HomeMy WebLinkAbout13.C.2. Sidewalk Connections on CR 21 Project J3~ C. ;;L/ CITY OF SHAKOPEE Memorandum TO: Mayor & City Council Mark McNeill, City Administrator FROM: Bruce Loney, Public Works Director SUBJECT: Approval of Sidewalk Connections on CSAH 21 Project DATE: July 21, 2009 INTRODUCTION: Staff, in its final review, has looked at making additional sidewalk connections with the C.R. 21 Project and needs Council approval to make these connections or delete them from the project. BACKGROUND: In the final review of the plans, staff did review the sidewalk connections in the area, particularly arounLSouthbridge Parkway and C.R. 18 and also with the Riverview Fields and Bluff develop ents. There are two sidewalk connections that are being proposed for Council review and as follows: . CSAH 18 east sidewalk connection, from CSAH 21 to Crossings Boulevard. . Riverside Fields 4th Addition sidewalk connection, from Rye Court to CSAH 21 trail. With this memorandum, staff has the following items for Council review and discussion and as follows: . Aerial drawings and plan view of CSAH 18 connection, from Crossings Boulevard to CSAH 21 and a proposed sidewalk connection into the commercial district that mayor may not be needed some day. . Aerial view of the sidewalk connection, from Rye Court to CSAH 21, which is a 5% maximum grade to meet ADA requirements. . Cost estimate for the two sidewalk connections. . Elementary School boundary limits showing the School District boundary of elementary schools and busing routes. . Preliminary plat drawing of Riverside Fields . Overall sidewalk/trail map of Southbridge/Riverside Fields area . Pictures of sidewalk between Lots 10 & lIon Rye Court For the CSAH 18 connection, staff initially felt that an easterly connection to CSAH 21 could be a high conflict of pedestrians with vehicles due to the amount of right and left turn movements coming out of the commercial district. In review with the design engineer and County staff, improvements can be made and it is felt that a safe crossing can be made. Due to the volume of traffic on both CSAH 21 and CSAH 18, it would be best to make this sidewalk connection to facilitate pedestrians in the area and on both sides of major County roads. Also, a significant amount of grading would need to be done if the sidewalk connection were to be done in the future and that would be a City cost. It is proposed that with this connection the County would be doing the grading work. The City would be responsible for 50% of the pipe work, 100% of the concrete curb & gutter and concrete sidewalk. The estimated cost for this connection is $6,741.04, which includes 21% County administrative fee for these improvements which includes Federal funding. Upon further review, staffwould recommend that this connection be made. For the sidewalk connection on Riverside Fields 4th Addition, from Rye Court to CSAH 21 trail - staff is following up from a preliminary plat condition in which a sidewalk connection was shown on Rye Court and in between Lots 9 and 10 to make a connection to CSAH 21. The actual sidewalk route was built between Lots 10 and 11. The cost of making this connection is approximately $19,585.61, which also includes two pipe culverts under the sidewalk for storm water flow between the pond. Staff has additional concerns with this item, as both of the houses have been sold and there is not a sidewalk easement provided for the sidewalk between the lots on Rye Court. Also, staff is wondering how useful this connection will be considering that some day sidewalk and trail connections will be provided along Crossings Boulevard connecting Pike Lake Road and CSAH 18. Currently, this sidewalk connection ends at the end of the lots on Riverside Fields 4th Addition and into a pond. In order to make the connection, pipe culverts need to be installed, significant grading work needs to be done into the pond area and switchback design of the sidewalk grade in order to meet Federal ADA Standards to make the connection to future CSAH 21 trail. The amount of money that the City was going to pay the County towards the CSAH 21 Project has been greatly reduced due to the County being successful in obtaining additional Federal stimulus dollars for this project. Thus significant funds do exist in the City's Capital Improvement and State Aid Funds to fund these improvements. The question for Council is to decide whether or not these connections should be made at this time or at all and if to be made, to add to the CSAH 21 Project. ALTERNATIVES: 1. Approve a motion approving the CSAH 18 sidewalk connection, from Crossings Boulevard to CSAH 21. 2. Approve a motion approving the sidewalk connection of Riverside Fields 4th Addition, from Rye Court to CSAH 21 trail. 3. Do not approve the CSAH 18 sidewalk connection at this time. 4. Do not approve the sidewalk connection of Riverside Fields 4th Addition, from Rye Court to CSAH 21 trail at this time. 5. Table for additional information. RECOMMENDATION: Staff has discussed the sidewalk connections and the CSAH 18 connection will be a safer connection for the public, especially as traffic and development grows in this area. The City's costs in installing this improvement would be at a minimum, with the County picking up most of the grading work and the County is applying Federal funds to the City's cost. The Riverside Fields 4th Addition sidewalk connection is to meet a preliminary plat condition. Staff believes the sidewalk connection was installed along Rye Court and in between two lots with the ultimate goal to connect to the CSAH 21 trail. There are concerns in making this connection due to the lack of sidewalk easement, impact to the storm water ponds and minimum value as a connection to CSAH 21, once the trail and sidewalk connection are made on Crossings Boulevard to Pike Lake Road. ACTION REOUESTED: 1. Approve a motion approving the CSAH 18 sidewalk connection, from Crossings Boulevard to CSAH 21. 2. Approve a motion approving to install or not to install the sidewalk connection of Riverside Fields 4th Addition, from Rye Court to CSAH 21 trail. ~n~ Public Works Director ENGR/2009-PROJECTS/CSAH21IWORDISIDEW ALK.CONECTIONS __ __ _.__.n_ _~_ __ _ __ ___' __ _ ___ _____ ______ _ ___ _ __ _ __ _ ____ ---- --- ----- -- - - - -- - -- - - I I I - - I lW I I I "_' I II I ~--..___:...Eo1~"..92.._~~L-._t if ':,~~ : I "0' 1 I - i \ i~; : ~ .~ ~ I _ _ _ _, ~5"'OO ~l, - - -I I ------ I "-~-r-r- :1&;1 '1 \ r..'; I ....1 l : ~.;~ I -', '\( , '" ,0- .z: " ',~ ~ ,. ~ '~. ~ ,. " . "' ~." " ~ '~ "'-.. PARCEl 4\ "~I . ~ ,. KQPfE CROSSINGS l:a "'s~'? . IlfO PTN$HP . . . . '" \'\:I_,~ ' . ~1 It& ",.. I ~ \~~s"':" I .~ t'- c~';. I,;':' ...."o'? ,-,- ~ ~ : I I "~.fII' I:'! f;ij . :OSSl'GS LTO PTNSHP I, I ' ~"' ..' . _fa!. 4' "'10; I . I' .. 1ll$1.. V I - I I " 'c,!1) I - I t' At' 'I II ft'l'i I 1 ' "" I I : f : 1.1 1 I f! I I, I I, I I · : t : .' :~'l' I" , : _ _ _ _ _ _ "::"JIf_.. ~'~ . .. . I 1llI ,;;I j", I . -' I '" ."' · ,. .fI?J' I - - ~,I ~ - ' " Jilll! . . ~.it: I I . ' I I ',,1 I I "j ~" I l- I '"'.# I , .,,~ "fifE. 4f S~ ,~ ",,-!.!' ""i' 4lit~ "',- t ,!,'~ ", , '. ...,.~ \ At '*'" 4 \ ~ I ,,,,,:,# I I " " . I . : '. I .j' "', I # ~ I "!if'~ ~~ '.... . ...A.' w ," ,.0 ~.' ./ ~ .6~ ".....v'.." . " . ' . . (r~ ' , . \ 'l'~" . i . . '" ,,\ : ~ -\\;'" , : , ~"'#' ,.~ ~r'/ I I I I.. I f _ '.... ie- J<..... "', L..... ' ~-::- """- ~,.....~ ,'., tit ~... - ......--.,.- ;. . J ....~,~ , ......~ " ~I" ~ ,,~ _Ii.... .__ ~"..; ,- --- ----~-------- -------- ------- ---.---- f~ '::J I !l el' I " .,~ .' T" "i@ , ~ I.!' ~ " Wi I i ',,11< i i I . I ~'~,tr \,~'~' /:." ," "~, '.' , ~. I ~ ,. h\ \\h ~ I ~ ~~" . \~ 1 ~ t \. , . l " . !'I I --..", ... ""-~l ~.~ " ~ l!l " I" ., 'I '. .' " I I ili ~ w II I 1 i 'll . II m . .~,-w.,~ \ \ ~ \ 1l :!II \ t ..\- \ .. Il\ \. I "... CSAH 21 Extension Local City Sidewalk Connections City of Shako pee July 15, 2009 Item Unit Estimated Estimated Number Description Notes Unit Price Ouantitv Cost Sidewalk Connection--Riverside Fields 4th Addition 100% LOCAL COST 2501.515 24" RC PIPE APRON EACH $540.00 4 $2,160.00 2503.541 24" RC PIPE CULVERT DESIGN 3006 CLASS III UN FT $35.00 192 $6,720.00 2511.501 RANDOM R1PRAP CLASS IV CUYD $75.00 32 $2,400.00 2511.515 GEOTEXTILE FILTER TYPE IV SQYD $10.50 48 $504.00 2521.501 4" CONCRETE WALK (SIDEWALK) SOFT $3.75 1174 $4 402.50 SUBTOTAL I $16,186.501 INDIRECT COSTS (21 % OF SUBTOTAL' $3.399.17 I TOTAL LOCAL COSTII $19.585.671 1 Sidewalk Connection--CSAH 18 FEDERAL COST PARTICIPATION (87% FED/13% LOCAL) DRAINAGE ITEMS (50% COUNTY/50% LOCAL) 2501.515 15" RC PIPE APRON EACH $425.00 2 $850.00 2503.541 15" RC PIPE CULVERT DESIGN 3006 CLASS V UN FT $25.50 24 $612.00 2511.501 RANDOM R1PRAP CLASS IV CUYD $75.00 5.8 $435.00 2511.515 GEOTEXTILE FILTER TYPE IV SOYD $10.50 8.7 $91.35 TOTAL DRAINAGE ITEM COSTS I I $1,988.351 LOCAL PARTICIPATION FOR DRAINAGE ITEM COSTS (50%\ $994.18 2521.501 4" CONCRETE WALK (SIDEWALK) SQFT $3.75 7214 $27,052.50 2531.501 CONCRETE CURB & GUTTER DESIGN B424 UN FT $12.00 1234 $14808.00 TOTAL CONCRETE COSTS I $41,860.501 LOCAL DRAINAGE COSTS $994.18 I SUBTOTALII $42,854.681 LOCAL PARTICIPATION AFTER FEDERAL FUNDS APPLIED (13%) I $5,571.111 INDIRECT COSTS (21 % OF ABOVE TOTAL $1,169.93 I TOTAL LOCAL COSTII $6,741.041 C:\Documents and Settings\bloney\Local Settings\Temporary Internet Files\Content.Outlook\66R4KWQL\shakopee_walks - Final Elementary ~ Attendance Areas, 2007 February Shakopee I Public Schools , ! I I I . Schools. ^ / Roads Boundaries Att~ndance k Elem. D Eaale Cree Pearson Elem. D Red Oak Elem. Ii:::] Sun Path Elem. B Sweeney Elem. N f' 8 Miles 4 0 - 4 '~ RIVERSIDE FIELDS ;.H~~:~~D~~EET/SITE PLAN g PRELIMINARY PLANS 2. EXISTING CONDITIONS ~ . 3. PRELIMINARY PLAT w SHAKOPEE MINNESOT 4. PRELIMINARY GRADING 0 , 5. PRELIMINARY PROFILES iQ .........,/,/" 6. PRELIMINARY PROFILES ~ // 7. PRELIMINARY UTILITIES 0:: /// TR1. TREE PRESERVATION PLAN SETBACKS /// TR2. TREE PRESERVATION PLAN ig: ~~T __----/ L1. LANDSCAPE PLAN 10' HO~SE SlOE -- L2. LANDSCAPE PLAN zg: ~,~~Argo~~iR LOT) L3. LANDSCAPE PLAN 30' REAR COUNTY PRINTED AUG 1 12003 ; PIONEER Fr\IG'N--r'-IN'~ "A _ I tet < \:J,.. , < "A " "Jtt 0 50 lOD :!Oil ",J\' ~...... I "" ;~z:ff'-. GRAPHIC SCALE IN FEI!T " · /'- "," Ai! \. <-.. ~ A""~F'_,A " '~ !.d~,i/ifJ .,{ffT 1> ,,' i!f#lir'l',' " 1'" ,i'#; '/.-t!} '\. "'i/.fo1:.{"~, , ,y, ill'ff .I -'!it '\ . ''';';';$' /f~ !J"f!~ " " -, ,f if J'II" " ~'f '- .. PRF"PAR!='n RY P10NF"I'"R F'Nl':INJ':E"RING P A '\.. DEAN M. ROSBINS "- REGIS1ERED PROFESSIONAL CIVIL ENGINEER "- 41968 " ~. "- ~~~~~R~~R;~~FESSIONAL LAND SURVEYOR ""- 19828 =<'ro, DEVElD?ER RYLAND HOMES 7900 W. 78TH STREE:T SUITE 100 . EDINA, MH. 55439 lh.nfo,ma\kln Md/orr~d"'ln9san<lmap'COlIlatl.dh"'."'su:ho..\ra.1 and 101 local...., dl,....IQIIS, art... lond...pl.,9ond ""'..IIl...._e.l 110. E:~r:1\O~~;.~~I:;,~~:.~!: ~~3RQ~:,~:~i~~::: ...lond..lII..,',..y...'....."'lom>.lI.n.nd/..""'d.'I.91...."'.P.'" vl.... <:onl.lnod h..cln In d.<ldInG l.pIIrch....ny.......rly..lc. Pion.... Er\;1noorlnG, P."" m.lco.., ......nUtI... ,.pr....I.U... 0/ ""y tlnd RECR "'d>Qrocl.... .'p'....d or"'p1Iod, 00111\ "'....., t.l....m.U.... d'plol.d or cO\lU.dby\IIt'~..I"'._~""d..\nOlllll...m.UonhOloln, For dol.~..r ..1s1ln9 d.1/oI""od ...... nl... La lh. ,.....dld /InoI ol.L ll:: ~:~tj. .~.: ~';'IYd:~~..::t ~'::~.~~"Ji.~.:.:,;~ .;:= for cr,yp"I(').llh..",p.r~ Th.dovcl_.....'_'h.~GMI..honG.lh.plon."llhoUI""l/I.'".'Iu. Sub,..lt. Clly..dall G........"Ollt .ppnwol.. ~**~ :: PIONEER 1. flL\ol5ED fliGHT_or_WAY & LOT l~l(S **Bng~na~.~~'::-"I~~.~''t.''".... r._.by"",lIlylh.tlhl.pl.......prop...dby",...lIndormy N..". 1I'9.N","_ t'i~r!D3 Dol. 6-05-0:1 SHEETlIlLE O~ER PROJECT ~* ....-.--.. ~1!!i:1:;;'n>-1W ~~~I.:.up.:.::.:;,.""~h:}llh':"Sr.I~!ll~:.:::::I:."'I...lon.. Si~.lu,. llolo~ ~;::'d ~~ COVER SHEET RYLAND HOMES L J 0: l( Q .JI >- ~ ... ~ ~ W1NlJSOR /JRN ~ NS :;:: ~ Q 0: " )J Z G) V> FOX RUN Q ct:: ................... ~:::::::::::~~ ..- -........ .CROSSINGS Q :5 0: llJ '" ~ ii: ffi oR '" 0 ":':i '" . . 0 . . . . ... . . . . I . . . . . . . . . . I . . . . . . . . : : . . Q . . . . 0: . . llJ . . . . ; : . . . . ! : tnl ~ Sidewalks Existing - I Potential Sidewalks ........, N SHAKOPEE Trails Existing - Trails and Sidewalks w+" s CcJMMUNlIY l'RlDE SINCE HI57 Potential Trails ........1 0 550 1.100 2.200 3,300 ~-- 'Feet ''1 ,1 I I I I , I I I i .~ .- -- ~..~- ----. --- ~ ,...- ~ - -- -