HomeMy WebLinkAbout15.C.1. Relocation of Existing Power Lines on Project No. 2003-4
, IS. c. J
.
CITY OF SHAKOPEE
Memorandum
TO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
SUBJECT: Relocation of Existing Power Lines on the
Valley View Road Improvement, Project No. 2003-4
DATE: August 19,2003
INTRODUCTION:
Associated with the Valley View Road Improvement Project, from the east plat line of
Pheasant Run 6th Addition to the east plat of Greenfield is the relocation of existing
overhead power lines with this project. This agenda item is for City Council to consider
whether or not the Council wants the existing overhead power lines to be placed
underground or to be relocated overhead on this project.
BACKGROUND:
With the Valley View Road Improvement Project, the existing overhead power lines will
be need to be relocated with the construction of Valley View Road to a 44 foot wide
roadway, sidewalk and trail. It is proposed that the electric lines would be relocated
north of the bituminous trail on the north side of Valley View Road. Per the City's
Right-of-Way Management Ordinance, if an existing overhead power line installation is
relocated more than 300 feet, the City has the discretion to require the existing overhead
power line to be placed underground or to remain overhead. Previously, with the Valley
View Road Project west of the Greenfield Addition, City Council did decide to allow the
existing power line to be relocated and remain overhead.
Per Shakopee Public Utilities Commission's (SPUC) staff, it is estimated to relocate the
existing overhead power line installation will cost approximately $12,000.00, and to
place the power lines underground would cost $55,000.00. SPUC is currently
considering funding mechanisms and policies to pay for the undergrounding of existing
overhead power lines, if required by the City. These policies were discussed at SPUC's
meeting on July 21,2003 and by motion a report was approved. This report on financing
undergrounding of existing lines is attached.
With this item, City Council should consider a motion to either allow the existing
overhead power lines to be relocated and remain overhead or to require the existing
overhead power lines to be placed underground.
Per the report on relocation of electric facilities prepare by a SPUC consultant, the
options for SPUC to recover the additional costs of undergrounding facilities are as
follows:
. Continue to recover the costs through standard retail rates.
. Invoice the City and recover the costs by a direct payment from the City as a
project cost.
. Recover the costs through a special retail rate added over a short period of time.
A future meeting may be in order for the Council and SPUC to discuss the funding
options. It seems Options # 1 and 3 are the best options, since adding the cost to projects
may be difficult to assess and will add to assessments amounts that could be contested in
court.
The issue for Council at this time is to discuss whether or not to underground the existing
overhead lines on Valley View Road. The funding option discussion can occur at a later
meeting.
The Valley View Road Project may be awarded on August 19,2003, and a discussion on
undergrounding or relocating the existing overhead lines should be done soon in order to
proceed with the construction work.
ALTERNATIVES:
1. Approve a motion determining that the existing overhead power lines along
Valley View Road can be relocated.
2. Approve a motion determining that the existing overhead power lines along
Valley View Road should be relocated and placed underground.
3. Table for additional information.
RECOMMENDATION:
Staff would recommend that City Council would discuss the issue and provide comments
to SPUC, if consensus is obtained, on the City's policy for funding for undergrounding of
existing overhead power lines and on whether to underground the existing overhead lines
or relocate the existing lines overhead.
ACTION REQUESTED:
1. Discuss the undergrounding of existing overhead power lines issue on Valley
View Road and provide comments, if so desired, to SPUc.
2. Approve a motion determining on whether the existing power line along Valley
View Road along the Greenfield development to be relocated, should remain an
overhead line or be placed underground.
~~
Bruce Loney
Public Works . rector
BUpmp
POWERLINES
July 15, 2003
Mr. Joe Adams
Planning and Engineering Manager
Shakopee Public Utilities
1030 E. Fourth Ave.
Shakopee,~ 55379
Subject: Relocation of Electric Facilities - Preliminary Report
Dear Mr. Adams:
R. W. Beck was retained by Shakopee Public Utilities (SPU) to examine issues related to costs
incurred by SPU for relocating electric facilities due to road widenings necessary to
accommodate growth. This letter describes the results of the analysis we undertook related to
this issue.
Background
The City of Shakopee and its surrounding area are experiencing significant growth. This growth
results in work performed to widen and otherwise improve area roadways. These road
improvements often times necessitate the relocation of electric distribution facilities. At the
time of relocation, existing overhead electric facilities are sometimes replaced by new
underground electric facilities.
Overhead electric facilities may be installed as underground facilities when they are relocated
for reasons of higher reliability and visual aesthetics. It is not uncommon for cities to request
relocated facilities be placed underground to improve city aesthetics. For the City of Shakopee,
the existing City ordinance 1 allows the City to require electric facilities relocated due to road
widenings to be placed underground if one or more ofthe purposes set forth in the ordinance are
met. These purposes include:
. The fostering of safe travel over City right-of-way
. The fostering of non-travel related safety around homes and buildings where overhead
feeds are connected and
. The fostering of orderly development of the City
Current Policy
SPU does not currently have a policy regarding contributions from other entities to help defray
the cost to SPU of relocating electric facilities due to road widenings or installing them
underground. SPU fully funds electric facility relocations and the costs are paid by all SPU
ratepayers. This approach is typical for most utilities when relocations are required and the
1 City Ordinance No. 570 approved August 15,2000.
01-00256-10101-01011 070013 I 3292 P:\Shakopee\undergound policy\07l503 Itr.doc
~
Mr. Joe Adams
Planning and Engineering Manager
July 15, 2003
Page 2
relocated overhead facilities remain as overhead facilities. However, increased desire by cities
and by some utilities to have as many facilities as possible underground has increased costs
associated with relocations. This is due to the fact that typical costs for putting electric facilities
underground is more expensive than comparable overhead facilities.
Recently, the SPU Commission updated the connect fee paid by new customers to fund the
difference in cost between overhead and underground facilities needed to serve such customers.
The connect fee, however, does not cover the costs associated with installing facilities
underground to accommodate road widenings.
Discussion
Road construction or relocation often requires that existing electrical facilities be moved to
accommodate the road work. This circumstance is often viewed by cities to be an opportune
time to convert existing overhead facilities to underground. To provide an example of the
policies pursued by other utilities, we have reviewed the current policy of Xcel Energy relative
to this issue. In the case of Xcel, if the existing overhead Xcel facilities are located on a public
right-of-way, Xcel pays the cost to move them, provided the relocated facilities remain
overhead. However, if the city government requests the lines be placed underground, the
increased cost associated with placing the lines underground is charged to the city. In cases
where a city requests a line to be placed underground absent a concurrent road widening, Xcel
calculates the charge using a formula approved by the Minnesota Public Utilities Commission
("MPUC") that takes into account the original cost of the overhead facilities, depreciation on
such facilities, the cost of moving the overhead facilities and the cost of equivalent underground
facilities.
In a January, 1999 report to the MPUC regarding undergrounding electric facilities2 Xcel states
that: "In many cases, City governments have decided to have specific lines placed underground
at the point of new construction or relocation by a road move. In these situations, NSP
coordinates closely with the community, working to ensure that the conversion costs are paid for
by the community as opposed to all other customers." The Xcel report goes on to state that
"For local governments interested in pursuing conversion, NSP works with the community to
recover the incremental conversion costs. NSP recovers the higher on-going costs through the
monthly service charge paid by the individual customers." Based on discussions with Xcel
personnel, the additional costs for underground facilities can be collected either through a direct
payment by the city to Xcel or can be recovered by a monthly service charge or fee per kWh on
the bills of retail electric customers located in that city. Xcel reports it has used both methods
for recent projects.
2 ''Northern States Power Company Report on Undergrounding Electric Distribution Facilities January, 1999"
01-00256-10101-01011070013 13292 P:\Shakopee\undergoundpolicy\0715031tr.doc
, ,
Mr. Joe Adams
Planning and Engineering Manager
July 15, 2003
Page 3
The table below summarizes four alternative scenarios that may arise in a relocation of existing
overhead facilities. In all cases the existing line is assumed to be overhead. The relocated line
may be overhead or underground and the electric current carrying capacity of the line mayor
may not be upgraded at the time of the relocation.
Relocated Line (Existing OH Facility)
Alternative Scenarios Comment
No Line Upgrade Line Upgrade
Overhead Overhead Current Utility Baseline
Underground Underground New Utility Reality
The current utility baseline has been the longtime standard operating procedure for most
utilities: existing overhead facilities are relocated as overhead lines. Depending on system
requirements and plans, the opportunity to upgrade the facilities may be accomplished as part of
the relocation. However, this upgrade was always done at the discretion of the utility. If an
existing overhead facility is moved due to road construction and no upgrade of the line is
otherwise required, many of the existing materials (e.g., poles and wire) can be reused. Based
on an actual relocation of an existing 2/3 mile of overhead line in Shakopee along Valley View
Road, east of Marschall Road for a total cost of $18,070, it costs approximately $27,100 per
mile to relocate an existing overhead line as overhead with no upgrade of the line. However,
sometimes when a line is relocated to accommodate a road widening, the line will also be
upgraded to accommodate the same growth that is forcing the road work. Upgrading the line at
the time of relocation, but staying overhead, would approach the cost of new overhead facilities
which was estimated to be $38,855 per mile in our April 17 letter.
As discussed above, it is often requested or required that relocated facilities be placed
underground. If no upgrade is required, the incremental cost of converting to underground can
be substantial. As reported in our April 17 letter, new underground facilities in Shakopee cost
approximately $114,050 per mile. This cost will generally be the same with or without a line
upgrade. Per mile costs for the four instances shown in the table above are summarized below.
01-00256-10101-01011070013 I 3292 P:\Shakopee\undergound policy\071503 Itr.doc
"
Mr. Joe Adams
Planning and Engineering Manager
July 15, 2003
Page 4
Relocated Line (Existing OH Facility)
(Typical Costs per Mile)
Relocated Line No Line Upgrade Line Upgrade
Overhead $27,100 $38,855
Underground $114,050 $114,050
Based on typical SPU costs as summarized in the above table, it costs approximately $87,000
per_mile more to place a relocated overhead line underground when no upgrade is necessary.
When the relocated line also has to be upgraded, the additional cost for underground lines is
estimated to be $75,000 per mile. Currently these extra costs to place relocated lines
underground is recouped via standard SPU electric rates.
Although the additional cost of underground lines for new customers was included in the
development of a new customer connect fee as described in our April 17, 2003 letter, such
additional underground costs related only to new circuits and did not include relocation costs
associated with road widenings which do not involve upgrading existing circuits. Thus it is
appropriate for the additional costs associated with road widenings and relocated circuits whose
capacity is not upgraded to be recovered via a separate charge as described below.
When a line is upgraded as part of a relocation, new customer growth is generally driving the
upgrade. In such case, the incremental cost of converting to underground facilities ($75,000 per
mile) would be similar to the cost differential between new overhead and underground main line
feeders discussed in our April 17 letter. In this case, implementation of an underground
connection fee (which would be paid by the new customers causing the growth), as discussed in
the April 17 letter, would contribute funds to this conversion process. In this case the costs are
recovered by the customer connect fee and no additional cost recovery mechanism is needed.
It should be noted that the above costs for overhead, underground and upgraded circuits are
typical costs only. Costs for construction can vary widely depending on various items such as
the subsurface conditions and peripheral construction activity. For example, when County Road
16 (Eagle Creek Boulevard) from County Road 17 (Marschall Road) to County Road 83
(Canterbury Road) was widened in 1995, the overhead circuit along County Road 16 was
relocated and partially upgraded as an overhead circuit. The average cost was $103,000 per
mile. This cost was significantly higher than the $27,100 to $38,855 cost per mile for typical
construction as shown in the above table due to close-to-the-surface bedrock and the inclusion of
secondary work in the project. The cost for placing the facilities underground would, however,
have been considerably higher.
01-00256-10101-0101 ! 070013 I 3292 P:\Shakopee\undergound policy\071503 Itr.doc
,
"
Mr. Joe Adams
Planning and Engineering Manager
July 15,2003
Page 5
Recommendation
Relative to road widenings we propose that SPU pay for the cost of moving any existing
overhead lines in road rights-of-way and recover such costs from its retail customers through its
standard retail rates, provided the relocated facilities are installed overhead. When the circuit
capacity is required to be upgraded due to system load growth and the facilities are installed
underground, the additional cost of placing the circuit underground is recovered by customer
connect fees. When there is no need for the circuit capacity to be upgraded, SPU has several
options to recover the additional costs of putting the facilities underground:
. Continue to recover the costs through standard retail rates
. Invoice the City and recover the costs by a direct payment from the City as a project cost
. Recover the costs through a special retail rate adder over a short period of time
We propose that SPU either bill the City directly or recover such additional costs from its retail
customers via a special retail rate adder. The additional cost of placing facilities underground
would be estimated by SPU staff using the best available data and information. If the additional
costs are recovered via a special retail rate adder, we propose they be recovered by a per kWh
charge applied to all customers. If desired, this charge can be shown as a separate line item on
the monthly bill of each customer.
If a special retail rate adder is used, we further suggest that the SPU Commission establish a per
kWh adder based upon a levelized cost recovery approach. This would help avoid changing the
recovery level significantly from year to year depending on the specific projects that mayor may
not be undertaken during such year. Under this approach, the amounts recovered by the special
adder would be monitored and over time the adder would be adjusted up or down depending on
actual costs incurred for road widening projects.
Attachment 1 provides an estimate of such a levelized kWh adder based on expected costs
associated with road widenings and total kWh consumption of all retail customers over the 5-
year Capital Improvement Plan for 2003 - 2007. As shown on Attachment 1, the special adder
to cover the cost of installing overhead lines underground due to road widenings is estimated to
be $0.0002 per kWh. For a typical residential customer with monthly consumption of750 kWh,
this represents a charge of 15 cents per month.
01-00256-10101-01011070013 I 3292 P:\Shakopee\undergound policy\071503 Itr.doc
..
Mr. Joe Adams
Planning and Engineering Manager
July 15,2003
Page 6
Thank you for the opportunity to have provided assistance to SPU relative to this issue. Please
let us know if you would like additional analysis concerning this matter.
Sincerely,
R. W. BECK, INC.
David A. Berg, P.E.
Principal and Senior Director
c. Kevin Favero
01-00256-10101-01011070013 I 3292 P:\Shakopee\undergound policy\071503 Itr.doc
, ' >..
, . . Attachment 1
Projected Road Widenings in Shakopee
Capital Improvement Plan 2003 - 2007
Project Length in Miles
Circuit Project Description 2003 2004 2005 2006 2007 5- Year
Total
SH-08 4th Ave. (Marschall Rd - Viking Steel Rd) 0.38
SH-10 4th Ave. (Viking Steel Rd - Shenandoah) 0.63
S8-31 Valley View Road (Williams St - CR 83) 1.25
SH-09 Fuller St. (1st Ave. - Levee Dr.) 0.10
SH-10 Viking Steel Road north of 4th Ave. 0.25
SH-07 Adams St (3rd Ave - 6th Ave) 0.30
SS-31 CR 79 (11th Ave - 17th Ave.) 0.75
Total 2.35 0.55 0.00 0.00 0.75
Estimated cost differential per mile between
overhead and underground construction $87,000 $87,000 $87,000 $87,000 $87,000
Total Annual Cost Differential $204,450 $47,850 $0 $0 $65,250 $317,550
Average Annual Cost Differential over 5 years $63,510 $63,510 $63,510 $63,510 $63,510 $317,550
Estimated Retail Consumption (kWh X 1,000) 306,950 321,074 336,757 353,669 370,584 1,689,034
Est. Average Annual Consumption (kWh X 1,000) 337,807 337,807 337,807 337,807 337,807 1,689,034
Est. Average Charge per kWh for Recovery $0.0002 $0.0002 $0.0002 $0.0002 $0.0002 $0.0002
Est. Average Residential Consumption (kWh/month) 750 750 750 750 750 750
Est. Average Residential Charge per Month $0.15 $0.15 $0.15 $0.15 $0.15 $0.15
Est. Amount Recovered from All Customers $61,390 $64,215 $67,351 $70,734 $74,117 $337,807
Attachment 1.x1s 8/12/03
i
.- ",
1
1