HomeMy WebLinkAbout5.A.4. Overhead Power Relocation on CSAH 17 and CSAH 42 Interchange ProjectTO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
SUBJECT: Overhead Power Relocation on CSAH 17 & CSAH 42
Interchange Project
DATE: May 3, 2011
INTRODUCTION:
BACKGROUND:
CITY OF SHAKOPEE
Memorandum
5, Pr. ti-4
c !SENT
This agenda item is to consider relocation of existing overhead or undergrounding of the existing
power lines on County State Aid Highway (CSAH) 17 & CSAH 42 on the interchange project.
On April 15, 2011, the City Council approved a Cooperative Agreement with Scott County for
the CSAH 17 & CSAH 42 interchange. Associated with this project is the relocation of existing
overhead power lines. Council has the right to require the existing power lines go underground
or be relocated overhead.
Attached to this memo is a memo from Joe Adams of Shakopee Public Utilities Commission
(SPUC) in regard to the relocation of this facility that is going to the May 2, 2011 SPUC
meeting. Mr. Adams outlines the cost alternatives for relocating overhead or undergrounding
power lines or a combination of both.
In review of the project area, the cost of undergrounding power lines is slightly more than
overhead due to the curves of the roadway alignment. Staff has met with County staff and SPUC
staff to review the alternatives.
The conclusion from all parties involved, is to underground the power lines on the north half of
the project and across C.R. 42 to a point that serves an existing house on the east side of C.R. 17.
The rest of the existing line could be relocated overhead to the south project limit. The
underground and overhead combination is shown in the attached SPU memo labeled "OH/UG
RELOCATION ".
Staff would note that in the future CSAH 17 will be widened from St. Francis Avenue to Blue
Heron Trail. CSAH 17 is being designated as a principal arterial and proposed to be a 4 -lane
divided highway. The Council will be able to consider the relocation of power lines to
underground or not with those future projects.
For this project, staff would be recommending undergrounding existing power lines from the
north project limit to across C.R. 42 to approximately 700 feet south and then allow overhead
lines to the south project limit
ALTERNATIVES:
1. Approve a motion determining that the existing overhead power lines on CSAH 17 &
CSAH 42 to be relocated shall be placed underground, from Blue Heron Trail to
approximately 700 feet south of C.R. 42, and then remain overhead to south project limits
and as shown on SPU drawing labeled "OH/UG REOCATION ".
2. Approve a motion determining that the existing overhead power lines on CSAH 17 &
CSAH 42 shall remain overhead.
3. Approve a motion determining that the existing overhead power lines on CSAH 17 &
CSAH 42 to be relocated shall be placed underground.
4. Table for additional information.
RECOMMENDATION:
Staff would recommend Alternative No. 1.
ACTION REQUESTED:
Approve a motion determining that the existing overhead power lines on CSAH 17 & CSAH 42
to be relocated shall be placed underground, from Blue Heron Trail to approximately 700 feet
south of C.R. 42, and then remain overhead to south project limits and as shown on SPU drawing
labeled "OH/UG REOCATION ".
ENGR/ 2010- PROJECTS /CSAH17- 42- INTERCHANGEIPOWER -LINES
Public Works Director
SHAKOPEE PUBLIC UTILITIES
MEMORANDUM
TO: John Crooks, Utilities Manager
FROM Joseph D. Adams, Planning & Engineering Director
SUBJECT: CR 17 &42 Interchange Improvement Project and Overhead Line. Relocation
DATE: April 28, 2011
ISSUE
Scott County, with assistance from federal funding, the SMSC and the City of Shakopee, is planning to
construct improvements to the CR 17 &42 intersection, creating an interchange, during 2011. The
improvements will consist of a unique interchange design for Scott County to improve traffic safety.
The improvements also include roadway lighting within the right of way.
These improvements will require the relocation of utility lines; including the SPU overhead three-
phase distribution mainline feeder extending throughout the project from the north end, which is just
south of Wood. Duck Trail, to the south end, which is just south of Marcia Lane, for a distance of
approximately one mile.
BACKGROUND
Shakopee Utilities' existing overhead three phase power lines along CR 17 currently extend from as
far north as Eagle Creek Boulevard /Gorman Street to CR 72 on the south end of our service territory:
The overhead main line feeder through the project area provides bulk distribution to the rural
residential properties to either side of CR 17 and also serves as a critical circuit tie as it extends east
along CR 42. The circuit is a radial feed to areas south of CR 42.
Scott County's Transportation Improvement Plan includes a project to widen CR 17 to four lanes. from
St. Francis Avenue to south of CR 42. The CR 17 &42 interchange is the first phase of improvements
planned to be constructed in this corridor. Scott County staff has told us that the funding for the
section north of CR 78 has been secured, but the remaining funding has not and they do not know if
and when the section south of CR 78 will be able to be constructed.
Per the terms of the City of Shakopee's Right of Way Management Ordinance, the Council may order
the line to be relocated underground pending notification of the cost difference between relocating the
line overhead.
DISCUSSION
Staff has reviewed the preliminary construction plans for the right of way improvements and has
determined that the estimated cost of placing the three -phase main line feeder and single -phase lateral
lines on the project underground to be approximately $165,000.
In comparison, the estimated cost to relocate the existing facilities and keep them overhead throughout
the project area is approximately $120,000.
In either case, we would also incur an additional cost to remove the existing overhead facilities at an
estimated amount of $15,000.
The funding source for the relocation of the facilities would be from electric revenues via standard
rates for the first $135,000 and via the Relocation Underground Charge fund for any excess due to
placing the facilities underground if so ordered by the Council. This is in accordance with the
Commission's relocation policy adopted in Resolution #742 Resolution Establishing a Relocation
Underground Charge dated November 3, 2003.
Some of the complications with this project that occur involve timing and the lack of availability of
enough underground cable to place the feeder underground throughout the project. We do not have
enough cable in stock and the estimated cost to purchase the required amount of cable would exceed
$1 00,000. Thus, the cable purchase would require undergoing a formal bid process where we estimate
the earliest we would have the cable delivered would be mid- to late July. Scott County plans to have
a contract awarded before then and the overhead lines will need to be adjusted or removed sooner to
allow for the construction to begin.
Another complication involves the curvature of the roadway north of and through the actual
interchange. This curvature makes for a difficult overhead design and more involved than normal
overhead construction that requires a guy wire and anchor on nearly every pole. When future planned
roadway and trail improvements are constructed, the poles and guy wires would undoubtedly interfere
with the trail and that section of the feeder would most likely have to be relocated underground at that
time if not now.
The area south of CR 42 is "cleaner" in the sense it is straight and Scott County advises that the right
of way area they have acquired in this area is sufficient for the future roadway and trail construction
without the need to relocate our facilities a second time. Additionally, the east side of the right of way
is clear of obstacles now and will not be disturbed during construction of the current project. We have
the material in stock to construct this section of the line overhead and could begin work as soon as we
are issued a permit
Due to these circumstances, it may make the most sense for the section of the feeder along CR 17 north
the interchange with CR 42 to be relocated underground and the section south of CR 42 to be relocated
overhead. We estimate the cost of that combination of underground and overhead construction to be
approximately $155,000.
RECOMMENDATION
Staff recommends the Commission accept the estimated costs and direct staff to forward them to the
Council to aid the Council in making their determination under the City's Right of Way Management
Ordinance whether or not to order the facilities, or a portion there of, to be relocated underground.
REQUESTED ACTION
Staff requests the Commission adopt the recommended action.
it
11TH AVt
1
CA N
V 6A1w0 AN
160
8 1 7 ! 6 I 5
OA.
O•W10N A f
WOCLICVCA
1• AK Cie 4.}
WAyA
calm I
•
4 ! 3
2
•
OVER HEAD
ELECTRIC LINES
.a
04.26.11
••.-A. a.
SIIACMCC AVh (C VIILIPICS
t)vCFMAD PRDURr 1►1 .WRSCCACC RD
SHAKOPEEE PUBLIC UTILITIES
D
C
4-
8
bk
f
VOL
•
,%
CO
_ tom.. ..
OUCX
OH RE 6OCA TI JN
REMOVAL ONLY°
W
X REMOVAL OF FACILITY
rlt
C> v
- MATCH
Pig
CC RD ITS.D
SH. XOPEE PUBLIC UIIIMTIES
Waeat mw
C) a
I !
m
rn
4-
N
q CO 0 0
8 I 7 6 5 4 I 3 I 2 I 1
ALL UG RELOCATION _j_I
_
8 I 7 I 6 I _ 5 '4" 4 I 3 I 2 I 1
\ Jy
•
.-
....„...:-.-„,
. .\,% \
�lj 1 - �' --
/
Olt
t'
I1W�
,
1 , `' , 1 j 1 90 UG •
1
It • \ %/
500 MCM UG
X17,
I I
i
-Q - - -__
fie-
• CD RD 17 .2 UG PROPOSED
SHAKOPEE PUBLIC UlILmES
•
.�
O 1 ,
m
•
D I co I n 0
N
8 I 7 I 6 I 5 4 3 I 2 I 1
'a
\ : OH RELOCATION
' te _ OH INSTALLATIO
co
IV
_
8 7 I 6 I 5 4 1 3 I 2 I 1
--
1 �
X REMOVAL OF FACILITY
\ ° INSTALL POINT OF INTREST
-.
1
\ O
; ; �
C:=1:
.,
r (
f
V. ..
I
0
0
o
/
.,
S
` 4 I ,
0
I
i.� 1
a° -I-a 7 p. p
_ -.—. ;'
,
IQ
1 6c,
I F
.--.-
CG 4D:Jd t?
SHAKOPEE PUBLIC UT41TmES
MY
7-2?1
0
9i1
D I m C) 0
Ni
8 1 7 I 6 1 5 T 4 I 3 I 2 I 1
i t
—
N
8 I 7 I 6 I 5 .L 4 I 3 ) 2 I 1
ILIA M1717N Mt OH / UG RELOCATION
— �
1
1
. I' a •\ r
111 SW
4t / i . 1 1
, �
'
0102
500 M UG
•
4 ,.
•,..,... i t
I o
1
.•
I e
' ." CO pp 17 t ;2
SHAKOPEE PIEUC MUTES
AnY
S I
�•
wo
..�.
30.
,. an
D I CO
C) 0