Loading...
HomeMy WebLinkAbout5.F.10. Authorization to spend Building Funds for Fire Station #2 work Consent Business 5. F. 10. SHnKOPEE TO: Mayor and City Council Mark McNeill, City Administrator FROM: Kris Wilson, Assistant City Administrator DATE: 12/16/2014 SUBJECT: Authorization to Spend Building Funds for Fire Station#2 Work(F) Action Sought The Council is asked to authorize the expenditure of an amount not to exceed $32,000 from the General Government Buildings Fund for the installation of additional gutters, snow guards and heat tape at Fire Station#2 and related work. Background Professional building envelope and r oo f inspections were recently completed on several City buildings, including Fire Station#2. Following review of the report, quotes were obtained from three contractors to address the major issues associated with the roof and water drainage at the station. One of the major issues identified is the fact that the original design of the building did not include gutters or snow guards along the east side of the building. This is the side of the building where the two major entrances are and a long stretch of sidewalk, which is difficult to keep clear J g � p of melting snow and water. This project will address that shortfall, as well as several other minor issues associated with the roof and water run-off. One component of the project for which quotes were sought is not being recommended and that is labeled as "Issue #4." This would have installed flat metal panels along the top of the existing metal sun shades. While it would protect the sidewalk from snow and ice, staff is concerned that these have the potential to create additional hassles and may not be necessary once the additional gutters and snow guards are in place. Therefore it is recommended that the project proceed without the work identified as issue#4. Budget The lowest of the three quotes received was from John Dalsin & Son, Inc. for $29,420, after issue #4 is removed. A $2,580 contingency is also requested to pay for inspections services from Skyline Building Envelope Consultants and to accommodate any unanticipated issues. This amount can easily be accommodated within the General Government Buildings Fund. Relationship to Vision This is a housekeeping item. (F) Requested Action The Council is asked to authorize the expenditure of an amount not to exceed $32,000 from the General Government Buildings Fund for the installation of additional gutters, snow guards and heat tape at Fire Station#2 and related work. Attachments: Project Description Low Quote SKYLINE BUILDING ENVELOPE CONSULTANTS CONSULTING&PROJECT MANAGEMENT SERVICES FOR FACILITIES MANAGEMENT WHICH INCLUDE: ALL TYPES OF ROOFING&WATERPROOFING,BUILDING ENVELOPE&FACADE EVALUATIONS&RESTORATION, PARKING GARAGE EVALUATIONS&RESTORATION,FORENSIC EVALUATIONS. "CONTRACTOR SCOPE OF WORK PERTAINING TO THE ROOF ISSUES ON THE SHAKOPEE CITY FIRE STATION #2" City of Shakopee / Shakopee, Minnesota November 6, 2014 rot IP. w t+ .�._ x e f Y 7„1 3Y 15050 CEDAR AVENUE S./STE 116-3331 APPLE VALLEY,MN 55124 MOBILE: 952/210-7803 SKYLINE1221(a?MSN.COM WWW.SKYLINEBEC.COM #;y 4 {-)4 .- /44; — :- aq� s , SY. 4. 'h 4't 47,'4. �g.• fir- ', ' Y U) is I ... b-, Q- E i 113;•t • O CO H is-H 3 0 -H a) 3 U 0 4- 0 O Z 0 -H H 0 -H 0 -H -H OH 4-1 04J 0 > Q tr. .0 Q, 0 0 Q .0 O 4J4JCa 0 (E3 U) H (TS fd 1-4 U) H Ul >, rd Z .. Ul 0 4J - � rti U rd Pa N CL k 0 0 •H 4J -H 4-) -H 23 4J CC U 4 X 0 H W N u) a) O (3] S-1 X S-1 ..t 3 t a) 3 • U) E 4-J 4-) R$ S4 �-1 4-i >~ r d E ,.Q Q Cl, H 0 «S tr 0 "I✓• )6 4 ;': •u --- 0 r t S (1) 0 rd 0) X ,-� 0 3 Q) -H E -H 0 0 -H Z -- lit 4 rd s~ ,.~ r� H 4•) C G > 0 O tr O Qa r0 0 Q S4 a) N U r-I td . -4 0 3 4-) •H rt3 ,Q U) 4■ 0 • 0 0 0 4 -H $-1 23 O 44 023 Q., 4J ..0 cn x O b' N a) rd >1 H u) r� is 0 U 4) 4J rd H — N •H Q 0, U) 4) 3 • t3~') = ,0 0 Q -- U U) 0 -U -H 4 N H U 0 -H S- to 0 3 (d is a) 0 U) rd >1 O 0 E 0 3 >0'0 Hi (TS 44 H H 0 0) rn0 -H ° 3 N 0 + •H C) a) 4-, O O O N J ul - 0 ✓0 k u) 0 H 4-) r N -,-,--1 U) H ttJ) rd,tS a) 0 -H -- 023 r0 3 rn >i r 23 H N a) ... -(-) 0 0 N 4, 0 E a) L7 4-) }4 4- H a) a) >I U E 4J .0 -H a) 3 - U) 0 rd a) r-1 >i S4 -S-> -H rd a) a) >H O U) ,, >4 04-1 O 0) b)r0 O H 4- -H Z 0 Q,r-I H H 0 4-1 O 0 -Q - H Sa 5 4J -- O H Q •-1 a) rCS rd 0 X U? rd 0 rci 4J 0, -H N rd (Tj 4-1 4.4`_•• rd U) U H -H 0 -H O 4-4 0 0 -t-) 4J -H O 4-I $-1 .0 0 0 4J 0 0 4) I a) >i,O rd 44 -H O 4J is (r) ^ • r0 la U) rd H 0 Q 0 .Q 4J 3 ,C u) 0 4J m fiy s =j U) tr.1C-,. U) (d .Q 0 0 - a) 0 0 0 t~ -H 4J •H rd 0 0 - LW 0 U) -H S4 !-1 -H -H N ,. 0 rd -H S-I to S4 (TS Q 4-1 a) 3 -H M 0") UJ Z rd H 0 4-) X Q 0 4- (n 4J -H Q, r� rd 5..1 Q tr > U) a Ql td a) G. 0 S•4 -H rzi a) tr 04-4 U) 23 4J U) r0 rO 0 • H 4) 4J 3 0 0 -H -H 0 U) k rd Sa 0 0 S-1 O O >I is Q ,Q N 0 >14-) 4- lea H 4.) U) rd >1-H 23 X rd •H 0 > 0 H rd Q,-u H N -H t~ (d N H a) • O „* I-. RS O H 4-1 rd a) 0 > 0 Q H Qa 0 -H O S4 H O 4-) 0 E ✓s 4J is 0 rd 4J -H U) 4J Qa Q .0 0 H 0 rd ,Q rd .0 4-1 0 4-) Si H •H (I) 4J c= U) a) 023 -H U) 0 H rd 4J a) 4J 4J rd Q, O tT U) '0 rd 4-1 > Qa (d 01 23 '„. 0 4J 0 u) O X 0 O H 4-1 tr rn m m 4-1 r0 • -H 0 0 rd rd -H E Q 0 ; -H -H tt) 5 O E 0 N H RS H 4-) rd O Q rO - rd X is U) U) U ,0 H -H -H H (d (dH -H H 0 0 U) 44 -H H rd a) r) tr 0 rd a) 0 U) X 4J H *771-_.-.--. H }-1 0 0 O HI ,L 41 0 S H H rd r---I ,..0 CD f-1 O E H H O U) rd . r-I JJ H 44 H 3 (d RS 023 0 RS Q U H. (NI ,. rd •H a) H 0 S4 -H -IJ rd H a) rd a) 0 0 . H Qa W S4 4 -H (d N U tT H ) (d 4J (2 > U) . -H -H H O ,.t~ O -0 0 r0 U) (d U) U) (d U) U) 4-1 • 4J a) U) -H .O -H Qa 0 S~+ U) (d O U1 U) 41 0 4.4 4--) -H O rd 4J H rd (d 4-1 23 >1 N 3 rd -H 1 TS 2S ,. (d 23 Sa 0 a) ,~ Qa ?, S4 .Q (d 0 E O -H U) . a) + ' a ( 0 0 in 0 $4 0) 4-1 O 4J 0 4- X 0 O 4J Q Q U) 4J (J H ,.1~ >, E 1 0 0-, (0 0 0 0 U) Q.4, Q 0 .4 4, .Q rd -H H U) tr •-■ 4J 0 0 H 4J ■ 4J 0 - 4) 4J ,0 -H 0 U 0 U) 0 4J U 0 •H • 4 H 0 0 0 > (d 3 H '' .t O O U) 0 U 4- CI (d 4J O ,-1 rti 4J •H 4J ((3 23 Hr� 4-) O CL O 4-1 4-1 0 H RS H 4J a) -H Ri S4 0 E r0r1 S-i rd ?C H a) ki (d 0 X -H ,O -H Z 4J SD, U) t.) U1 O O (d 1 S-1 0 4J (d S4 0 -H a) }., 4J E U (I) (d C) 4J O 3 O 3 m U) U 0 U) O 4~ .0 , -N a) 0 U) E 4-) 4J 4) (d 0 -H O (d 0 0 0 i-i H is !~ 3 H -H 0 0 to I f" H Q, > 0 J m O X 4, 0 0 0 0 3 Oa E S4 Ste' Z" 3 O 0 • S_Z 0 mo r 0 .Q u) U) rd 0 0 0 >) E U 0 U) H -H U O U) Q, a) a) 44 to C O r0 a) .. '20 0 4J E "" U 0 O U .tom, Qa U) a) S-1 rd U) H (d 4J 4J 0 -H 'o -1-) H 0 H a) '' ,�P' °' O 3 a) 0 4J 4J H Qa 4-) Q,H H 4-a 0 U) +-) 0 3 (d S-I U) 0 rd m E 4J • ) r;�. i H r0 O H •H H Q) 0 U) (d Qa aS ?(•H 0 al (J O ... 0 >- 0 u) O • ( 10 0 3 O W ,y y S# (d 23 .Q al 0 is H >14-) rd H Q, i-i 0 4-) 0 -H 5..1 4J U) 0)) H O 0 4rJ, ... 0 0 4J S4 >y , U . (d tr 0 -H (d U) Z "4-1 0 4J (d 0 > 4J O rd ob H 0 3 N Y, 4J rC3 U) U) 4-I Vl $s.`': -H : 3 U 0 -H S-I (d Z C U) Qa Z 0 rd • U ( 3 0 -H 0 •H 0 -H -H rd (d • . i" S-4 E 0 -H S4 E (d U J ,O 0 (CS U -H a) a) .>~ FL, 4J Z U) U 3 (n ,- a) a) 23 § ±.'. 4J a) 0 4J 23 4-) a) tr a) 4.) -1-J N O rH J (1) 0 4-1 S•4 4-) [ 4,4 U Oa S- C) 4-) rd H U 4J 4J 4J QI tr O H U a) tr H O .Q 4-1 S-1 S-4 0 O rd - 0 U) (1) 0 •H 0 Ul 0 rd 4) 0 0 0 0 rd 0 0 (TS 4-1 O • • • 0 0 H 0 • Sr ' H >+.� = H >I-C 0 .. a) S4 ..c 4J rd 0 Oa) 0 0 0 W U 04 4J U i 0 ( x;, W U) 4-)- A W W 4J 0 CD m H Q m u) co m tr-H )• • •y (v) L-) l0 P • •.•,7.7-7°•.':',t • • ''• •---•---••••`' , • .44„, •. • ••:?; ;•- • s' • e • a_z 0 2 = , • = 4 •• 1_ ' Purchase & instal l ; a", e, i . , approxmately 93 ' •`, `. ,t ' of "S-5 k\`ColorGard `'.. ' System with LMClamps" / f;" or approved equal. g t. .r. . .. y i ,: GoogIe earth Go 1'e earth feet X100 )k O meters' 50 1 � _ SKYLINE BUILDING ENVELOPE CONSULTANTS CONSULTING&PROJECT MANAGEMENT SERVICES FOR FACILITIES MANAGEMENT YYHICH INCLUDE: ALL TYPES OF ROOFING 8 WATERPROOFING,DUILJ�NG ENVELOPE&FACADE EVALUATIONS&RESTORATION, PARKING GARAGE EVALUATIONS&RESTORATION,FORENSIC EVALUATIONS. Issues on all the various roof sections: ISSUE #1: On this overflow scupper is huge, way over-sized; appropriately sized catch basin and downspout should be fabbed and installed on the exterior brick masonry wall. Install double looped heavy duty heat cable system in catch basin and down!up the new downs•out. ryY t _ y9� ' .. .. +��" ', n2frCH cmµ-t, .b �Y� . y , r � r ♦t. 3 .al ,,,� 1 ... ..... x-Ill,' s t , ..h aw. Y 3^�3.. ,mod :.Y.*'" �` ✓ ...r4'"'y.;r y.^"'r'" j .r ._.i r" Jam 173 IF ' .- x.• . -. _ •— zr 4 J ......�..„,.. w..-...... a_ tv- i �..__ ... ''''� . : bra } s 1 �x m-0.,- ax'' "14,,,„,,,_ ISSUE #1A: Install heavy duty heat cable, two parallel runs at base of new large catch basin and down new downspout and back up. ISSUE#2: Fabricate and install a heavy duty sloped rain gutter system all along the east elevation of the existing metal roof system, within an outer decorative kynar gutter (with at least two expansion joints) to match the kynar color of metal roof system and install three large downspouts which will dump water onto the adjacent landscaping or into a foot wide concrete trench covered with appropriate treaded steel cover which will drain onto the asphalt pavement. I 1ff?'�,,.,. fir' 4-,-, k =.71 ' i . IF ISSUE#2A: Install heavy duty heat cable,two parallel runs at base of new gutter system and down all three downspouts and back up; including back and fort h within the new steel trough installed in the sidewalk. ISSUE #3: Install appropriate heavy duty snow guard system on east sloped metal roof system per LM 'all - '-1 /I Curb manufacturer's requirements and as specified on attached photos. .tea• • F.., ,ry s'v l"qk 35 a ISSUE#4: Fabricate and Install over the existing Sun Screen louvers all along east elevation,from between each steel support framing new 22 gauge kynar metal panels to match existing. T 3 iii ` h ,;(0,'4' '' t �s fir,'aF tic' zi .ate' ISSUE#5: Replace the existing heat cable in the rain gutters along north &south elevations, in some areas are wedged up and under the metal roof panels; also, the new heat cable should be a double run (double looped)for the entire length of the gutter systems and should be laying at the base of the gutter not on top of the hanger straps; also run the new heat cable double looped up and down the existing downspouts. Perform work to fix existing issues as explained. m 1 I i I ' 'i'c'',..."!i',.,„,-,,,,.;3,,L, ,::::::::.-:,,,,v1:‘,"4„,';:l'',--,:,,,,,,,...--.- --- 5tx, 1 :.,, ,,,,, ,,,,,, . : '''',-.,. F • a' k Ci - .4 Llialiti ili:#': . 15050 CEDAR AVENUE S./STE 116-333/APPLE VALLEY,MN 55124 MOBILE: 952/210-7803 SKYLINE1221eMSN.COM T F REVISED QUOTE SUBMITTAL FORM TO BE EMAILED TO: Ms. Kris Lyndon Wilson Assistant City Administrator City of Shakopee, MN. 129 Holmes St.South Shakopee, MN. 55379 kwilsonaShakooeeMN.00v Quote form due by 3 PM on November 21,2014 SUBMITTED BY: Company: John A.Dalsin&Son, Inc. Address: 2830 South 20th Ave ue M. neapolis,MN 55407 Authorized Signature: Phone Number: 612-729-9334 Email Address: dougddalsin.com ISSUE #1: On this overflow scupper, appropriately sized catch basin and downspout should be fabbed and installed on the exterior brick masonry wall; or per addendum #1. Total Cost = $ 2,030.00 ISSUE#1A: Total Cost to install heavy duty heat cable system in newly installed catch basin and up I down newly installed downspout; or per addendum #1 $ 2,400.00 ISSUE#2: Fabricate and install a heavy duty sloped rain gutter system all along the east elevation of the existing metal roof system, within an outer decorative kynar gutter (with at least two expansion joints) to match the kynar color of metal roof system and install three large downspouts which will dump water onto the adjacent landscaping or into a foot wide concrete trench covered with appropriate treaded steel cover which will drain onto the asphalt pavement; or per addendum #1. Associated cost to perform specified work=$ 11,450.00 ISSUE #2A: Total Cost to install heavy duty 12 watt heat cable system (double looped) in newly installed rain gutter system along the east elevation of the existing metal roof system and up I down newly installed downspouts=$ 5,540.00 ISSUE#3: Install appropriate heavy duty snow guard system on east sloped metal roof system per LM Curb manufacturer's requirements and as specified. Associated cost to perform specified work =$ 3,900.00 ISSUE #4: Fab and install over existing Sun Screen louvers along east elevation (where there are none,from between each steel support framing) new double layered 24 gauge kynar metal panels to match existing; or per addendum #1. Associated cost to perform specified work = $ 3,150.00 ISSUE #5: Reinstall existing Heat cable in the rain gutters per addendum #1, in some areas the existing are wedged up and under the metal roof panels; also, install additional new heavy duty 12 watt heat cable, which should be single run and should be laying at the base of the gutter not on top 1 of the hanger straps. Associated cost to perform specified work= $ 4,100.00 GRAND TOTAL COST OF PERFORMING THE WORK SPECIFIED WITHIN THIS SCOPE OF WORK, ADDENDUM #1 AND THIS ROUTE FORM FOR ISSUES #1, 1A, 2, 2A, 3, 4 & 5 $ 32,570.00 In submitting this quote, it is understood that the right is reserved by the Owner to reject any and all quotes and it is agreed that this quote may not be withdrawn for a period of 60 days after the date of filing the same. All Addenda shall become part of the quote and the work, and shall be acknowledged here in the spaces provided. I A quote shall be rejected if it contains any alteration or erasure unless the alteration or erasure is corrected as herein provided. An alteration or erasure may be crossed out and the correction thereon printed in ink or typewritten adjacent thereto and initialed in ink by the person signing the quote. The person signing the quote shall also file a certificate with the quote explaining the correction of the alteration or erasure. If a Corporation, what is the State of Incorporation: Minnesota If a Partnership, state full name of all co-partners: FIRM NAME: John A. Dalsin &Son,Inc. OFFICIAL ADDRESS: 2830 South 20th Avenue Minneapolis.MN •07 AUTHORIZED SIGNATURE: /l. • Brian Bar • TITLE: Vice President DATE: 11/21/2014 2