MEMORANDUM
To: Mayor and City Council
Mark McNeill, City Administrator
From: Jamie Polley, Parks, Recreation and Natural Resources Director
Meeting Date: May 3, 2011
Subject: Approving Plans and Specifications for Greenfield East/Park
Meadows Park and Authorization to Advertise for Bidding,
Resolution No. 7095.
INTRODUCTION
The City Council is asked to offer Resolution No. 7095, A Resolution of the City of
Shakopee Approving Plans and Specifications for Greenfield East/Park Meadows Park
and Authorize to Advertise for Bidding.
FINAL SCHEMATIC DESIGN
On March 19, 2011 the City Council approved the final schematic design for the
Greenfield East/Park Meadows Park (Attachment A) and directed staff to prepare the
plans and specifications for the park development. The final schematic design approved
by the City Council included one baseball field, one soccer field, playground, hockey
rink, pleasure skating area, sand volleyball, horseshoes and picnic shelter /warming
house. In addition the City Council directed the design to include a separate half court
basketball court and smaller open air shelter. The City has hired Bonestroo to complete
the final schematic design and develop the plans and specifications to bid the
construction of the park.
Bonestroo has contacted the City and SPUC in developing the plans and specifications
to ensure that the required permits are identified and that all fees are included and
amenities are in the acceptable locations. Upon Council approval, the plans and
specifications will be made available to bidders on May 10, 2011.
The playground construction is not part of the construction bid and staff is working with a
few consultants to design possible playground plans. The plans will be presented to the
neighborhood for input on amenities and size.
Budget
The current CIP allocation for this project is $675,000.00. The main components of this
budget include: play equipment, earthwork, trails, hockey /basketball, parking paving,
utility connections to the building pad, and improvements for one 275' youth baseball
field and one soccer field. Site furniture includes benches, pedestrian lighting and grills.
Other amenities include hockey boards and lighting, basketball court, volleyball court
and horseshoe pits. Staff time (Engineering /Public Works will be in charge of the
Construction Administration) contingency, and Trunk Water Charges (estimated) are all
included in the estimate as part of the 10% project contingency.
I 901.
PARK CIP
$675,000
PLAYGROUND
L.S.
$85,000
DESIGN & CONSTRUCTION DOCUM.
$34,940
AMENDED CIP
$555,060
CONTINGENCY
10.0%
$49,186
CONSTRUCTION BUDGET
$505,874.00
The CIP total does not include the $120,000 in costs for building construction for the
restroom /warming building. The current proposed project does not include the
construction of the park building but utility stubbing is included in the budget.
From that amended total, and 10% contingency produces a $505,874 construction bid
total. This is the number that bids must be within to stay in budget.
The estimate construction budget total is $491,862 which includes an unpaved hockey
rink with no basketball court and a 30 stall parking lot. The total does not include the
sand volleyball court, horseshoe pits or the cost of the additional small shelter. This
estimate is $14,012 under budget.
The additional items not included in the construction budget estimate to keep the park
within budget can be included in the bid as add alternates.
The add alternates, which were discussed as deduct alternates during the PRAB and
Council approvals process include:
• A) paving the hockey rink +$65,520.
• B) increasing the size of the parking lot to 60 stalls, +$44,000
• C) add sand volleyball and horseshoe pits +$10,500.
If add alternate A above is chosen and the basketball court is desired within the hockey
rink the additional cost would be $4,400. To add the separate basketball court and small
shelter, the estimated total should be increased by $69,454 ($48,000 for the shelter and
$15,140 for separate basketball court plus 10% contingency).
Additional items may be bid as add alternates in order to get a pricing on the item such
as concrete pavement for the sidewalk by the parking lot and the hockey rink surface
versus bituminous.
It is the recommendation of the consultant to bid the above alternates as deduct
alternates versus add alternates to obtain more favorable bids due to higher quantities.
Overall Park Reserve Budget
This project will serve two primary developments which were platted in 2002 and 2004,
so these residents have been "waiting" for several years. The only other park within safe
walking distance is the smaller neighborhood park on Independence, Cloverleaf Park.
Thel7th Avenue Sports Complex and Sun Path Elementary School are also within
walking distance.
In addition, we have set the proposed completion date at October, 2011. The site
grading, concrete work and seeding can be completed this year. Since it still appears to
be a favorable bidding climate, we may get good pricing from a contractor who sees this
project as one which can carry them through the late fall. Turf establishment is
estimated to take a full year so the turf areas of the park will not be usable until the
spring of 2013. Amenities such as the playground, hockey rink, pleasure rink, volleyball,
basketball and horseshoes will be usable in the spring of 2012.
The additional park CIP projects planned for 2011 include the installation of the
playground at Riverside Fields /Riverside Bluffs Park and the continuation of our park
signage installation. The park CIP project planned for 2012 is to complete the second
phase of the Riverside Fields /Riverside Bluffs Park.
Timeline
The proposed timeline for this park is to have advertisements run in the Shakopee Valley
News on May 5 and 12 and in the Construction Bulletin on the 9 and 16 The Bid
Opening is scheduled for June 1, 2011 and Award of Contract will be presented at the
June 7 City Council meeting.
REQUESTED ACTION
1. If Council concurs, offer Resolution No. 7095, A Resolution of the City of
Shakopee Approving Plans and Specifications for Greenfield East /Park Meadows
Park and Authorization to Advertise for Bidding -
2. Move to authorize the bid opening on June 1, 2011 at 2 p.m.
RESOLUTION NO. 7095
A Resolution Approving Plans and Specifications
and Ordering Advertisement For Bids
For Greenfield East/Park Meadows Park Construction
Project No. PR201:1 -1
WHEREAS, The City of Shakopee has hired Bonestroo to prepare plans and specifications
for improvements for the Greenfield East/Park Meadows Park Construction, and any appurtenant
work, and has presented such plans and specifications to the Council for approval.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF SHAKOPEE, MINNESOTA:
1. Such plans and specifications, a copy of which is on file and of record in the Office
of the City Engineer, are hereby approved.
2. The City Clerk shall prepare and cause to be inserted in the official paper and in the
Construction Bulletin an advertisement for bids upon the making of such improvement under such
approved plans and specifications. The Advertisement for Bids shall be published as required by
law.
held this
ATTEST:
City Clerk
Adopted in session of the City Council of the City of Shakopee, Minnesota,
day of , 2011.
Mayor of the City of Shakopee
ti
06
A
THRUSH STREET
r —
...:4 'h am A 444.
Baseball (12 -13 yr of
;275' @ cnterfield
1 1 250' @ fd lines i
J \ j
� 823 —
GRAVEL QUARRY (FUTURE RESIDENTIAL)
1 � ww
1
828 --
-- 822 —
._ ` 823 -
Grills
1
\ 1
1
1
/ \
\
/ \
)
/
fi S�fccer /Lacrosse
\ (225' x 330')
1
\ Soccer
\
\ 150'x270'
1
\ \
\ \
— 824
SINGLE
FAMILY
RESIDENTIAL
04-06/2011
00RVEY PJE
DRAWN 14 0
DES 0)16) Sll/MMK
APPROVED SMK
60603.600. 0000710010
-a
— \ 4 82
,/,------- — _ _ _
�/` \ \ —; i' 825 824
/ // 0S \ \�' r / / r '.. ■ / .._.
'' / / f
: /�
\ / /
\ \ S 1
// /` I ` % - - -
J/ I
/
///, /
/ //
///
SINGLE
FAMILY
RESIDENTIAL
/
¢r A
L
NWL = 817.0
HWL = 822.6
1 '826
1 --
\
\1\
\ \+,
823 ---- ....T— .- --- - --
su
1 A
w
a
l
a
SINGLE
FAMILY;
RESIDENTIAL
w
06
1
1
BZ9 1 f i ll
/
1i
CO
au
4,
2
r
SIIgLE
FAMILY
RESIDENTIAL
�'.
0 50'
2335 Highway 36 W
St. Paul, MN 55113
Ph: 651-636-4600
Fax: 651 -636 -1311
www.6onest0o.com
BONESTROO 2011
H
Ng“
a.
0
LG.I
< 1
0
J
W
L '—' -
Z
Lu
W
(7
EET NUMBER
C4 0 1
F
a s
REVISION DATE
CITY HALL
BID SITE
MINNESOTA RIVER I'
mfr-- i111�� � ■
VICINITY MAP
0 2500 5000
Horizontal Scale In Feet
GREENFIELD EAST /PARK MEADOWS PARK
CITY PROJECT NUMBER PR2011 -1
INDEX
SHEET NO. SHEET TITLE
CIVIL
G0.01 TITLE SHEET
0.01 EXISTING CONDITIONS, TEMPORARY EROSION CONTROL, AND REMOVALS
C1.01 SITE LAYOUT PLAN
C1.02 SITE PLAN ENLARGEMENT - WEST
C1.03 SITE PLAN ENLARGEMENT - EAST
C3.01 GRADING PLAN - OVERALL
0.02 GRADING PLAN - WEST
C3.03 GRADING PLAN - EAST
C4.01 SANITARY SEWER AND WATER SERVICE PLAN
C5.01 STORM SEWER PLAN
C8.01 DETAILS
C8.02 DETAILS
C8.03 DETAILS
C8.04 DETAILS
0.05 DETAILS
C8.06 DETAILS
C8.07 DETAILS
C8.08 DETAILS
I1.01 IRRIGATION PLAN
I8.01 IRRIGATION DETAILS
LANDSCAPE
L1.01
L1.02
ELECTRICAL
E0.01 ELECTRICAL LEGEND
E1.01 ELECTRICAL PLAN
FIELD SEEDING PLAN
PLANTING PLAN
JOHN J. SCHMITT
STEVEN CLAY
PATRICK HEITZMAN
MATT LEHMAN
PAMELA PUNT
JAMES THOMSON JR.
MARK McNEILL
BRUCE LONEY
MICHAEL LEEK
JAMIE POLLEY
THIS PLAN SET CONTAINS 24 SHEETS
MAYOR
COUNCILMEMBER
COUNCILMEMBER
COUNCILMEMBER
COUNCILMEMBER
CITY ATTORNEY
CITY ADMINISTRATOR
PUBLIC WORKS DIRECTOR
COMMUNITY DEVELOPMENT DIRECTOR
PARKS, RECREATION, AND
NATURAL RESOURCES DIRECTOR
I,!
,r
Bonestroo
2335 Highway 36 W
St. Paul, MN 55113
Ph: 651- 636 -4600
Fax: 651-636-1311
a
S
P
a S
NO.
www.bonestroo.com
0 BONESTROO 2011
REVISION DATE
SURVEY PJE
DRAWN
MMK
DESIGNED
01)1MMK
APPROVED 01K
PROJ. NO. 000077110010
SHEET NHMW R
G0.01
Al
8
_ _ 1 t =_,, , . c = , i , m .. = ,, , . . ,_,,_,., _ _ _ _ _ _, _ _ ,,,...fl..,, _ .2; i Em 2= m N-. ... , m = k 1 0=,,. . . :•■■•• ,
IV 11.1.1,
— -..■..._
_ `C---- _ --------------- - 822 - ------__— — _ ----- _ ------ — -- ----- - - - - -2 - —
\ \
-,-..----- "--' /A
.--- „--/..--
• \ / //
\ / / (
) \
\
..:
\
\ „...-
, )‹
7 i
1 k 7 ,nvo
1 ,s,
....., ‘ \ ■
0ETA LS.
r i
-- a ., ...... N.
z r ,-, , ,....■
/ //,'-'-',..,- . - .. r
i ,,-----,,--,•,-',....., 7 :
--, ,
/ //
. 1 .---'.. ---
.-4 .,--'`.,,.`...,.", .N \\\.„'-• 1
/ / / /1,./ / / / , ....■5 9 .r , . ° \ ''
/ r , /I
/71„.1- „..-,/ ''''--)■'\\ \
/ / / ,,,,, .--
r r ..,
. \
—.,-
i / 0 --,,, — 2 7 I k \\\ \ I /
/ ,./
/ /
/ I
//
i , 0 I, r\ _______-,-„--______
) I 1
■,,I,,
1„,/,
,,,,,,,,,, \ __________— ,...
i ii i,7
1
,i,o if,/
,,,,,
L --117
/"//8"
ir ,,Ir
\
.
I I \
II
7 \\
1
1 +
BASE AL -FIELD..
SEE
C8.OX AND
FOR I OUT AND
— 824
825
I
/
v /
\
\
H KEY RIlk,
SEE ;SHEETS )
C8.0k AND C8.0)
FORILAYO I
UT AND
DETAILS.
PLAY AREA N.I.C.
PROVIDE 1
CONCRETE RAMP I
PER DETAIL 1
X/C8.0X.
-- 822
V823 -
C8.
TO .SPE
SHELTER.
FOR SLA
IFICAT1O
SAND
VOLLEYBALL.
SEE SHEET C8.OX
FORIIAYOUT AND
GRILLS (2)ION LRII1RETE SLAB.
SEE DETAI1L x/c8.q1 AND REFER
0 SPECIFfCATIONSI.
SOCCER AND
LACROSSE
FIELDS .
SEE SHEET C3.0X
FOR GRADING.
NJ
Horizontal Scale In Feet
NO. REVISION DATE
01-06/2011
PROJ. NO. 000077110010
2335 Highway 36 W
St. Paul, MN 55113
Ph: 651-636-4600
Fax: 651-636-1311
www.bonestreo.com
BONESTROO 2011
SHEET MM.
C1.01
S
MMK
S.11/M MK
9.10