January 5, 2005 Submit plans to MnDDT & Scott County for review..............:........................ February 18, 2005 Receive final plans approval ..................................................................................M arch 4,2005 (assuming 3-week review time by MnDOT) Approve plans ... ........... ..... ........ ....... ............... ........; ,........ ::.: ..........:..~..:. .......... ....M arch 15, 2005 The City of Shakopee agrees to reimburse WSB &Associatesforthese services in accordance with Section N ofthe Agreement for Professional Services:lftfii~; agreement nieets with your approval, please sign below and return one copy to our office, Sincerely, WSB:fi3~ - . ~... -.,' -~ ". Nt. ~- Donald W. Sterna, P.E. City Administrator Vice President -.'- City Clerk Mayor Date -'-~. -r-r,. F: \ WP W1MI5 66-06lLTR-b/-/223 04.doc - ~ Scope of Design Services County Road 77 and County Road 79 Roadway Improvements Scott County City of Shakopee WORK PLAN 1. Project Management This task includes planning and coordination of all work tasks, establishment and monitoring of budgets, and correspondence with the City of Shako pee, Scott County, S.P.D.C., Independent School District 720, Mn/DOT and Tollefson Development on a periodic basis. The project manager will provide technical direction on all aspects oftIle project review, all work products, and preparemcinthly progress reports. Theprojyct manager will serve a primary role in the many design considerations: Don Sterna is '. proposed to manage the project for WSB & Associates, Inc. (WSB): ,~ 2. Data Collection Available data will be collected from the City, Scott County, Mn/DOT, private utility companies, and adjacent developers as necessary, to prepare the cOllstructiondocuments.. 3. Soils Report Soils information will be provided by Tollefson Development and the School District." Any additional soil borings will be considered additional services. 4. Design Survey WSB has collected topographic infonnation from the adjacent developments which will be utilized in the final design. WSB will supplement these surveys with additional surveys at each termini of County Roads 79 and 77 in order to properly design the profile at each termini. Also, additional survey will be collected on the pond outlet located on the east'side of County Road 79 just south of 1 ih Avenue. Vertical and horizontal control will be tied into the adjacent developer's control to ensure consistence of the field survey data. 5. Construction Plans The construction plan phase involves the bulk of our final design effect. The plans will be developed meeting Mn/DOT State Aid standards. WSB will forward a copy of the final plans to Scott County and Mn/DOT Metro State Aid for state aid compliance review. It is WSB's understanding that both County Roads 77 and 79 will be constructed as pari: of the Countryside development and no specifications or bidding documents are required:.AIso,,,ojtis WSB' sunderstanding that County Road 77 will be widened to a 44- foot urban roadway with curb and gutter, bituminous trails and concrete sidewalk. County Road 79 is proposed to be reconstructed to a two-lane urban roadway with curb and gutter, 8-foot shoulders, with a 10-foot bituminous trail on the west side. F:\WPWIM/566-06\Scope of Services. doc . , . c( WSB will prepare a set of detailed construction plans for the grading, surface drainage and paving in accordance with Mn/DOT and County State Aid Highway standards. We will coordinate our work closely with Scott County and the City of Shakopee during the entire design process to ensure that the County's and City's expectations are satisfied. Design meetings will be held as appropriate to discuss design elements and comments during the design process. A final set of plans will be submitted to the County, City and State Aid for their review and approval. The final construction plans will include the following: . Title Sheet and Index Map . General Layout . Estimated Quantities . Typical Sections . Misc'ellane()us Details . Construction Staging/Traffic Control Plan '. 'Alignment Plans and Tabulation . Construction Plan and Profile . Drainage Plan, Details and Quantities . Turf~stablislunent Plans .. Signing and Striping Plans . Cross-Sections 6. Drainage Analysis It is assumed both County roadways will be urban design with storm sewer. An analysis of the drainage areawill be conducted to detennine any special stormwater management or ponding needs. 'This.analysis would verify the flow rates and determine what water ..' quality-and/or rate control will need to be designed into the project. This analysis would include catch" basin spacing and pipe sizing of all stoml sewer under the roadway, as well as pound outlet control structures. 7. Easements/Right-of- W ay Right-of-way and temporary easements will be necessary to complete the construction on County Road 79. It is WSB's understanding that the parcel drawings and right-of-way descriptions will be prepared by WSB and Scott County will be acquiring the necessary easements and right-of-way. 8. Permits Permits will be acquired as a part of the construction plan preparation. The cost of the permits would be paid by the City of Shakopee. . .... 9. Project-Bidding ~.O~ Upon approval of the bidding documents by the City, WSB will distribute the necessary number of plan sets to the developer for distribution. ,WSB will bill the City for the expenses ofthe plan printing. Ifrequested, WSB will sell the plan sets to prospective bidders and will not refund t4fit deposit to the unsuccessful bidders. In this case, the developer would not be billed for the plan printing. F:\WPWIM/566-06\Scope of Services. doc