HomeMy WebLinkAbout5.D.2. Aquatic Park Building Project Status and Budget Adjustment 5. 0.;1; CITY OF SHAKOPEE CONSENT MEMORANDUM To: Mayor and City Council Mark McNeill, City Administrator From: Mark Themig, Parks, Recreation, and Facilities Director Travis Karlen, Recreation Supervisor Meeting Date: December 19, 2006 Subject: Aquatic Park Building Project Status and Budget Adjustment INTRODUCTION This agenda items is intended to provide City Council an update on the budget status for the aquatic park, and to request an increase in the contingency for items included in the project budget that have been completed. DISCUSSION When City Council approved the contract for the Aquatic Park, there were several items that we were finalizing as part of the project that were beyond the contract. Since that time, we have had to authorize changes in order to comply with these items. These include: Additional Project Costs Approved Fire Alarm System (in lieu of sprinkler system) $11,402 Frost Footings $16,538 Asbestos/Hazardous Material Abatement $ 3,740 4" Water Stub for Lions Park Restrooms $ 500 New Gas Service to Lions Park Warminq House $ 3,950 Total Changes Authorized $36,130 The contingency approved by City Council was 5% of the base contract amount, $36,234. Although, the fire/security alarm system was listed as an "other project cost" in the approval documents, we had to handle the system as a change order to meet the contractor's construction schedule. A new gas service line was also needed to serve the Lions Park warming house. The service line is being installed by Center Pointe. The attached document provides the budget status. Three items that we still need to return to you with more information and more accurate cost estimates are the fence replacement, sand play structure, and additional shade structures. If you choose to implement all three additional project enhancements, the project budget shows a positive balance (under budget) of $31,101. RELATIONSHIP TO VISION F. Housekeeping Item REQUESTED ACTION Since we have utilized most of the authorized contingency, we are requesting authorization fgr a $1 0,000 inyr~ase in the contingency to reflect the cost of the fire alarm system, which was approved as a change order under the contingency. (Note: we will still return to Council with more information and cost estimates on the fence replacement, sand play structure, and additional shade structures for your consideration.) Aquatic Park Project Budget Status Building Construction 768,500.00 Pay # Description Contract Payment Change Order Status Notes 1 Payment for Contractor Services 22,013.00 Paid 2 Payment for Contractor Services 169,300.00 Paid Frost Footings 16,538 Approved Required by building. Address Block' 309 Approved MN Dept of Health Required Plan Revision 491 Approved Revised sewer connections. Glass Block Substitution 694 Approved Original colors not available. Fire Detection System 11,402 Approved In lieu of sprinkler system. 4" Water Line Stub 500 Approved Sitework Package Total 191,313.00 29,934.00 Other Project Cost Adjustments Number Description Amount Status Notes Design and Construction Admin 108,200 Approved Testing 5,000 Estimate Warming House Gas Connection 3,950 Approved Had to run new service. Landscaping and Irrigation Concession Equipment 9,934 Paid SACIWAC Charges 0 Picnic Tables and Bike Racks 14,555 Paid Footing and Foundation Permit 850 Paid Building Permit 2,244 Paid Utility Permit 206 Paid Asbestos Abatement 3,740 Paid Soil Borings 1,860 Paid Fence Replacement 40,000 Estimate Sand Play Structure 12,425 Estimate Additional Shade Structure 47,500 Estimate Other Project Costs Total 250,464.63 Summary Project Budget (Including Contingency) 1,080,000 Contract -768,500 Change Orders -29,934 Other Project Cost Adjustments -250,465 Summary Project Budget Status 31,101 12/15/2006