Introduction
Replacement of the carpet in the Community Center has been in the
budget requests for three years. It is currently not included in the
2004 budget.
Background
If council desires, the replacement could be funded out of the 2003
budget. The funds are available in the unallocated division due to
over estimating the amount of special assessment the city would need to
pay in 2003.
Because of bidding requirements and timing, the cost would probably
impact the 2004 budget in which case the funding would be in the carry
over fund balance from 2003. Estimated cost is $70,000 and bids are
required over $50,000.
Action
Move to authorize staff solicit bids for the replacement of carpet in
the Community Center and bring back to City Council for consideration.
Gregg Voxland
Finance Director