Loading...
HomeMy WebLinkAbout13.B.1. Add'n Work & Change Orders for Beckrich Park Estates/Kristal Estates, Project No. 2007-10 J 3. ~. I. CITY OF SHAKOPEE Memorandum TO: Mayor & City Council Mark McNeill, City Administrator FROM: Bruce Loney, Public Works Director SUBJECT: Approval of Additional Work and Change Orders for Beckrich Park Estates and Kristal Estates, Project No. 2007-10 DATE: September 16, 2008 INTRODUCTION: This agenda item is to authorize additional work for the Beckrich Park Estates and Kristal Estates Improvement Project No. 2007-10. BACKGROUND: At the May 20, 2008 City Council meeting, Resolution No. 6775 was adopted awarding a contract to S.M. Hentges & Sons, Inc. in the amount of $552,770.63. At this same meeting, Council authorized a 5% contingency for change orders and quantity adjustments. At the August 19,2008 Council meeting, staff asked for additional contingency to 7.5% of the original contract for reconstructing more of Hampton Circle. Council by motion approved the 7.5% contingency amount. After August 19th, there have been additional costs in extra work primarily with utility conflicts and trench rock for stabilization. Attached to this memo is a summary of additional work and change orders associated with the Beckrich Estates Project. The utility conflicts were a negotiated price based on monitoring of the actual extra time worked. The utility conflicts were not identified on the plans. The additional trench rock was needed to correct poor soils in order to stabilize the trench bottoms in the wetland area by Hampton Circle. Staff had anticipated some quantity, however, much more was needed to correct the soils. Also attached is a sheet showing the construction costs and the current projection of costs for the Beckrich Estates Project which is $625,249.67. In addition to this amount, there were areas of channel erosion in the drainage system in Beckrich Estates that were repaired by the contractor and were not part of this project. The cost of those repairs in four areas total $10,017.00 and would be paid out of the Storm Drainage Fund. Attached is a CIP sheet for Beckrich Park Estates drainage system improvements. With the contractor in the area and the area disturbed, it was cost effective to do this work at this time. The total cost of construction work that staff is seeking authorization for is $635,250.00. Staff did conduct a meeting with 25 residents ofBeckrich Estates to go over the project costs and affect on the assessments. Attached is a summary sheet on the assessments for Beckrich Estates and with the increased costs, the assessment is projected to be $27,045.33. The feasibility report had the assessment estimated at $29,514.01. Despite the increased costs, as mentioned, the overall cost of the project is under the feasibility report. ALTERNATIVES: 1. Approve an additional contingency amount of $41,022.00 for the Beckrich Park Estates and Kristal Estates Improvement Project No. 2007-10. 2. Do not approve additional contingency amount. 3. Table for additional information. RECOMMENDATION: Staff recommends Alternative No.1, as the extra work was necessary to complete the project. =." ACTION REQUESTED: Approve an additional contingency amount of $41,022.00 for the Beckrich Park Estates and Kristal Estates Improvement Project No. 2007-10. Bruce Loney, P.E. Public Works Director BUpmp ENGR/2007-PROJECTSlBECKRICH-PArAlWORD/APPROVE-CONTINGENCY J I ADDITIONAL WORK/CHANGE ORDERS I 1. UTILITY CONFLICTS NOT ON PLANS $19,400.00 (Beckrich Park - $17,150. and Kristal Estates - $2,250) 2. CHANGE ORDER NO. 1 $3,600.00 (Extra Pipe Depth, Plug Drain in Butterfly MH and 30" - 36" RCP) 3. CORE DRILL MANHOLE FOR SERVICE RELOCATION $2,000.00 4. TRAIL REPLACEMENT $5,000.00 (Quantity not in Bid Proposal) 5. QUANTITY ADJUSTMENTS $10,000.00 TOTAL $40,000.00 I QUANTITY ADJUSTMENTS I 1. TRENCH ROCK TO CORRECT UNSTABLE TRENCH BOTTOM $33,000.00 2. ADDITIONAL HAMPTON CIRCLE RECONSTRUCTION $10,000.00 (70% City Cost) ENGR/2007-PROJECTS/BECKRICH-PARK/EXCEL/ADDITIONAL.COSTS Beckrich Park Estates & Kristal Estates Extension of Sanitary Sewer & Water Utilities Date: September 10, 2008 City of Shakopee, MN Project Number 2007-10 Original Bid Original Bid Summary of Costs Feasibility Report Original Bid (+ 5% Contingency) (+ 7.5% Contingency) Construction Schedule A - Street Improvements $ 263,078.09 $ 157,254.00 $ 165,116.70 $ 169,048.05 $ 166,204.44 Schedule B - Storm Sewer Improvements $ 5,975.20 $ 10,890.00 $ 11,434.50 $ 11,706.75 $ 4,325.00 Schedule C - Watermain Improvements $ 136,899.40 $ 141,989.43 $ 149,088.90 $ 152,638.64 $ 127,052.03 Schedule D - Sanitary Sewer Improvements $ 308,316.80 $ 242,637.20 $ 254,769.06 $ 260,834.99 $ 287,668.20 Change Orders/Quantity Adjustments Not Applicable Not Applicable Not Applicable Not Applicable $ 40,000.00 Totals $ 714,269.49 $ 552,770.63 $ 580,409.16 $ 594,228.43 $ 625,249.67 Notes: (1) The feasibility Report includes a 10% contingency. (2) The City Council approved a 5% contingency for the original bid. (3) The City Council approved a 7.5% contingency for the original bid on August 19, 2008 for the additional Hampton Circle work. The total indirect costs for the project were estimated to be $178,567.37 for the Feasibility Report. The actual amount of indirect costs is $200,000.00. H:\2007 ENGINEERING PROJECTS\BECKRICH PARK ESTATES\Assessments\Summary of Costs Assessment Beckrich Park Estates Sanitary Sewer & Watermain Extension Summary City of Shakopee Beckrich Park Estates Costs/Charaes/Funds to be Assessed Total Street & Utility Costs $ 491,978.49 Hampton Circle Reconstruction (Assessed at 30%) $ 13,101.45 Total Indirect Costs (0.85 * $200,000) $ 170,000.00 Total Trunk Sanitary Sewer Oversizing Reimbursement $ (17,417.97) Total Trunk Water Oversizing Reimbursement $ (14,662.50) Total Trunk Sanitary Sewer Charge (*) $ 77,832.44 Total Water Trunk and Connection Funds (*) $ 198,709.36 Total Amount to be Assessed = $ 919,541.27 Total Lots to Receive Even Apportionment of Assessment = 34 Total Assessment Per Lot = $ 27,045.33 Beckrich Park Estates Sanitary Sewer and Watermain Extension City of Shakopee, MN City Project No: 2007-10 City of Shakopee Capital Improvement Program 2007 -2011 Project Manager: Project Type: Project Title: Total Project Cost: Bruce Loney Storm Sewer Beckrich Park Estates/Stonebrooke $180,000 Draina e Control S stem A. Expenditure Items: 2007 2008 2009 2010 2011 Land & ROW 20,000 Construction 130,000 Improvements . Engineering/Admin. 30,000 Total - 180,000 - - - B, . Funding Source: General Fund Capital Improvement Fund Park Reserve Fund Grants (specify) Donations (specify) State Aid Assessments Sanitary Sewer Fund-Base Sanitary Sewer Fund-Trunk Storm Drainage Fund-Base 180,000 -...,J Storm Drainage Fund-Trunk ~ Tax Levy (X) Total - 180,000 - - - f Description: Construction of a drainage control system within the Beckrich Park and ~ Stonebrooke Additions. The system will utilize a combination of outlet control structures and pipe outlets. Justification: Developing properties in the area will produce more storm water run-off requiring outlets to be constructed from an existing wetlands. Ultimately, the outlets will reduce water running downstream to future developing properties It is recommended as part of the City's Comprehensive Storm Water Management Plan. Other Comments: Controlled outlets will better manage the storm water discharge rates and more fully utilize the upstream storage available in existing wetland areas. Operatina Costs: PROJECT LOCATION ..----<- - ----- --- -- - ----- .--.---- ..----.- ----.-- _.._-~- -- ~ ---~