City of Shakopee Caplt.llmproyement Program 2009.2014 4.
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Interfund Loan Payback 1,396,250
Year Added to CIP: 2007
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction
Improvements
Engineering/Admin. 227,500 230,250 232,500 234,250 235,500 236,250
Total 227,500 230,250 232,500 234,250 235,500 236,250
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 227,500 230,250 232,500 234,250 235,500 236,250
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 227,500 230,250 232,500 234,250 235,500 236,250
Description
The Park Reserve is paying back a $2,000,000 interfund loan at 5% interest over 10 years.
"'\. ~ (......""'- .. .
I -,-.. - I ":::_.. - ... ... .... II ..... JustificatIOn
,. "'--~'41~' At';E~.:,~... .,:::1''''''"''''.,p,,~ .... \. The interfund loan was transfered into the Park Reserve at the time of the Huber Park redevelopment.
..a'lrtl' . j1 '''1i..t'1it'7'') 11'"....:1 '\....r~, F
r.. 11..'1' L ""'I'" '~r,.j.. ( .... I'...'...,.~ 'I ";;if. I
L!". ;] .u.lr<."'''-. "':3. -'v'~
~;!;;: Lt..ii. ~;I' '.".~j.;ji~~$;G~:'t'lJ~:.~.."'..\.'~.:f~ ~~ye~ ~~:~~~t~etermi.n,e is they.will require a 5 year pay~ack at 5% or i~ the time or interest r~te will be
!:- J'~ '~~~"'IJf' ~~'<f<. \~~'~~J~;I, adjusted to allow for additional projects to take place. ~t~ff IS recommendl~g that the loan be paid back at 5%
r!!\,...i~~..~! { '.."T..'.,..~ :::1,1 over 10 years. The Xcel. Agreement payments were a~tlclpat~d to pay the In~erfund loan payment, how~ver,
:Ct' 5\:; Y._, .. I r . j -t( \..{::,l;' the Xcel payments end In 2010 and the Park Reserve IS required to pay the Interfund loan payment until 2012,
, I' "'{~%'" I - - ...~.
::~. )'c--:-j Operatina Costs
'1\ (,
,,"' "', \:01
t::i~-\':.. ..I
l ;;.'
l t' 'I
____---1
1
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley & Bill Egan Improvements Park Signage 65,000
Year Added to CIP: 2006
A. Expenditure Items: 2009 2010 2011 2012 2013 2014 +
Land & ROW
Construction
Improvements 8,000 8,000 10,000 8,000 9,000 22,000
Engineering/Admin.
Total 8,000 10,000 8,000 9,000 22,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 8,000 8,000 10,000 8,000 9,000 22,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 8,000 8,000 10,000 8,000 9,000 22,000
Description
This project provides funding for designing and installing new park signs for all park locations,
Improvements, $65,000 (Park Reserve):
Neighborhood Park Signs, 20 @ $2,500 ea = $50,000
""\. ~. (',....... Community Park Signs, 4 @ $5,000 ea = $20,000
, -',;.-... -- J~~",__ .".... '" _ ,/ '" '"
, " ",..1'~~\ -""'" .... JustIfication
:'f" .' l):U\....7~:::.:;:d;:::.:+"'~~ This project would standardize signing for all parks and help create uniform identity for park areas.
tII-c" J1." ~2-l::Jsj '~
..( ,J ~ ,,"if! r~'~ ,.'; '~\"'v:";';;;;:',&i'- ~r~ YT Other Comments
- ~~l. ~ "r "cf",'iitv t. I Woek w,"1d be ,,",d;oated with P"blie Woek, aod Eog;o","ng
L . ;~. , ,~1; '1v-~- ':>\ \;11
'" '; ,> -,,!rqdifJii, ~:!~'),;:\vJ OperatinQ Costs
::~ttr;;~:ir' I J __r 1- I ':.~'9 (included in general park maintenance)
,c~"-'T'I
I.", 1:L l;;,
r-:L-~::" J
;;J
"-~-^-~:
I
2
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Park Development Greenfield/Park Meadows Community 600,000
Year Added to CIP: 2004 Park
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 560,000
Improvements
Engineering/Admin. 25% 10,000 30,000
Total 10,000 30,000 -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 10,000 590,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 10,000 590,000 -
Description
: This project would develop the east park in the Greenfield Development, which is adjoined by 8 acres from Park
I Meadows, for a total of 13 acres,
Construction: $600,000 (Park Reserve)
Play equipment $50,000, 2-260' Ball fields $180,000,1 hockey/BB rink w light $180,000,
Lighting $30,000, Planting, $20,000, earthwork $30,000, trails and walks $30,000, ball field irrigation $30,000
total $550,000
Engineering/Admin: Design and construction administration of park development (25% of total project costs, which
includes additional costs for design of building) (Park Reserve)
This park will be built in phases: 2009 - Design, 2010 - Phase I construction, 2011 - Phase II Construction
I including parking area $75,000 and prefab restroom/warming building $250,000,
I Justification
I This provides for development of the second park in the Greenfield development and neighboring developments to
I the east.
. Other Comments
Actual park amenities would be determined in planning process with residents. This park will likely serve as a
: location for organized activities such as playground programs and youth sports.
Operating Costs
_ Estimated yearly operating costs: Labor $15,000 + Equip/Supplies $10,000 = $25,000
,~
3
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Park Development Riverside Bluffs Community Park 800,000
Year Added to CIP: 2005
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 400,000 200,000
Improvements 200,000
Engineering/Admin. -
Total 200,000 400,000 200,000 -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 200,000 400,000 200,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 200,000 400,000 200,000
Description
This project would develop the park that will serve Riverside Fields, Riverside Bluffs and Ridge Creek developments, The park
approximately 8-10 acres (ridge creek has not yet been preliminary platted) for a total cost of $600,000 in 2010 & 2011.
Play equipment $550000, 1 combined hockeyfBB rink w light $180,000
Lighting $30,000, Planting, $20,000, earthwork $40,000, trails and walks $20,000 and prefab
restroom building $75,000, medium program gazebo $50,000, parking, $75,000, total
$540,000
Engineering/Admin: Design and construction administration of park development (10% of total project costs, which includes
additional costs for design of building staking, testing, etc.) (Park Reserve)
This park will be built in phases: 2010= Playground design and installation, 2011 - Phase I construction, 2012 - Phase 1/
Construction.
Justification
This provides for development of a park in the Riverside Fields, Riverside Bluffs and Ridge Creek developments, (also serving
Glacier Estates and Premier/Zotschke developments. Riverside Fields is nearing fully developed, Riverside Bluffs is nearing
Final Plat and Ridge Creek is in the Preliminary Plat process,
Other Comments
Actual park amenities would be determined in planning process with residents, This park will likely serve as a location for
organized activities such as playground and summer youth programs and youth sports.
Operatina Costs
Estimated yearly operating costs: Labor $15,000 + Equip/Supplies $10,000 = $25,000
4
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Tunnel Fencing & Park Development Shutrop Community Park 1,259,000
Year Added to CIP: 2006
A Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 1,000,000
Improvements 9,000
Engineering/Admin. - 250,000
Total 9,000 - - - 1,250,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 9,000 1,250,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk -
Tax Levy
Total 9,000 - - 1,250,000
Description
This project would provide funding for future development. The design and construction of this park would
take place beyond 2014,
Construction: A trail will be installed under CSAH 21 to access Shutrop Park, The County is funding the
tunnel, council approved upgrading the fencing on the tunnel ($9,000). Develop park area, $1,000,000 (Park
Reserve)
Design/Admin, $250,000: (25% of project costs) (Park Reserve) total $1,250,000
Justification
This will provide funding for development of Shutrop Park in the future.
Other Comments
The land adjacent to the current property owned by the City has been obtained by the Sioux Community and
is therefore not available for purchase in the future, The plans to have a large park including passive
recreation and larger group picnic facilities, shelters, rest rooms, parking, trails and play equipment will be
reevaluated,
Operatina Costs
Unknown at this time - dependent on scope of development.
5
City of Shakopee Capital Improvement Program 2009. 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Special Facility Construction Off-Leash Dog Area 44,000
Year Added to CIP: 2006
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 44,000
Improvements
Engineering/Admin,
Total 44,000 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 24,000
Grants (specify)
Donations (specify) 20,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 44,000 - - -
Description
This project creates the first off-leash dog area for Shakopee. Potential sites include MnDot parcel
43 near the Town Square Mall, parkland west of ParcellS, open space in Southbridge, Xeel
~~~ energy property attached to Quarry Lake.
ti!!t~-:::. .. ..:\(< Construction:
<I .,,4~. ~t ~" .'til--a-;}.f./." .......7...' r...~,,"'-:1 j"..... ""-,0.":'""
Z".\..I ~If( '- ~ I 2010 - Site TBD, $44,000 for fencing, gates and trails.
/' ",. ..., '. (; .~!E' ;!;'?;,.',.,..._ ...,..J...J:,:::) '. " _'"
r' IE, ,~':;"jl."'NjtM~~ ",...-' ',.' ~J'
-"'*'f~'d~,;~:"--;',., ..' .;.~..
~".. ~tll:r 'T' ...,71'l'I' Justification
l., "i:', .... ;1,.." ~1"" .' '\0J../ I
"I.,J,g~rl tl ....., ~ " "I This project responds to resident requests for a legal place to run dogs off leash,
"';r... ''''" .!.. f-' 'T;:'\,.
.- (.11.. J-"n -'
(~,~r -' .- ~ ~ Other Comments
Most likely would begin with a single site and evaluate need for additional sites in the future,
I;'; \~ I
r"'-~;I- Ol>erating Costs
__.._.,-...1 $500/site per year.
6
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley, Bruce Loney Trail Connection Savannah Oaks Southbridge Trail 100,00U
Year Added to CIP: 2008
A. Ex enditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 100,000
Improvements
Engineering/Admin,
Total - 100,000 -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 100,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 100,000 - -
Description
A trail to connect Oxford Dr N to Southbridge Parkway. The trail will begin in Savannah Oaks Park where a
portion of the trail is constructed and cross the wetlands connecting to South bridge Parkway.
Justification
, The trail would allow the residents of Southbridge a safer, convienient access to Savannah Oaks
Neighborhood Parks.
Other Comments
The trail construction may possibly require a boardwalk over the wetland area.
Operating Costs
7
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Restroom/Warming House Building Westminster Restroom/Warming House 200,000
Year Added to CIP: 2004 Park
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction
Improvements 200,000
Engineering/Admin, 25%
Total - 200,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - 200,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
T ax Levy
Total 200,000
8
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Ball Field Construction & Lighting Tahpah Park Improvements 6'16,500
Year Added to CIP: 2007
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 172609
Improvements 363,478
Eng ineering/ Admin. - 25891 54,522 -
Total - 198,500 4'18,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 98500 218,000
Grants (specify) 100000
Donations (specify) 200,000
State Aid
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - 198,500 4'18,000 -
Description
2012- Baseball field Construction, $172,609+10% and 5% D&CA=$198,500The City will apply for a grant from Baseball of
America in the amount of $100,000, (Anticipates donation of labor or in house labor for some work,)
2013- Light fields 7 and 8 $418,000. ($200,000 anticipated to come from donations)
Justification
This project would complete development of Tahpah Park with an additional baseball field in 2012, The additional baseball
field is outlined in the Parks, Trails and Open Space Comprehensive Plan
Other Comments
The project for 2012 is contingent on funding from a grant application to Baseball America
Operatin" Costs
The estimated operating costs for additional baseball field is approximately $2,000 per year, Lighting two softball fields with
lights would add $800 per year for operating 4 nights per week.
9
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Improvement Riverview Park Parking Lot 78,750
Year Added to CIP: 2006
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 75,000
Improvements
Engineering/Admin. 3,750
Total - 78,750
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 78,750
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - 78,750 -
Description
This project would provide funding for a parking lot in Riverview Park and provide accessible trail
connections.,
Construction: $75,000 (Park Reserve)
Engineering/Admin: Design and construction of park development, (5% of project costs) (Park Reserve)
Justification
On street parking is limited, and users currently park on the grass.
Other Comments
Operatinq Costs
10
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Field Lighting 17th Avenue Sports Complex Field Lighting 330,000
Year Added to CIP: 2006
A Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction
Improvements 330,000
Engineering/Admin.
Total - 330,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 230,000
Grants (specify) I
Donations (specify) 100,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
T ax Levy
Total - - - 330,000
Description
Field Lighting, $300,000.
Justification
This project provides for field lighting for the Soccer Complex to allow evening
play. The park building was designed to accomodate future lighting and
includes conduit stubs.
Other Comments
Operating Costs
Estimated operating costs: $5,000
11
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Park Development Quarry Lake Park and Special Use Facility 1,400,000
Year Added to CIP: 2005
A. Expenditure Items: 2009 2010 2011 2012 2013 2014 & Beyond
Land & ROW
Construction 100,000 762,000
Improvements 100,000 258,000
Engineering/Admin. 180,000
Total 200,000 1,200,OQO
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 100,000 730,350
Grants (specify) 269,650
Donations (specify) 100,000 200,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - 200,000 1,200,000
Description
This project would provide funding for acquisition of the restored Aggregate Industries quarry site, and funding
for future development.
2013 - City crews. will continue with site cleanup and begin grading. final design and trail and parking lot
construction from 2004 Concept Plan will begin when public access is obtained.
2014 & Beyond or when public axcess is obtained. Cont. const. (2004 Concept Plan cost est. w/ minor
adjust.): $1,200,000 (Donations & Grants)
Infrastructure (bridge, roads, parking, utilities)- $430,000
Trails (bituminous and boardwalk) - $500,350
Plantings (shoreline and site) - $124,000
Site Amenities (picnic tables, grills, fencing, signage, etc.) - $145,650
Engineering/Admin: Design and const. administration of improvements (25%)
Donation: Bituminous Roadways contribution for roadway construction to provide secondary access to plant.
Justification
This project would develop the facility as recreational amenity for the city. If possible work would be
coordinated with the Watershed District's plans for channel improvements,
Other Comments
Funding sources include grants and partnerships with committee members. $30,000 Xcel grant, $10,000
Polaris grant in 2006. All costs listed are estimates, Depending on public access and funding this park will be
built in phases.
Operatin~ Costs
Costs would depend on scope of development.
12
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Park Redevelopment Huber Park Riverbank Stabilization 2,400,000
Year Added to CIP: 2004
A. Expenditure Items: 2009 2010 2011 2012 2013 2014 & Beyond
Land & ROW
Construction 2,400,000
Improvements
Engineering/Admin.
Total - 2,400,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 500,000
Grants (specify) 1,900,000
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
$torm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - 2,400,000
Description
Stabilization of river bank along Huber Park,
Beyond 2014 - Construction
Justification
This project completes the redevelopment of Huber Park by stabilizing the river bank, constructing river overlooks, and
reconstructing trail segments.
Other Comments
OperatlnQ Costs
$500/year.
13
City of Shakopee Capital Improvement Program 2009" 2014
Project Manager Project Type: Project Title: Total Project Cost:
Jamie Polley Park and Trail Development Southbridge Area Park Development 1,4'1O,3'IU
Year Added to CIP: 2004
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW 368,000
Construction 1,042,310
Improvements
Engineering/Admin. - -
Total - 1,4'10,310
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 1,042,310
Grants (specify)
Donations (specify)
State Aid
Assessments 368,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
T ax Levy
Total - - '1,4'\ 0,3'1 0
Description
This project would develop several park areas in the Southbridge Development, including the MNDOT 75 parcel.
2009- Parcel 75 Aquisition in process along with planning for CSAH 21
2014 - Trail from Cambridge Road to Whitehall Road along gas easement to connect to school trail, 2600LF @
$27/LF=70,200+10% (inflation per year), $77,200+5% Design/Admin, $3860, $81,060 (Park Reserve)
2014 - Park at Southbridge Pkwy: Hockey/basketball w light 180,000, shade structure 30,000, Water ftn & water service
15,000 and Plantings 20,000, concrete and trails, $20,000, earthwork, 30,000, site furniture 15,000, = $310,000 plus 25%
design and admin $77,500, total $387,500 (Park Reserve)
2014 - Construction: MNDOT 75 parcel 2 mi trail @ 27/LF=285,000, 1 small picnic shelter, $30,000, lights at kiosk 14,000
total site furn and interp sign age 30,000, sod and plant resto $25,000, 25 space parking @$75,OOO= $459,000+plus 25%
design and admin, $114,750 = $573,750 (Park Reserve)
2010 - Parcel 75 Assessments Council directed assessments on Parcel 75 to be paid from the Park Reserve. Council will
decide when or if these fees will be paid,
Justification
In 2001, the City worked with residents to prepare a master plan for the Southbridge area, The improvements identified in
this project are a portion of the overall master plan
Other Comments
Estimated cost for total development of the system based on the master plan is $3 million (2001),
Operatina Costs
Estimated costs: Labor $50,000 + Equip/Supplies $25,000 = $75,000 (when fully developed)
14
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Community Park Project Title: Total Project Cost:
Jamie Polley Improvements Lions Park Improvements '100,000
Year Added to CIP: 2006 Update
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction
Improvements 75,000
Engineering/Admin. 25,000
Total - 100,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 64,000
Grants (specify)
Donations (specify) 36,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
T ax Levy
Total - - 100,000
Description
Lions Club has plans for continued improvements in Lions Park.
Additional hockey rink $100,000 -(donation of concrete cost and labor, $36,000) 25% design,Admin (Hockey
Association Requested to postpone 2nd outdoor sheet until a firm decision has been made about the
construction of a 2nd indoor sheet of ice),
Justification
Projects have been identified by Lions Club and Youth Hockey Association, and would serve park users.
Other Comments
Proceeds from Lions Park land sale in 2003 ($41,000) have been deposited into Park Reserve fund and
should be used to help fund future park improvements, Lions requested use of $5,000 in 2007 for restroom
upgrades, $4,500 in 2008 for irrigation at Tahpah Park & $6,000 for Ice Arena in 2009,
Operatin~ Costs
Estimated year operating costs: $1,000,
15
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Improvements O'Dowd Lake Community Park Improvements 396,000
Year Added to CIP: 2000
A. Expenditure Items: 2009 2010 2011 2012 2013 20'14
Land & ROW
Construction 316,800
Improvements
Engineering/Admin, - - 79,200
Total - - 396,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - 396,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 396,000
Description
This project would develop O'Dowd Lake Park with larger picnic shelters and parking,
Construction: $396,000 (Park Reserve)
Two large picnic shelters 150,000, Site furniture $20,000, 50 car parking @ $3,000/space==$146,800,
total $316,800 + 25% Design/Admin, $79,200: $396,000 (Pa~k Reserve)
Justification
This community park is located on the shores of O'Dowd Lake. The city has made improvements at the site
over time inclUding trails, canoe launch, retaining walls, fishing pier, and stairways.
The city built a temporary parking area and restricted vehicle traffic in 2003.
Other Comments
Operating Costs
Estimated yearly operating costs: Labor $10,000 + Equip/Supplies $5,000 == $15,000
16
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Trail Construction CR 79 Trail 275,000
Year Added to CIP: 2000
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW 100,000
Construction 150,000
Improvements
Engineering/Admin, 25,000
Total 275,000
B. Funding Source:
General Fund
Capita/Improvement Funds
Park Reserve Fund 275,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 275,000
Description
This project will design and construct a segment of the trail from CR 78 to O'Dowd Lake Park.
Land & ROW: Acquire needed easements, $100,000 (Park Reserve)
Construction: $150,000 (Park Reserve)
Engineering/Admin: Design and construction of trail (10% of total project costs) (Park Reserve)
Justification
Segment is identified on the City's trail plan as a key connection to future O'Dowd Park improvements.
Other Comments
Scott County has assumed responsibility for the regional trail connection along CR 79 from 169 to CR 78.
Portions of this trail was constructed in 2005, but the timeline for the remaining conneciton to CR 78 is
dependent on additional funding.
Operatin~ Costs
Estimated yearly operating costs: $1,000
17
City of Shakopee Capital Improvement Program 2009.2014
Project Manager Project Type: Trail Project Title: Total Project Cost:
To Be Determined Greenway Development Prior Lake/Spring Lake Greenway '157,000
Year Added to CIP: 2002 Corridor
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW 100,000
Construction 50,000
Improvements
Engineering/Admin. 7,500
Total '157,500
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 157,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
T ax Levy
Total 157,000
Description
This project would provide for greenway acquisition and improvements along the Prior Lake/Spring Lake
outlet channel, most likely south of CR 16,
Construction: Greenway improvements, $50,000 (Park Reserve)
Land & ROW: Acquisition of greenway corridor, $100,000 (Park Reserve)
Engineering/Admin: Design and construction of improvements (5% of project costs) (Park Reserve)
Justification
This project would provide the greenway connection along the Prior Lake - Spring Lake outlet channel and
connect with potential greenway, open space, and park development east of Dean Lakes.
Other Comments
Greenway grants may supplement funding.
OperatinQ Costs
Unknown at this time - dependent on scope of development.
18
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park and Trail Development Premier/Horizon Heights 236,250
Year Added to CIP: 2000
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 225,000
Improvements
Engineering/Admin, (5%) 11250
Total - 236,250
B. Funding Source:
General Fund '-'
Capital Improvement Funds
Park Reserve Fund 236,250
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - 236,250
Description
This project would construct trails and park amenities in the Premier/Horizon Heights developments.
Construction: $225,000 (Park Reserve)
Park and trail development
Engineering/Admin: Design and construction of park development, (5% of total project costs) (Park Reserve)
Justification
>. The city has undeveloped open space in this area that could accommodate trails and small park amenities.
.. Proposed improvements have been part of the CIP for many years.
,I Ou..,Commen"
Actual park amenities would be determined in planning process with residents. Future park dedications from
J adjacent undeveloped land may be better suited for active recreational use.
Operatin~ Costs
Unknown at this time - dependent on scope of development.
19
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Killarney Hills Neighborhood Park 420,000
Year Added to CIP: 2000
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW
Construction 336,000
Improvements
Engineering/Admin, - 84,000
Total - 420,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - - 420,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 420,000
Description
This project would develop the Kilarney Hills park. The park is approximately 3 acres.
Construction: $336,000 (Park Reserve)
Play equipment, courts, trails, picnic area
Engineering/Admin: Design and construction of park development (25% of total project costs) (Park Reserve)
Justification
This provides for development of a park in the Killarney Hills subdivision, which would also serve future
development north of 17th Avenue, If 17th Avenue is built out sooner and development occurs in the area,
this park may need to be moved up.
Other Comments
Actual park amenities would be determined in planning process with residents,
Qperatinq Costs
Unknown at this time - dependent on scope of development.
20
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Community Sports Complex 1,050,000
Year Added to CIP: 2006
A. Expenditure Items: 2009 2010 2011 2012 2013 2014 +
Land & ROW
Construction 1,000,000
Improvements
Engineering/Admin. 50,000
Total - - - - 1,050,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 1,050,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - 1,050,000
Description
This project would provide funding for a future sports complex,
Construction: $1,000,000 (Park Reserve)
.... t..... Engineering/Admin: Design and construction of park development, (5% of project costs) (Park Reserve)
_. _ _ J ...... ~...... .,..1" '\. ,." ""- ....... This project is anticipated to begin beyond 2014
'.~n:~'_.'-'" - "
· ~~ i.-"'- -l~
Art "mF+'l( 7~~-,-,,_rt:/~e4, (I Justification
~d i,' J: JW ,St,~lj~;~~.~( l " fC ,::J j i , '1" "I
~~ t.f~~ !!~r:j."wj[;it:ib;0;,.-;-: -'- .+,~'~\!C~ll This will provide funding for a future sports complex, potentially at a future school site.
- . ~ldriJy";"'.i"'--::--'- "~'" ':;r J,,~ :-I,)t J I
~- .,."",. .. ~..~' jWE i' "~ " /',~. '1'-
t ..1 r ~;WiJ t~; ;,' ,^,'<1+,~. .;q,~, ":,M.,\;) I Other Comments
.(;~! (t~h~ rHlI i"fl: I \j
:Cl:~h:.;: " ,~ . ~':'ei~
,. t.. .,. r. - "dY~
:r:r:;:. (';: - - - I - "", Operatina Costs
Unknown at this time - dependent on scope of development.
1,,,L,q
r<:J._-2;~.~ . - j
1,__'.~;1
21
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Land Acquisition and Development Prairie Village Neigborhood Park 337,500
Year Added to CIP: 2001
A. Expenditure Items: 2009 2010 2011 2012 2013 2014
Land & ROW 150,000
Construction 150,000
Improvements
Engineering/Admin. 37,500
Total - - 337,500
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 337,500
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
T ax Levy
Total - - 337,500
Description
Provides for acquisition of 2 acres of land adjacent to Prairie Village development.
land and ROW: $150,000 (Park Reserve)
Construction: $150,000 (Park Reserve)
Play equipment, trail connections, picnic area
Engineering/admin: Design and construction of park, (25% of project cost)
Justification
In 2002, residents from Prairie Village development asked City Council if it could obtain land to locate a park
near their subdivision. Council directed staff to investigate potential sites. Staff approached Beta Seed in 2004
for possible land sales, but Beta Seed declined.
Other Comments
The City received cash in lieu of land in this development, and there are no nearby recreational amenities. If
land is not available, another option that could be pursued is to work with Sl. Francis and include a
recreational amenity as part of their future expansion.
Operatina Costs
Unknown at this time - dependent on scope of development.
22
City of Shakopee Capital Improvement Program 2009 - 2014
Project Manager Project Type: I Project Title: Total Project Cost:
Jamie Polley Improvements Small Improvement Projects 40,000
A. Expenditure Items: 2009 2010 2011 2012 2013
Land & ROW
Construction 20,000
Improvements
Engineering/Admin.
Total - - - 20,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 20,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - 20,000
Description
This project provides funding for non-designated projects requested by Council, residents,
general, the project should 1 )correct a problem or address an issue, 2) not exceed $20,OO(
consistent with the comprehensive park plan,
"'\ .pi'\. (.......,- Justification
,-- -I...... _-" '" ....
· <'c..' ~~Q;:}-'":::r"'-- "
i1' ' rl,-" ~-'k . r't Other Comments
)1'" T"P )hlh~r!% ll\i~ J~ ---Lc~~"JI ~i\ I
~f~ u,~~~,: '"h~~l'r~~;!j''' "f '{1'-lc~J' ~J~
'""',-, h,t0L' '':.. . " .. :;;:i~; .,," "'" ~".;?':4:;;\i'<{'cr' I
~ ~JJ'lllt""f:(:; ....,;; 0(,0'"., 1.:) Operatin~ Costs
- r f;~~" ~~'4f~ J'-'-'- '~~'~1':~;i"{ Unknown at this time - dependent on scope of projects selected.
:J:,","l',.L ..' "" ~ l'J 'I'^
+~ ':1;:~ J - ", "';-')1
I',".'~ _r _l I ''&
kJ~~_!,\:
1-, L ~
r "
'Jf-'
...--..,.......-,...."-.....,,..
I I
23
2009-2014 CIP Working Summary - 8-7-09
Task Estimate Funding Source 2009 2010 2011 2012 2013 2014 Comments
Park Dedication Fee Proiections
Commercial 120,000 120,000 Final Plat Approved
Residential
-
Grants
Tax levv
Assessments - - - - -
Xcel Aqreement 5-year aqreement. 440,900 440,900 Have not received as of 8/7/09
Donations/Contrib
Parks Developed by Developers
Interfund Loan
Transfer in Fund Balances 1,016,400 Recreation & Telecom fund balance transfer
Total Revenue/Credits 440,900 1,577,300 - - - -
Off-Leash Doq Area Desiqn and Development 24,000 Park Reserve 24,000
Desiqn and Development 20,000 Donations/Contrib 20,000
Lions Park Improvements 64,000 Park Reserve 64,000
36,000 Donations/Contrib 36,000
Greenfield/Park Meadows Park Desiqn and Construction 600,000 Park Reserve 10,000 590,000 Desiqn in 09, Construct Phase 1 in 2010
Westminster Bathroom Facility/Warminq House 202,652 Park Reserve 2,652 200,000 09 is final playqround payment
Park Signage Install Park Signaqe 34,000 Park Reserve 8,000 8,000 10,000 8,000 9,000 . 22,000 3 siqns per year throuqh 2015
Southbridge Area Park MNDOT 75 & Active Park Development 1,410,310 Park Reserve 1,410,310 $368000 Assessment paYback, Construct later than 2014
Savanna Oaks- Southbridqe Trail Trail Construction 100,000 Park Reser/Other 100,000 Reqional Trail Connection
Retainaqe held -
Tahpah Park Improvements Ball Field 98,500 Park Reserve 98,500 Additional field
Donations 200,000 Donations 200,000
Grants 100,000 Grants 100,000
Liqhtinq fields 7 & 8 218,000 Park Reserve 218,000 Liqhts for fields 7 & 8
Quarry Lake Park Cleanup/Desiqn/C onstruction 830,350 Park Reserve 100,000 730,350 $1,685 used in 07 for cleanup,
Grants 269,650 170,000 Grants returned to DNR 2009
Construction 300,000 Donations 100,000 200,000 40,000 Donations received from Polaris & Xcel Enerqies, SPLWSA fundraisinc
Huber Park Improvements Phase 2 Bank Stabilization 2,400,000 Park Reserve 2,400,000 $2,400,000; Graffetti Paint for wall and tunnel to be funded from other source
17th Avenue Sports Complex Liquididated Damages 52,500 Park Reserve 52,500 18000 will be used for fence & netting
Fencinq & Netting 18,000 Park Reserve 18,000
Field Liqhting 230,000 Park Reserve 230,000
Field Liqhtinq 100,000 Donations/Contrib 100,000
Riverside Bluffs Park (East Dean Lake) Desiqn and Construction 800,000 Park Reserve 200000 400,000 200000 Playqround in 10, Phase 1 const in 11
Premier/Horizon Heiqhts Park Developmen Desiqn and Construction 236,250 Park Reserve 236,250
Kilarney Hills Park Development Desiqn and Construction 420,000 Park Reserve 420,000
O'Dowd Lake Park Improvements Desiqn and Construction 396,000 Park Reserve 396,000
CR 79 Trail to O'Dowd Lake Park Desiqn and Construction 275,000 Park Reserve 275,000
Prairie Village Park Land Acquisition/Construction 337,500 Park Reserve 337,500
PUSL Channel Greenwav Corridor Desiqn and Construction 157,000 Park Reserve 157,000
Riverview Park Parkinq Lot Parkinq Lot Construction 78,750 Park Reserve 78,750
Shutrop Park Development Desiqn and Construction 1,250,000 Park Reserve 1,250,000 Construct later than 2014
Tunnel Fencing 9,000 Park Reserve 9,000 Approved upqrade to CSAH 21 trail tunnel
Community Park Sports Complex Desiqn and Construction 1,050,000 Park Reserve 1,050,000 Construct later the 2014
Small Improvement Proiects Construction 40,000 Park Reserve 20,000 20,000
Interfund Loan Payback Financinq, 5 year payback 924,500 Park Reserve 227,500 230,250 232,500 234,250 235,500 236,250 10-Year pavoff (a) 5%
Total Expenditures 13,012,312 - 318,652 1,037,250 786,500 840,750 1,291,250 9.510,310
Net Revenues (Expenditures) 122,248 540,050 (786,500) (840,750) (1,291,250) (9,510,310)
Cash Balance 5/19/2009 36,500
Ending Park Reserve Balance 158,748 698,798 -87,702 -928,452 -2,219,702 -11,730,012
I I I
!
I