TO: Mayor and City Council
FROM: Mike Hullander, Public Works Superintendent
DATE: 08/18/2015
SUBJECT: 2015 Trail Reconstruction (A,E)
Action Sought
Move to accept the low quote and authorize staff to contract with Northwest
Asphalt, Inc. for the 2015 Trail Reconstruction Project for the price of$59,995.00.
The funding for this project to be expended from the Internal Service Park Asset
Fund.
Background
Public Works staff budgeted $60,000.00 in the 2015 Internal Service Park Asset
Fund for park trail reclamation and bituminous pavement reconstruction. The 2015
project will complete the trail re-paving in the Lions Park area. Staff is
recommending to reclaim (grind-up) the existing 6 foot trail from 10th Ave. to the
Youth Building, add needed class 5 material, and re-pave the trail to City Standards
(8 foot). Staff is also recommending to reclaim and re-pave the trail section from
Vierling Dr. to Fuller St. The pedestrian ramps will also be reconstructed to current
ADA standards. Three quotes were received for this project as follows: Bituminous
Roadways, Inc. - $75,266.00, Plehal Blacktopping, Inc. - $68,315.50 and Northwest
Asphalt, Inc. - $59,995.00.
Recommendation
Staff recommends approval of 2015 Trail Reconstruction Project.
Budget Impact
Funding is to be expended from the Internal Service Park Asset Fund.
Relationship to Vision
A. Keep Shakopee a safe and healthy community where residents can pursue active
and quality lifestyles.
E. Deliver effective and efficient public services by a staff of well-trained caring
and professional employees.
Requested Action
Move to accept the low quote and authorize staff to contract with Northwest
Asphalt, Inc. for the 2015 Trail Reconstruction Project for the price of$59,995.00.
The funding for this project to be expended from the Internal Service Park Asset
Fund.
Attachments: 2015 Trail Reconstruction
rrrrn
NORTHWEST NORTHWEST
Excavating, Utilities & Paving
1451 Stagecoach Road, Shakopee, MN. 55379 Phone (952) 445-1003
Fax (952) 445-1056
2015 Trail Improvements
Shakopee, MN
ITEM UNIT QTY Per Unit Total Cost
1 Mobilization LS 1 $2,750.00 $2,750.00
2 Reclaim Bituminous SY 2780 $1.65 $4,587.00
3 Class V TON 60 $20.00 $1,200.00
4 Dirtwork/Widening Trail SY 240 $10.00 $2,400.00
6 Pave 2.5" SY 3340 $10.70 $35,738.00
7 Concrete Ped ramps 6" SF 415 $14.00 $5,810.00
8 Truckated Domes 2"x2' EA 15 5264.00 $3,960.00
9 Restoration (topsoil, seed, mulch) LS 1 $3,550.00 53,550.00
10 TOTAL $59,995.00