HomeMy WebLinkAbout4.A.2. Request of Chard Tiling and Excavating, Inc. for Extending Work Hours on CR 69 Project �f. A. a.
CITY OF SHAKOPEE � �, � �, �
Memorandum � � � � � i;�����
TO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
SUBJECT: Request of Chard Tiling and Excavating Inc. for Extending Work Hours
on C.R. 69 Project
DATE: April 17, 2012
INTRODUCTION:
Chard Tiling and Excavating Inc., the contractor for the C.R. 69 Reconstruction Project,
has requested that City Code Sec. 10.60, Noise Elimination and Noise Prevention, Subd.
3, Hourly Restrictions on Certain Operations, be suspended for certain work hours.
BACKGROUND:
The above named section of the City Code restricts the hours of operation from 7:00
A.M. to 10:00 P.M. on weekdays, and from 9:00 A.M. to 9:00 P.M. on weekends and
holidays.
Chard Tiling and Excavating, Inc. is requesting a suspension on the hours to allow for
work on Saturdays, to start at 7:00 A.M. from 8:00 A.M., for the project duration in 2012;
and to allow the Contractor from April 20 to May 2" to work 24 hours a day to
rehabilitate the Railroad Bridge over CSAH 69.
This request is being made to help expedite the work and meet the schedule for the C.R.
69 Project and to restore service to Rahr Malting as soon as possible.
Staff would recommend that if the suspension of hours is ganted, that the approval is
subject to the following conditions:
1. Approval is contingent upon minimizing noise exposure.
2. If property owner complaints are received by the City, the suspension can be revoked
at the discretion of the City Engineer.
If Council approves the suspension, a public notice to meet the City Code requirements
and notice such as a news release would be placed in the Shakopee Valley News.
ALTERNATIVES:
1. Approve the suspension of City Code Sec. 10.60, Noise Elimination and Noise
Prevention, Subd. 3, Hourly Restrictions on Certain Operations, per this memo, and
direct staff to publish notice of the suspension terms with the conditions as
recommended by staff.
2. Approve the suspension of City Code Sec. 10.60, Noise Elimination and Noise
Prevention, Subd. 3, Hourly Restrictions on Certain Operations, for some other period
of time as determined appropriate by the City Council, and direct staff to publish
notice of the suspension terms.
3. Do not approve the suspension of City Code Sec. 10.60, Noise Elimination and Noise
Prevention, Subd. 3, Hourly Restrictions on Certain Operations, D.
RECOMMENDATION:
Staff recommends Alternative No. 1.
ACTION REQUESTED:
Offer a motion approving a suspension of City Code Sec. 10.60, Noise Elimination and
Noise Prevention, Subd. 3, Hourly Restrictions on Certain Operations, D, allowing work
on Saturdays starting at 7:00 A.M., allowing work 24 hours a day from April 20` to May
2 2012, and directing staff to publish notice of the suspension terms with the conditions
as recommended by staff.
ruce Lone .E.
Public Works Director
ENGR'_OL'-PROJEC"TS CSAH69 � WORD��EXTFND-WORKING-HOURS
f� f r r � �� r �j"
_ C_-i2Gt.iCl �� L��'Gj � ���CLCTGL�LI2C�, ` 1t2�.
r./ sJ
�iHLEYAGGREGATES 26239 STATE H1NY 2 BEI��E P�aiNE, MN 56011
3�?�AL P.`-t41Ni� & G�r'�RC �'�NC�?�.TE {9'S�if373 ' Fr-X {952}49�
Date: 13 Apr 2012
To: City of Shakopee
Name: Bruce Loney
Title: Public Works SuperinCendent
Address: 475 Gorman St, Shakopee, MN
Re: Extended working hours
Cc: Leroy Chard
Job File
Bruce,
This letter is to request additional working hours for the CSAH 69 project. As you now this project has
some time constrains attached to it that we feel may need extended hours to complete, therefore 1 would
like to ask for a couple differing working hour estensions.
o The first addresses the reconditioning of the rail road bridges that cross CSAH 69. Rahr Malting has
hired Edward Kreamer and Sons to complete the upper portion of the bridge which Rahr actually
owns. And at the same time they are doing that we will have a subcontractor doing the
reconditioning of the steel structure itself. Needless to say this will take a lot of time for both
contractors and will need to happen within the constraints of the road closure which is scheduled to
happen from the 20` of Apr to the 2" of May. Attached you will find a letter from our subcontractor
spelling out the specifics of their schedule, but I would request that we have the ability to run 24
hours a day during the road closure, so if the weather comes into play we still have the ability to
continue working around the clock.
o The second request is that we would have the ability to start work at 7:OOam on the Saturdays that
fall outside the road closure.
I would appreciate it if you could present this to council and that they would indicate which if not all the
above items are acceptable to them.
Sincerely,
Rich Schmid
Project Manager
Chard Tiling & Excavating, Inc.
Office 952-8T-6152
RAINBOIN
INC.
u.� e4�'ni aerc�aruNr7v E�PZO��a
7324 - 36th avenue nortt�
• r�inneapolis, min�esota
55427
(763) 535-4041
Commercial & lndustrial Painbng
APRIL, 12TH, 2012
Chard Tiling & Exca�ating, Inc.
26239 State Highway z5
Beile Plaine, MN 56011
Attn: Rich 5chmid
Re: Working Hours far CR 69 Project
Dear Rich:
Rainbow inc. would like to request additional project working hours, ha5ed on railroad schedule and
project changes. Rainbow will be working in eonjunction with the railroads contractor to complete
abrasive blasting and painting of the entire Bridge #6885.
Rainbow will ha�e a schedule as faliows, Aprii 20`�', 21st and 2�" we wilf be working single shifts with
working hours of 7:�0 arn to 7:00 pm. Beginning on Monday the 23 of April we will be running two 12
hour shifts round the ciock until Thursday the 26 Friday ihe 27`" of April we will run a single 12 hour
shift and turn the bridge o�er to the railroads contractor to complete the remainder of the bridge rehab
items.
In �losing working this type of schedule will allow Rainbaw, the railroads contractor and Scott County to
compfete this rehat�ilitation in a timely, safe and quality conscious rnanner.
Sincerely,
� �� �C�
J
Mike DeBuhr
.
Eawaao
KRAEMER
& SONS,
INC.
April 13` 2012 . , .
Mr. Bruce Loney
City of Shakopee
Public Works Director
129 Holmes Street
Shakopee, MN 55379
Project Title: CSAH 69
Project Number: CP 69-02/SAP70-669-002
EKS Job Number: 241207
RE: Extended Work Hours
Bruce,
EKS is requesting extended work hours between Apri120` and May 2 we are
requesting a variance to work 24 hours per day Monday through Friday and from
7:OOam-S:OOpm on Saturday and Sunday.
The extended hours are being requested as a contingency if work items take longer
than anticipated or if inclement weather delays our progress.
Our priority is to complete bridge wark in conjunction with the painting contractor in
the time allotted by Rahr Malting.
Please feel free to give me a call with any questions/comments.
Sincerely,
Zach Pontzer
-Project Manager
EDWARD KRAEMER & SONS, INC.