HomeMy WebLinkAbout13.C.1. Park Reserve Capitol Improvement Plan 2009-2013
/3, C./.
CITY OF SHAKOPEE
MEMORANDUM
To: Mayor and City Council
Mark McNeill, City Administrator
From: Jamie Polley, Parks, Recreation & Natural Resources Director
Meeting Date: June 2, 2009
Subject: Park Reserve Capital Improvement Program 2009-2013
INTRODUCTION
This agenda item provides the first review of the Parks 2009-2013 Capital Improvement
Program. Staff is seeking direction on the priority of projects to fund.
DISCUSSION
The Capita/Improvement Program (CIP) program identifies costs and funding for construction of
new parks and recreational trails, land acquisition, and improvements in park facilities. The
program attempts to focus limited resources on projects that are priorities for meeting the needs
of a growing community.
With the decision to move forward on Huber Park in 2006, the City committed a significant
amount of current and future funding resources toward completing this project, including a $2
million interfund loan. As a result of this action and the subsequent slow down in development
and decrease in park dedication revenue, you will see a significant change in the CIP from what
is proposed for 2009-2013, with many projects deferred until funding is available after 2013.
The proposed plan focuses our limited financial resources on projects that are in most demand,
as well as acknowledging the projects that have some level of commitment to undertake yet this
year.
The summary spreadsheet attached to this memo is used to regularly track and update revenue
and expenses for the Park Reserve fund. The summary spreadsheet reflects expenses paid as
of 5/19/09 and includes estimates for remaining payments of Savannah Oaks retainage and 1 ih
Avenue Sports Complex Liquidated Damages. Once Savannah Oaks is finalized and accepted
by Council, and the mediation of the 17th Avenue Sports Complex is completed the final bills can
be paid and the spreadsheet can be updated to reflect those final costs. The spreadsheet also
includes funds to continue the park signage installation and paint the wall and tunnel near Huber
Park with a graffiti resistant paint.
Proposed CIP and Options
The proposed CIP includes the payment of the interfund loan over five years.
2009
. Riverside Bluffs/Fields Park - (Playground)
. Greenfield/Park Meadows Park (park design)
. Park Signage
. Shutrop Park/CSAH 21 Project - (trail underpass fencing)
. Quarry Lake Park
(This project has grant funding that will expire in 2010 if it is not constructed. Public access
has not been obtained)
.
2010
. Off-Leash Dog Area (site to be determined)
. Greenfield/Park Meadows Park (site work phase 1 construction)
. Park Signage
. Quarry Lake- (completion)
2011
. Greenfield/Park Meadows Park (site work phase 2 construction)
. Park Signage
. Savannah Oaks Trail Construction (to connect to ped bridge over 169)
. Riverside Bluff/Fields (site work phase 1 construction)
. Second baseball field at Tahpah Park.
2012
. Lions Park Improvements (2nd sheet if needed)
. Greenfield/Park Meadows Park completion
. Park signage
. Tahpah Park light installation on fields 7 & 8
. Field lighting at 1 ih Avenue Sports Complex
. Riverside Bluffs/Fields Park completion
Additional projects have since been deferred to 2013 and beyond. However, if a large
development project comes forward or development picks up, projects that have been deferred
may be moved up. The Advisory Board, City Council, and staff will have an opportunity to revise
timelines and projects each year when the CIP is reviewed and updated.
The Quarry Park project has received the grant funding that expires in June of 2010. Public
access has not been obtained and therefore a determination of the desire to move forward with
site construction needs to be made. Do we put money into a park that the public cannot use?
The City can turn the grant dollars back over to the DNR and it mayor may not hinder the City
from receiving further grants. In addition, the Engineering Department will be submitting a
grant for a pedestrian bridge over 169 that would complete the construction of an anticipated
regional trail.
BUDGET
The 2009 budget anticipates that park dedication fees will be received in the amount of
approximately $315,000. The final plat for the commercial development was approved and it is
anticipated that the developer will record the plat in 2009. Staff is currently reviewing the final
plat for the residential development. 2010 anticipates obtaining $350,000 in park dedication
however there are no pending developments at this time.
In 2010 the recreation fund will be part of the general fund. To date the recreation fund fund
balance is approximately $340,000. It is anticipated that the fund balance will go into the
general fund fund balance in 2010. Staff is recommending that the City Council transfer the
balance of the recreation fund at the end of 2009 to the Park Reserve CIP. The City Council
has identified the need to find alternative Park Reserve funding options in the City two year
goals and strategies. Transferring the fund balance is a one-time alternate funding option.
Finally, with the absence of the Landscape Architect, the Engineering staff has assisted with
many of the remaining park development projects and is planning to assist with future projects.
At this time the Engineering Department's time is billed back to the park reserve with a multiplier
of 2. Staff is recommending that staff time charged to the Park Reserve be charged at straight
time to allow for projects to be completed in house at a more cost effective rate.
REQUESTED ACTION
1. The City Council, if concur, move to transfer the recreation fund fund balance at the end
of 2009 into the Park Reserve CIP fund.
2. The City Council, if concur, move to charge staff time to the park reserve at straight
time.
3. The City Council is asked to review the proposed 2009-2013 Capital Improvement
Program for parks and provide direction to staff on project prioritization.
--.---
/'!J,C. J,
/<Sl/iSC-O
2009-2013 CIP Working Summary - 6-2-09
Task Estimate Funding Source 2009 2010 2011 2012 2013 Comments
Park Dedication Fee Projections 350,000 500,000 500,000 500,000
Commercial 120,000 120,000 Final Plat Approved
Residential Final Plat 2nd Addition Submitted-land accepted w/ Prelinary Plat
Grants 170,000 100,000
Tax levy
Assessments - - - -
Xcel Agreement 5-year agreement. 440,900 440,900 Rcd Xcel Pmt for 2008
Donations/Contrib 20,000 100,000
Parks Developed by Developers
Interfund loan
Total Revenue/Credits 560,900 980,900 600,000 600,000 500,000
Off-leash Dog Area Design and Development 24,000 Park Reserve 24,000
Design and Development 20,000 Donations/Contrib 20,000
Lions Park Improvements 64,000 Park Reserve 64,000 25,500 held for Lions land sale
36,000 Donations/Contrib 36,000
Greenfield/Park Meadows Park Design and Construction 1,226,250 Park Reserve 30,000 170,000 400,000 626,250 Design in 09, Construct Phase 1 in 2010
Park Signage Install Park Signage 34,000 Park Reserve 8,000 8,000 10,000 8,000 9,000 3 signs per year through 2015
South bridge Area Park MNDOT 75 & Active Park Development 1,042,310 Park Reserve Construct later than 2013
Savanna Oaks- South bridge Trail Trail Construction 100,000 Park Reser/Other 100,000 Regional Trail Connection
Retainage held 3,450 3,450 I
Tahpah Park Improvements Ball Field and Lighting 200,000 Park Reserve 100,000 100,000 Additional field & Lights for fields 7 & 8
Quarry lake Park CleanuplDesign 130,000 Park Reserve 30,000 100,000 $1,685 used in 07 for cleanup. Grant funding will expire 2010 if not used.
Design 170,000 Grants 170,000 Grant Received Deadline 6/30/10
Construction 40,000 Donations 40000 40,000 Donations received from Polaris & Xcel Energies
Bluffs at Marystown Design and Construction - By Developer
Huber Park Improvements Paint 10,000 Park Reserve 10,000 Graffetti Paint for wall and tunnel
Phase 2 Bank Stabilization -
17th Avenue Sports Complex Liquididated Damages 81,000 Park Reserve 81,000 18000 will be used for fence & netting
Fencing & Netting 18,000 Park Reserve 18,000
Field Lighting 230,000 Park Reserve 230,000
Field Lighting 100,000 Donations/Contrib 100,000
Riverside Bluffs Park (East Dean lake) Design and Construction 320,000 Park Reserve 75,000 245,000 6435001 Playground in 09, Phase 1 const in 11
Premier/Horizon Heights Park Development Design and Construction 236,250 Park Reserve 236,250
Kilarney Hills Park Development Design and Construction - Park Reserve 420,000
O'Dowd lake Park Improvements Design and Construction 396,000 Park Reserve 396,000
CR 79 Trail to O'Dowd lake Park Design and Construction 275,000 Park Reserve 275,000
Prairie Village Park land Acquisition/Construction 337,500 Park Reserve 337,500
PUSl Channel Greenway Corridor Design and Construction 157,000 Park Reserve 157,000
Riverview Park Parking lot Parking lot Construction 78,750 Park Reserve 78,750
Shutrop Park Development Design and Construction 1,250,000 Park Reserve Construct later than 2013
Tunnel Fencing 9,000 Park Reserve 9,000 Approved upgrade to CSAH 21 trail tunnel
Community Park Sports Complex Design and Construction 1,050,000 Park Reserve Construct later the 2013
Small Improvement Projects Construction 80,000 Park Reserve 20,000 20,000 20,000 20,000 20,000
Interfund loan Payback Financing, 5 year payback 1,862,500 Park Reserve 457,500 463,750 468,750 472,500 5-year payoff
Total Expenditures 9,581,010 - 741,950 1,015,750 1,343,750 2,300,250 1,929,500
Net Revenues (Expenditures) (181,050) (34,850) (743,750) (1,700,250) (1,429,500)
! Cash Balance 5/19/2009 37,953
Ending Park Reserve Balance -143,097 -177,947 -921,697 -2,621,947 -4,051,447
<
!