HomeMy WebLinkAbout6. CIP-Park & Recreation
:, tl-G
CITY OF SHAKOPEE
MEMORANDUM
To: Mayor and City Council
Mark McNeill, City Administrator
From: Mark Themig, Parks, Recreation, and Facilities Director
Meeting Date: August 22, 2006
Subject: 2007-?011 Parks CIP
2007-2011 Parks CIP
Andrea Weber and I have completed updates to the 2007-201 t CIP that reflect Council's
decision to move forward with Huber Park. In addition, we have analyzed in more detail
the projects planned for 2007 in order provide more accurate cost estimates. Finally, we
have made adjustments in timing based on funding and workload, Key changes in the
CIP are as follows:
Pro.act Modification
Huber Park · Expenses continued into 2007
construction season.
17th Avenue Sports Complex Building · Expenses continued into 2007
construction' season.
Aquatic Park Building* · . Expenses continued into 2007
construction season.
Tahpah Park · Added baseball field funding from park
reserve in 2007 to meet potential
rriatchin rant re uirement.
Quarry Lake Project . · Deferred design funding to 2007.
· Added park reserve funding for project
to meet matching grant requirements.
· Moved construction to 2008 to meet
rant re uirements.
Southbridge Park Development · Moved park development up from 2008
Dean Lakes/Southbridge Trail Connection to 2007 and deferred trail connection to
2007. This would provide efficiency and
cost effectiveness by combining all
ro'ects.
Lions Park · Added 2nd ice sheet in 2007 based on
Hockey Association request with
contribution from the Association.
· Added indoor tennis facility in 2011
based on Tennis Association re uest.
Glacier Estates Park · Deferred to 2007 due to work load.
Off-Leash Do Area · Deferred to 2007 due to work load.
Park Si na e · Deferred to 2007-2008 due to work load.
Westchester Park · Construction remains planned for 2007.
.U dated cost estimates.
Greenfield East Park · Construction deferred to 2008 due to
funding.
· U dated cost estimates.
· U dated cost estimates.
· Deferred to 2011 from 2010.
· Deferred to 2011from 2010.
· Added in 2011.
Overall, the proposed CIP provides funding to continue construction of our undeveloped
parks. However, that funding is contingent on park dedication revenue from upcoming
developments. If revenue slows, projects will need to be delayed.
Also, City Council will need to provide direction onhow itwants tohandle the MN/DOT
Parcel 75 Assessment, should that land be conveyed to the City. Bruce Loney reviewed
the file on the assessments which shows that MNIDOT was assessed for 35.89 acres of
the -50 acre parcel. The developer was assessed the remainder. The outstanding
assessment is $368,000, which is not included in the proposed CIP. If Council wishes,
we can modify the proposedCIP schedule to defer a project (or portions of a project) in
order to pay the assessment from the Park Reserve Fund.
Parks and Recreation Advisorv Board Review
The Parks and Recreation Advisory Board discussed the proposed CIP at their July
meeting. They gener~i1ly co.r1curred with the proposed plan, with the following comments:
· Recognized potentfal concern with delaying Greenfield East park to 2008, and
discussed the possibility of doing a temporary rink at the park. (Not all of the park site
has been graded yet. Once that is done, then we will need to determine the feasibility
of this.)
. Directed staff to follow-up on the feasibility of the Blue Lake site for an off-leash area.
(Still to do.)
. Expressed an interest in completing construction of the Dean Lakes/Southbridge trail
connection and bridge crossing this year if at all possible. (Discussed with
Engineering the possibility of assistance with the design. Due to their work load, this
is not feasible.)
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Greenfield West Neighborhood Park 15,000
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements
Engineering/Admin.
Total - - - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 15,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 15,000 - - - - -
DescriDtion
This project is developing the west park in the Greenfield Development. The park is approximately 4 acres.
Construction: $330,000 (Park Reserve- construction budget bid=$240,304.80, + indirect costs=$20, 171.40 )
tennis court, basketball court, trails, landscaping, surveying, testing, utilities
Play equipment $98426.47 (Park Reserve)
Engineering/Admi: Design and construction administration of park development (5% of total project costs,
included in indirect costs, above) (Park Reserve)
Justification
This provides for development of a park in the Greenfield development, which is built out.
Other Comments
2005 payments totalled $173,917.60 (Contractor) and $98,426.47 (Playgrounds) and survey staking
$3,650.00= $275,994.10
,Remaining 2006 project costs $76,833.13 remaining bid payments+3,095 Utilities=$79,928.13 total
(remaining as of 5-06, $16,976.75 +5% retainage $12,893.15* (*Iess liquidated damages of at least $13,000),
+ testing and utilities (WCC, electrical UG service, BP and testing=$3095 budgeted)
ODeratina Costs
Estimated yearly operating costs: Labor $10,000 + Equip/Supplies $5,000 p= $15,000
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Church Addition Neighborhood Park 205,000
Year Added to CIP: 2006
A: Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 200,000
Improvements
Engineering/Admin. 5,000
Total 205,000 - - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 5,000
Grants (specify)
Donations (specify) 200,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - -
DescriDtion
This project would develop the Church Addition Park.
Construction: $200,000 (By Developer for Park Dedication Credit)
Play equipment, court, trails, picnic tables, Shelter, water fountain, landscaping
Engineering/Admin: Plan review and construction adminstration (2.5% of total project costs) (Park Reserve)
Justification
This provides for development of a park in the Church Addition, which is estimated to be built out in
2005/2006.
Other Comments
Developer is required to design and construct park as part of the development. Developer would be credited
construction costs toward total park dedication fees of $214,000. Estimated Improvements are $200,000 plus
staff administration (2.5%) for a total of $205,000.
ODeratina Costs
Estimated yearly operating costs: Labor $5,000 + Equip/Supplies $2,500 = $7,500
City of Shako pee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Valley Creek Crossing Neighborhood Park 123,000
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements 120,000
Engineering/Admin. 3,000
Total 123,000 - - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 3,000
Grants (specify)
Donations (specify) 120,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 123,000 - - - - -
DescriDtion
This project would develop the Valley Creek Crossin g Park.
Construction: $120,000 (By Developer for Park Dedication Credit)
Play equipment, trails, picnic table, landscaping
Engineering/Admin: Plan review and construction adminstration (2.5% of total project costs)
Justification
This provides for development of a park in the Valley Creek Crossing development, which is estimated to be
built out in 2005/2006.
Other Comments
Developer is required to design and construct park as part of the development. Developer would be credited
construction costs toward total park dedication fees of $128,358. Estimated Improvements are $120,000 plus
staff administration (2.5%) for a total of $123,000.
ODeratina Costs
Estimated yearly operating costs: Labor $5,000 + Equip/Supplies $2,500 = $7,500
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Countryside Neighborhood Parks (3 Parks) 675,475
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 659,000
Improvements
Engineering/Admin. 16,475
Total 675,475 - - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 16,475
Grants (specify)
Donations (specify) 659,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 675,475 - - - - -
Descriotion
This project would develop three parks that will serve the Countryside development.
Construction: $659,000 (8/05 estimate) (By Developer for Park Dedication Credit)
Northeast Park: $305,000 (gazebo, playground, basketball, trails, landscaping)
Northwest Park: $236,000 (pergola, playground, trails, 1/2 court basketball, landscaping)
Southwest Park: $118,000 (playground, trails, bridge
Engineering/Admin: Plan review and construction adminstration (2.5% of total project costs) (Park Reserve)
Justification
This provides for complete development of three parks in the 427 home Countryside development, which is
estimated to be built out in 2007.
Other Comments
Developer is required to design and construct park as part of the development. Developer would be credited
construction costs toward park dedication fees of approximately $1,314,330. Estimated Improvements are
$659,000 plus staff administration (2.5%) for a total of $16,475.
Ooeratina Costs
Estimated yearly operating costs: Labor $10,000 + Equip/Supplies $5,000 = $15,000
City of Shakopee Capital Improvement Program 2006 . 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Special Facility Construction Tahpah Park Improvements 2,055,480
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 1,565,980 170,000
Improvements 280,000
Engineering/Admin. 25,500 14,000
Total 1,565,980 195,500 - - - 294,000
B. . Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 455,250 95,500 294,000
Grants (specify) 100,000
Donations (specify) 54,340
State Aid
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy 1,056,390
Total 1,565,980 195,500 - - - 294,000
DescriDtion
2006- This project makes improvements to Tahpah Park, including one new baseball field, extending softball field fences, installing lights,
reconstructing parking lot, and replacing play equipment. Costs based on actual bid amounts and Engineering/Admin. $54,342.15 have
been committed to this project (WMN 6142.15, M/C-R $11,600, and JC $25,000).
2007- Baseball field Construcion, $170,000+10% and 5% D&CA=$195,500 (Anticipates donation of Labor for some work.)
2011- Light fields 7 and 8 $294,000
Justification
The original parking lot has exceeded its life expectancy of 20 years, and there is a portion of the lot that has never been finished.
Unfinished gravel parking does not meet city ordinance. The play equipment did not meet current safety standards and was removed in
2004. Additional field lighting increases the available use of existing fields, extending fields will allow for adult toumement play.
Other Comments
Shakopee Youth Baseball Association Women's Sorftball and Mens/Co-Rec softballlall have made donations to the 2006 project, Youth
Baseball and Public Works are interested in labor contribution to Youth Baseball Construction.
ODeratinCl Costs
The estimated operating costs for additional baseball field is approximately $2,000 per year. Lighting two softball fields with lights would add
$800 per year for operating 4 nights per week.
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Mark Themig Park Redevelopment Huber Park and Riverfront Redevelopment 5,649,032
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 1 ,490,402 2,158,630 2,000,000
Improvements
Engineering/Admin.
Total 1 ,490,402 2,158,630 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 1,490,402 1,490,402
Grants (specify) 226,500 2,000,000
Donations (specify) 236,858
State Aid
Assessments 204,870
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 1,490,402 2,158,630 2,000,000 - - -
DescriDtion
This project continues development of Huber Park, including grading, installation of a performance area, landscaping, trail
connections, parking, and riverbank stabilization. The project would be done in two phases:
2006/2007 - Construction, Phase 1: Park, buildings, streets, parking lots, utilities, boat launch. (Eng/Admin included in
construction costs.) Bid awarded July 2006.
2008 - Construction, Phase 2: River bank stabilization.
Justification
Redevelopment of focal park for the community.
Other Comments
Bids awarded in July 2006 for Phase 1.
ODeratina Costs
Estimated year operating costs:. Labor $15,000 + Equip/Supplies $5,000 = $20,000
Funding for performances and coordination of performance schedule has yet to be determined.
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Mark Themig Special Facility Construction Archery Range Relocation 122,000
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 111 ,000
Improvements
Engineering/Admin. 11 ,000
Total 122,000 - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 82,000
Grants (specify) 20,000
Donations (specify) 20,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 122,000 - - - - -
DescriDtion
This project relocates the archery range to the north side of the Minnesota River and uses the boat landing
improvements for access.
Design and Construction: (DNR Grant, Donations, and Park Reserve)
Roadway a.nd Parking Lot
Clearing and grubbing
Site amenities (targets, picnic tables, signs. etc.)
Justification
Replaces range removed from Lions Park due to safety reasons. Many archers have been in contact about
replacing the range.
Other Comments
DNR has committed $20,000 toward project. Local donations from the Scott County Chapter of the
Minnesota Deer Hunters Association and other organizations are anticipated at $20,000. City's $35,000
contribution would provide a paved roadway that would reduce long-term maintenance costs, which is
important due to flood plain location. Roadway would be bid with Huber Park redevelopment.
ODeratina Costs
Estimated year operating costs: Labor $1,000
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Mark Themig Special Facility Construction 17th Avenue Sports Complex 835,000
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 265,500 265,500
Improvements 300,000
Engineering/Admin. 7,500 7,500
Total 273,000 273,000 - - 300,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 267,500 267,500 300,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 267,500 267,500 - - - 300,000
DescriDtion
2006/2007: This project would provide funding for completion of the 17th Avenue Sports Complex.
Construction: Completion of Phase 2, $520,000 (Park Reserve)
Building, inc. permits -$492,000
Water and Sewer Fees - $13,000
Fencing and site work - $10,000
ADA Modifications - $5,000
Engineering/Admin: Architectural fees $15,000 (Park Reserve)
2011 Field Lighting, $300,000.
Justification
This project completes the development of a major sports complex that will serve the City's needs for many
years. The building will need to be constructed of durable materials that will stand up to public use, as well a
abuse (vandalism). Costs reflect similar buildings.
Other Comments
There was an extensive design process that produced the original design for the building, which bid insprin9
2005. Low bid ($528,000) was overbudget. On June 7, 2005, City Council set a maximum construction
budget of $520,000 for Phase 2.
ODeratina Costs
Estimated operating costs: $5,000
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Mark Themig Land Acquisition and Development Quarry Lake Park and Special Use Facility 1,696,000
Year Added to CIP: 2005
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 500,000 460,000 460,000
Improvements 10,000 10,000
Engineering/Admin. 14,000 100,000 14,000 28,000
Total 10,000 24,000 600,000 474,000 488,000 -
B.o Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 10,000 24,000 289,500 14,000 28,000
Grants (specify) 210,500 180,000 280,000
Donations (specify) 100,000 280,000 280,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 10,000 24,000 600,000 474,000 588,000 -
DescriDtion
This project would provide funding for acquisition of the restored Aggregate Industries quarry site, and
funding for future development.
2006 - Site Cleanup
2007 - Site Cleanup and Design Work
2008 - Construction (from 2004 Concept Plan cost estimates): $1,680,350 (Donations and Grants )
Infrastructure (bridge, roads, parking, utilities)- $630,000
Trails (bituminous and boardwalk) - $625,350
Plantings (shoreline and site) - $124,000
Site Amenities (picnic tables, grills, fencing, signage, etc.) - $301,000
Engineering/Admin: Design and const. administration of improvements (25%)
Donation: Bituminous Roadways contribution for roadway construction to provide secondary access to plant.
Justification
This project would acquire and develop facility as recreational amenity for the city. Work proposed for 2008
would be coordinated with the Watershed District's plans for channel improvements, and meet our t1imelinE
for grant expenditures.
Other Comments
Funding sources include grants and partnerships with committee members. $92,000 DNR grant awarded in
2005. $78,500 DNR Grant, $30,000 Xcel grant, $10,000 Polaris grant in 2006. All costs listed are estimates.
ODeratina Costs
Costs would depend on scope of development.
City of Shako pee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Community Park Project Title: Total Project Cost:
Andrea Weber Improvements Lions Park Improvements 791,250
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 50,000
Improvements 10,000 185,000 500,000
Engineering/Admin. 46,250
Total 10,000 231,250 - - 50,000 500,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 195,250 50,000
Grants (specify)
Donations (specify) 10,000 36,000 500,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 10,000 231,250 - - 50,000 500,000
Descriotion
Lions Club has plans for continued improvements in Lions Park.
2006 -Improvements; Entrance and shuffle board court, $10,000 (Lions Club donation), Bocce courts
(donation)
2007- additional hockey rink $180,000 -(donation of concrete cost and labor, $36,000) + ADA Upgrades to
restrooms $5,000 (park reserve) 25% design.Admin (Hockey Association Request)
2010 - Construction of additional picnic shelter (Lions Club) coordinated with construction of fire station
parking area.
2011 - Indoor Tennis Facility (Tennis Association Request) to be constructed along Adams Street.
Justification
Projects have been identified by Lions Club and Youth Hockey Association, and would serve park users.
Other Comments
Proceeds from Lions Park land sale in 2003 ($41,000) have been deposited into Park Reserve fund and
should be used to help fund future park improvements. Lions requested use of $5,000 in 2007 for restroom
upgrades.
Ooeratina Costs
Estimated year operating costs: 1,000.
City of Shakopee Capital Improvement Program 2006 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park and Trail Development South bridge Area Park Development 1,209,310
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 140,000 846,200
Improvements 20,000
Engineering/Admin. 7,000 196,110 - - -
Total 147,000 1,042,310 20,000 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 147,000 1,042,310 20,000 -
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 147,000 1,042,310 20,000 - - -
DescriDtion
This project would develop several park areas in the South bridge Development, including the MNDOT 75 parcel.
2006 - Savanna Oaks Tot Lot in Southbridge, $140,000 +5% Design and construction admin, $7000, $147,000 (Park
Reserve)
2007 - Trail from Cambridge Road to Whitehall Road along gas easement to connect to school trail, 2600LF @
$27/LF=70,200+10% (inflation per year), $77,200+5% Design/Admin, $3860, $81,060 (Park Reserve)
2007 - Park at Southbridge Pkwy : Hockey/basketball w light 180,000, shade structure 30,000, Water ftn & water service
15,000 and Plantings 20,000, concrete andtrails, $20,000, earthwork, 30,000, site furniture 15,000, = $310,000 plus 25%
design and admin $77,500, total $387,500 (Park Reserve)
2007 - Construction: MNDOT 75 parcel 2 mi trail @ 27/LF=285,000, 1 small picnic shelter, $30,000, lights at kiosk 14,000
total site furn and interp signage 30,000, sod and plant resto $25,000, 25 space parking @$75,000= $459,000+plus 25%
design and admin, $114,750 = $573,750 (Park Reserve)
2008 - Improvements: Installation of fishing pier, $20,000 (DNR Fishing Pier Grant)
Justification
In 2001, the City worked with residents to prepare a master plan for the South bridge area. The improvements identified in
this project are a portion of the overall master plan
Other Comments
Estimated cost for total development of the system based on the master plan is $3 million (2001).
ODeratinQ Costs
Estimated costs: Labor $50,000 + Equip/Supplies $25,000 = $75,000 (when fully developed)
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Trail ProjectTitle: Total Project Cost:
Andrea Weber Trail Construction Dean Lake Trail System (North Segment) 230,475
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 219,500
Improvements
Engineering/Admin. - 10,975
Total - 230,475 - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - 230,475
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 230,475 - - - -
Descriotion
This project would construct a trail in the Dean Lake area to connect with trail being constructed as part of the
west Dean Lake developments.
Construction: $198,700 (Park Reserve)
Paved trail from Wakefield to the west side of Dean Lake. Trail would be bituminous with a bridge
to cross the outlet channel.
Trail Construction at $30/LF for 2800 feet=$84,000
Bridge 10' wide by 20' long+ bridge footings 20,000=$135,500
Engineering/Admin: Design and engineering, (5% of project cost) (Park Reserve).
Justification
Identified in South bridge Master Plan. Trail through Dean Lakes Development is constructed and dead ends
at city property. This would provide trail connections to Southbridge.
Other Comments
Work would be conducted after planned Dean Lake outlet channel control structure is installed.
Qoeratina Costs
Estimated costs: Labor $1,000
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Glacier Estates Neighborhood Park 112,750
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements 110,000
Engineeringl Admin. 2,750
Total - - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 2,750
Grants (specify)
Donations (specify) 110,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 112,750 - - - -
DescriDtion
This project would develop the Glacier Estates Park as part of the development.
Construction: $110,000 (By Developer for Park Dedication Credit)
Play equipment, trails, picnic table, landscaping
Engineering/Admin: Plan review and construction adminstration (2.5% of total project costs)
Justification
This provides for development of a park in the Valley Creek Crossing development, which is estimated to be
built ouUn 2006/2007.
Other Comments
Developer is required to design and construct park as part of the development.. Developer would be credited
construction costs toward total. park dedication fees of -$115,000. Estimated Improvements are $110,000 plus
staff administration (2.5% of project costs).
ODeratina Costs
Estimated yearly operating costs: Labor $5,000 + Equip/Supplies $2,500 = $7,500
City of Shako pee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Mark Themig Special Facility Construction Off-Leash Dog Area 15,000
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 15,000
Improvements
Engineering/Admin.
Total - - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund
Grants (specify)
Donations (specify) 15,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 15,000 - - - -
DescriDtion
This project creates the first off-leash dog area for Shakopee. Potential sites include land north of
Memorial Park along the Minnesota River (easement restrictions to be resolved), land owned by
Metroplitan Council adjacent to the Blue Lake water treatement plant, open space in South bridge,
and potentially a small portion of Lions Park.
Construction:
2007 - Site TBD, $15,000 (using salvaged fencing from Tahpah Park)
Justification
This project responds to resident requests for a legal place to run dogs off leash.
Other Comments
Mostlikely would begin with a single site and evaluate need for additional sites in the future.
ODeratina Costs
$500/site per year.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Improvements Park Signage 70,000
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements 35,000 35,000
Engineering/Admin.
Total - 35,000 35,000 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 35,000 35,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 35,000 35,000 - - -
Descriotion
This project provides funding for designing and installing new park signs for all park locations.
Improvements, $70,000 (Park Reserve):
Neighborhood Park Signs, 20 @ $2,500 ea = $50,000
"'\. (.... Community Park Signs, 4 @ $5,000 ea = $20,000
I~:-..-J .......--...._/ '..-.,
Justification
This project would standardize signing for all parks and help create uniform identity for park areas.
Other Comments
Work would be coordinated by intern included in 2007 operating budget and overseen by Andrea Weber.
.,..:,~ 1 Ooeratina Costs
\, (included in general park maintenance)
I---/~
UJ
J<'"'1
City of Shako pee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Providence/Westchester Community 1,087,500
Year Added to CIP: Park
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements 870,000
Engineering/Admin. 25% 217,500
Total - 1,087,500 - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - 1,087,500
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 1,087,500 - - - -
Descriotion
This project would develop the park that will serve both Providence Point and Westchester developments. The
park is approximately 12 acres.
Park Construction: Play equipment $75,000, 2-240' Ball fields $160,000, Ball field irrigation $30,000,
1 combined hockey/BB rink w light $180,000 Lighting $30,000, Planting, $20,000, earthwork
$30,000, trails and walks $20,000 and prefab toilet/storage building $250,000, parking, $75,000
total $840,000
Engineering/Admin: Design and construction administration of park development (25% of total project
costs, which includes additional costs for design of building staking, testing, etc.) (Park Reserve)
Justification
This provides for development of a park in the Providence Point and Westchester developments, (also serving
ACC development) which is estimated to be built out by 2006.
Other Comments
Actual park amenities would be determined in planning process with residents. This park will likely serve as a
location for organized activities such as youth sports.
Ooeratina Costs
Estimated yearly operating costs: Labor $15,000 + Equip/Supplies $10,000 = $25,000
City of Shakopee Capital Improvement Program 2007. 2011
Project Manager Project Type: Project Title: Total Project Cost:
Andrea Weber Park Development Greenfield/Park Meadows Community 1,231,250
Year Added to CIP: Park
A. Ex enditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements 985,000
Engineering/Admin. 25% 246,250
Total - - 1,231,250 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 1,231,250
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - 1 ,231 ,250 - - -
Descriotion
This project would develop the east park in the Greenfield Development, which is adjoined by 8 acres from
Park Meadows, for a total of 13 acres.
Construction: $1,293,750 (Park Reserve)
Play equipment $50,000, 2-260' Ball fields $180,000, 1 hockey/BB rink wlight $180,000,
Lighting $30,000, Planting, $30,000, earthwork $30,000, trails and walks $30,000,skateboard
street area, $100,000, and prefab restroom/warming building $250,000, parking $75,000, ball field
irrigation $30,000 total $985,000
Engineering/Admin: Design and construction administration of park development (25% of total project costs,
which includes additional costs for design of building) (Park Reserve)
Justification
This provides for development of the second park in the Greenfield development, which is estimated to be
built out in 2005, and neighboring developments to the east.
Other Comments
Actual park amenities would be determined in planning process with residents. This park will likely serve as a
location for organized activities such as playground programs and youth sports.
Ooeratina Costs
Estimated yearly operating costs: Labor $15,000 + Equip/Supplies $10,000 = $25,000
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Improvements O'Dowd Lake Community Park Improvements 412,500
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 330,000
Improvements
Engineering/Admin. 82,500 - -
Total - - 412,500 - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 412,500 -
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund- Trunk
Tax Levy
Total - 412,500 - - -
DescriDtion
This project would develop O'Dowd Lake Park with larger picnic shelters and parking.
Construction: $462,000 (Park Reserve)
Two large picnic shelters 160,000, Site furniture $20,000, 50 car parking @ $3,000/space=$150,000,
total $330,000 + 25% Design/Admin, $82,500: $412,500 (Park Reserve)
Justification
This community park is located on the shores of O'Dowd Lake. The city has made improvements at the site
over time including trails, canoe launch, retaining walls, fishing pier, and stairways.
The city built a temporary parking area and restricted vehicle traffic in 2003.
Other Comments
ODeratina Costs
Estimated yearly operating costs: Labor $10,000 + Equip/Supplies $5,000 = $15,000
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Trail Construction CR 79 Trail 257,500
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW 100,000
Construction 150,000
-Improvements
Engineering/Admin. 7,500
Total - - 257,500 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 257,500
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - 257,500 - - -
Descriotion
This project will design and construct a segment of the trail from CR 78 to O'Dowd Lake Park.
Land & ROW: Acquire needed easements, $100,000 (Park Reserve)
Construction: $150,000 (Park Reserve)
Engineering/Admin: Design and construction of trail (5% of total project costs) (Park Reserve)
Justification
Segment is identified on the City's trail plan as a key connection to future O'Dowd Park improvements.
Other Comments
Scott County has assumed responsibility for the regional trail connection along CR 79 from 169 to CR 78.
Portions of this trail are being constructed in 2005, but the timeline for the remaining conneciton to CR 78 is
dependent on additional funding.
Ooeratina Costs
Estimated yearly operating costs: $1,000
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park and Trail Development Premier/Horizon Heights 210,000
Year Added toCIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 200,000
Improvements
Engineering/Admin. (5%) 10,000
Total - - - 210,000 - -
B. Funding Source:
General Fund
CClpitallmprovement Funds
Park Reserve Fund 210,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - 210,000 - -
Descriotion
This project would construct trails and park amenities in the Premier/Horizon Heights developments.
Construction: $200,000 (Park Reserve)
Park and trail development
Engineering/Admin: Design and construction of park development, (5% of total project costs) (Park Reserve)
Justification
The city has undeveloped open space in this area that could accommodate trails and small park amenities.
Proposed improvements have been part of the CIP for many years.
Other Comments
Actual park amenities would be determined in planning process with residents. Future park dedications from
adjacent undeveloped land may be better suited for active recreational use.
Ooeratina Costs
Unknown at this time - dependent on scope of development.
City of Shakopee Capital Improvement Program 2007 -2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Riverside Bluffs Community Park 993,750
Year Added to CIP: 2005
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 795,000
Improvements
Engineering/Admin. - 198,750
Total - - - 993,750 - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - 993,750
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - 993,750 - -
DescriDtion
Description
This project would develop the park that will serve Riverside Fields, Riverside Bluffs and Ridge Creek developments. The
park is approximately 8-10 acres (ridge creek has not yet been preliminary platted) for a total cost of $795,000.
Play equipment $75,000, 1 combined hockeylBB rink w light $180,000
Lighting $30,000, Planting, $30,000, earthwork $40,000, trails and walks $20,000 and prefab
restroomlwarming building $250,000, medium program gazebo $50,000, parking, $120,000, total
$795,000
Engineering/Admin: Design and construction administration of park development (25% of total project costs, which includes
additional costs for design of building staking, testing, etc.) (Park Reserve)= $198,750.
Justification
This provides for development of a park in the Riverside Fields, Riverside Bluffs and Ridge Creek developments, (also
serving Glacier Estates and Premier/Zotschke developments) which are currently under development: Riverside Fields is
nearing fully developed, Riverside Bluffs is nearing Final Plat and Ridge Creek is in the Preliminary Plat process.
Other Comments
Actual park amenities would be determined in planning process with residents. This park will likely serve as a location for
organized activities such as playground and summer youth programs and youth sports.
Operating Costs
Estimated yearly operating costs: Labor $15,000 + Equip/Supplies$10,000 = $25,000
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Bluffs at Marystolivn 500,000
Year Added to CIP 2007
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 400,000
Improvements
Engineering/Admin. - 100,000 -
Total - - - 500,000 - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - -
Grants (specify)
Donations (specify) 500,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - 500,000 - -
DescriDtion
This project would develop parks in the Bluffs at Marystown development. Parks are anticipated to be
constructed by the developer.
Construction: $400,000 (Park Reserve)
..... ,....... Play equipment, courts, trails, picnic area
1-'-'" - I .......... - ..- ,,_ '" ,................ Engineering/Admin: Design and construction of park development (25% oftotal project costs) (Park Reserve)
Justification
Other Comments
Actual park amenities would be determined in planning process with developer.
ODeratina Costs
Unknown at this time - dependent on scope of development.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Killarney Hills Neighborhood Park 437,500
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 350,000
Improvements
Engineering/Admin. - 87,500 -
Total - - - 437,500 - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund - 437,500 -
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - 437,500 - -
Description
This project would develop the Kilarney Hills park. The park is approximately 3 acres.
Construction: $350,000 (Park Reserve)
Play equipment, courts, trails, picnic area
Engineering/Admin: Design and construction of park development (25% of total project costs) (Park Reserve)
Justification
This provides for development of a park in the Killarney Hills subdivision, which would also serve future
development north of 17th Avenue. If 17thAvenue is built out sooner and development occurs in the area,
this park may need to be moved up.
Other Comments
Actual park amenities would be determined in planning process with residents.
Operatina Costs
Unknown at this time - dependent on scope of development.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Land Acquisition and Development Prairie Village Neigborhood Park 337,500
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW 150,000
Construction 150,000
Improvements
Engineering/Admin. 37,500
Total - - - - 337,500 -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 337,500
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - 337,500 -
Descriotion
Provides for acquisition of 2 acres of land adjacent to Prairie Village development.
Land and ROW: $200,000 (Park Reserve)
Construction: $150,000 (Park Reserve)
Play equipment, trail connections, picnic area
Engineering/admin: Design and construction of park, (25% of project cost)
Justification
In 2002, residents from Prairie Village development asked City Council if it could obtain land to locate a park
near their subdivision. Council directed staff to investigate potential sites. Staff approached Beta Seed in 2004
for possible land sales, but Beta Seed declined.
Other Comments
The City received cash in lieu of land in this development, and there are no nearby recreational amenities. If
land is notavailable, another option that could be pursued is to work with St. Francis and include a
recreational amenity as part of their future expansion.
Ooeratina Costs
Unknown at this time - dependent on scope of development.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Trail Project Title: Total Project Cost:
To Be Determined Greenway Development Prior Lake/Spring Lake Greenway 152,500
Year Added to CIP: Corridor
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW 100,000
Construction 50,000
Improvements
Engineering/Admin. 2,500
Total - - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 152,500
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - 152,500 -
Description
This project would provide for greenway acquisition and improvements along the Prior Lake/Spring Lake outlet
channel, most likely south of CR 16.
Construction: Greenway improvements, $50,000 (Park Reserve)
Land & ROW: AcquiSition of greenway corridor, $100,000 (Park Reserve)
Engineering/Admin: Design and construction of improvements (5% of project costs) (Park Reserve)
Justification
This project would provide the greenway connection along the Prior Lake - Spring Lake outlet channel and
connect with potential greenway, open space, and park development east of Dean Lakes.
Other Comments
Greenway grants may supplement funding.
Qperatina Costs .
Unknown at this time - dependent on scope of development.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Improvement Riverview Park Parking Lot 78,750
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 75,000
Improvements
Engineering/Admin. 3,750
Total - - - - 78,750 -
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 78,750
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - 78,750 -
Descriotion
This project would provide funding for a parking lot in Riverview Park and provide accessible trail
connections..
Construction: $75.000 (Park Reserve)
Engineering/Admin: Design and construction of park development, (5% of project costs) (Park Reserve)
Justification
On street parking is limited, and users currently park on the grass.
Other Comments
Ooeratina Costs
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Shutrop Community Park Development 1,250,000
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 1,000,000
Improvements
Engineering/Admin. - 250,000
Total - - - - - 1,250,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 1,250,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - - 1,250,000
Description
This project would provide funding for future development.
Construction: Develop park area, $1,000,000 (Park Reserve)
Design/Admin, $250,000: (25% of project costs) (Park Reserve) total $1,250,000
Justification
This will provide funding for development of Shulrop Park in the future.
Other Comments
This park would likely contain passive recreation and larger group picnic facilities and would have shellers,
rest rooms, parking, trails and play equip[ment.
Operatina Costs
Unknown at this time - dependent on scope of development.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
To Be Determined Park Development Community Sports Complex 1,050,000
Year Added to CIP: 2006
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 1,000,000
Improvements
Engineering/Admin. 50,000
Total - - - - - 1,050,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 1,050,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - - 1,050,000
Description
This project would provide funding for a future sports complex.
Construction: $1,000,000 (Park Reserve)
Engineering/Admin: Design and construction of park development, (5% of project costs) (Park Reserve}
Justification
This will provide funding for a future sports complex, potentially at a future school site.
Other Comments
Operatina Costs
~ I Unknown at this time - dependent on scope of development.
'~
1-> 1~ .~
C=;j j
City of Shakopee Capital Improvement Program .2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Sherry Dvorak Park Development High School Field Lighting 400,000
Year Added to CIP: 2007
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction 400,000
Improvements
Engineering/Admin.
Total - - - - - 400,000
B. Funding Source:
General Fund
Capital Improvement Funds 400,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total - - - - - 400,000
Descriotion
This project would consist of lighting 4 playing fields (football and soccer) at the new Shakopee High School.
Justification
Its estimated that by 2010, Shakopee Youth Football Association will have a need for 4 full size fields with
lights for their programs. With the time of the year that football is played, daylight hours are at a premium.
Other Comments
The Shakopee School District has verbally agreed to allow the City to light these fields.
Ooeratina Costs
Unknown at this time.
City of Shakopee Capital Improvement Program 2007 - 2011
Project Manager Project Type: Project Title: Total Project Cost:
Improvements Small Improvement Projects 120,000
A. Expenditure Items: 2006 2007 2008 2009 2010 2010
Land & ROW
Construction 20,000 20,000 20,000 20,000 20,000 20,000
Improvements
Engineering/Admin.
Total 20,000 20,000 20,000 20,000 20,000 20,000
B. Funding Source:
General Fund
Capital Improvement Funds
Park Reserve Fund 20,000 20,000 20,000 20,000 20,000 20,000
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Flow
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 20,000 20,000 20,000 20,000 20,000 20,000
Descriotion
This project provides funding for non-designated projects requested by Council, residents, or staff. In general,
the. project should 1 )correct a problem or address an issue, 2) not exceed $20,000, and 3) be consistent with
the comprehensive park plan.
,-'.......... Justification
Other Comments
Ooeratina Costs
, /,M Unknown at this time - dependent on scope of projects selected.
,,.So;. o<F' I
I> \~~~
t:-L-- _..l
U
City of Shakopee Capital Improvement Program 2006- 2010
Project Manager Project Type: Project Title: . Total Project Cost:
Travis Karlen/Mark Themig Facility Improvements Aquatic Park Improvements 1,180,000
Year Added to CIP:
A. Expenditure Items: 2006 2007 2008 2009 2010 2011
Land & ROW
Construction
Improvements 485,000 485,000 100,000
Engineering/Admin. 55,000 55,000
Total 540,000 540,000 100,000 - - -
B. Funding Source:
General Fund
Capital Improvement Funds
Building Fund 540,000 540,000 100,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer FundcFlow
Sanitary Sewer Fund-Trunk
StormDrainage Fund-Base
Storm Drainage Fund-Trunk
Tax Levy
Total 540,000 540,000 100,000 - - -
DescriDtion
This project would replace the existing service building, as well as add additional play features to enhance
attendance.
2006/2007 - Improvements: Demolish and replace existing building, add play features, $1,000,000 (Building
Fund)
2006/2007 - Engineering/Admin: Design and engineering services for project (8% of total project costs)
(Building Fund)
2008 - Improvements: Waterslide has 3-year life expectancy remaining. Will need to be replaced.
Justification
The service building was constructed in 1968, and has reached its life expectancy. Due to the type of
construction (cinder block and concrete), little can be done to make improvements. The plumbing needs
significant upgrading to repair leaks.
Other Comments
Costs of comparable buildings constructed during the past few years were used to determine this estimate.
(3,000 sq ft @ $250/sq ft. = $750,000 + $250,000 for permits and additional site amenities like fencing,
shade structures, play equipment, etc.)
ODeratina Costs
Building Rental = $38,000/year. Operating costs currently in operating budget.
1 2007-2011 CIP Summary - (Extended Loan Payback)
2 .Exl?~!!s~S ............... ...... ......... ....................... ................ ...I~~.~..... ............ ...............~!!tim!!.te..........f..\I.!!~.\n9 ~q,:!!~!!...... ........:?.9..9..~ .. ...........:?997 ...............}OO~ ................2.9.9.9 ..... ...........~01.9......... ... 2~.~.~.. .......... ~roi~ct..~.9.~..... ~.!?!!!!!).~!!~..... ........... ...... .......... .................. .. ...... . .............. ............... ............ ...............
3 .Q!~~!)fie.!~ '!.l!.!!~!.~a!:k l?.~'!.~!gpment.................. D~sl9n !!!).d ~on~!!!.~!Qn ... ......... ................ ........ 3~?,g,Q~.. P.?.r.k..~~.~~!Y.~...... . ................1.?,0.90. ............ ............... ..................... .... ..... ....... ............. ... ............. A~dre.!!.................. RerT)~.!!).!!!9.pa'y'.'!l~."!.!......... ........ ......... ................ ... ...... ............. .............. ........... . ... . .............
4 Church Addition Neighborhood Park Construction 200,000 By Developer 200,000 Andrea
5 Construction Administration 5,000 Park Reserve 5,000
30 Valley creek'crossing' Pa'ii( beveiop'menT'" besign"aiid Construction ... ............... ........... . .....120:000 By Devlii'o'per ......... .120,0.00..... . ............. .. ............... ...... ........... . .. ........... .... ........................ Andrea...... ...... ........ .. ... ................... .. ....... .............. .................... .. . ..... ................... ............. . ........... .... .................. ....................
31 Construction Administration 3,000 Park Reserve 3,000
22 'cOljntrYside"Development Parks"(3} ... ............... Design' and .ConStruCtfci.n............. ......... .... ....... ...... .....6.59 ,000' By 6eve'loper ........ .... 659:000.... . .............. ... ................ ...... ................ ......... ... ............... ...... .. "Andrea ........ .... ............. . ..... ....... .. .... . . ......
23 Construction Administration 16.475 Park Reserve 16,475
19 Tah'pah Park iiii.provemli.riis...... 'Fleld liliprovemenis'olislgn' an'd ConSt. ..... ......... 5'50,750" 'Park Reserve'" ......... ..... ....455.250... .............. 95,500'" ......... . ....... ....... . ......... ....... .. .... . .......... 29"(000" ..Andrea.............. .... Park"re<ievelopmeni'"in"io06 "Sari'flliiiTin' 2007,"contingeni on'grant award....Clght fields'7 & 8, 201'1:" ...................
20 Parking Lot-Playground DeSign and Const 54,340 Donations 54,340
20 Parking Lot-Playground Design and Const 1,056,390 Tax Levy 1,056,390
20 Parkin Lot-Pia round Design and Const 100,000 Grants 100,000
11 Huber Park Improvements Phase l' Park Development 2,980,804 Park Reserve 1,490,402 1,490,402 Mark Reflects full contract with recommended deducts and construction into 2007.
12 (Includes boat launch, Levee Drive Parking, Phase 1. Park Development 226,500 Grants 226,500 DNR boat launch grant, DNR trail grant, LMRWD boat launch grant
13 and power line undergrounding) Phase 1: Park Development 236,858 Donations 236,858 Includes all donations and other funding sources in project
14 Phase l' Park Development 204,870 Assessments 204,870
15................ .......... ...... .......... .... ...................... f'~~~e..:? ~an~..~!<!.~.!!iza,t.~QD. .......... .. .................. .. ....?,g.Q.Q,.O~O.. ~~~!.~............ ..... ........ ...... ....... .... ....... ....... ........... ?"OOO,QqQ... ... ..................... ..... ....... ..... . ............ . ... . ...... . ...... .... . .... f'~!!d.!n9. fuT}qlD.9...... .. ... ........ .. ... . .................. ............. .. .... ............... .. ...... ....... .... ......... ........ ....... . ...
16 Archery Range Relocation DeSign and Construction 20,000 Grants 20,000 Mark
17 20,000 Donations 20,000
18 ....... ... ................. ............... .................. 9Q.~st!".\!Y!ion {r.Q.!!:9~~.Y.2 . ...................... . ......??,.Q9.9. Park R~.~~!:y~ ....... .. 82.09,Q.... .. .. ..... .... ............ ..................
21 .17th ~.y.~.r.!~.~ Sp'g.r!~..~o':r.!p'I.~.~................. ............ .~!:!!l~e. 2. ~~!!Q!1)9 ~!)~ f..!~~! SI~e vy9.~.. ......... ... 5.~5,QOQ...E?!15.Reserve... ........ ... ...?~~,?OO .......:?!?!,500. ......... ........ .. ....... . ..... ...... .. ... 399,9qq. .M!lrk
6 Quarry Lake Park Design and Construction Administration 365,500 Park Reserve 10,000 24,000 289,500 14,000 28,000 Mark
7 Construction 770.500 Grants 210,500 280,000 280,000
8 Construction 560.000 Donations 100,000 180,000 280,000
9 'Lions Park'i"mprovements ......... ..... ... ......... Coiistructlon"and"improvements' .-.. ......... ............ ...........245:250 Pa.ii(..Reserve.... ..... ........ .................. 1.95~250 ........... . . ... .. ........ ........ ....... ............. ................. ......... ...... ............. . ..... ...... ............. ...... . ....... .
10....... ...... ......... .... ........... .... . ................... . .~o!l~!".\!~!o!l.l'!:!!g.Il1}l?rov~~.!2!:> ... ............. ............~?,999 Donl'!:!!9.ns.. .... ........... ~.Q,.q,Q,Q... ....~~,.OOO ...... .................... ............... ............... ..................... ....... ...... ....................... . ............ . .............. ................ .............
24 Southbridge Area Park Development Savanna Oaks Park Development 147,000 Park Reserve 147,000
25 Cambndge/WhitehallTraillnstallation 81,060 Park Reserve 81,060
26 Southbridge Parkway Active Park Develop 387,500 Park Reserve 387,500 Moved to 2007 from 2008
27 Fishing Pier 20.000 Grants 20,000
28. ...... ...... ............ ........... ........... ................ .~!:-lDOT..E~!ceI7~..Q~velol?m~.!!!......... .................... 5.???i?O.. ~!!.~..~.~.~~!Y.~.... .... ....................... ........... 573,7.?0.. ......... ... ............. .... ............. .................. ... ........ ........~g.y..~.d to 209.U~01T!.2Q1,Q..!.!QQ~Q.I?~.rklO~L.. .................... ......... ...... ........... .................... . .................. ....................
29 .Pel'!:!!..~.ake.I.!:<!!I..~.Y.st~l1}.. ............ .................P~.~ig~.a.!:1.~..90I)~.!".\!~ion.... ............... .. ............... .....2~9.,.~.?? Parkg.~.~~!Y.~.. ............... ....... .............. 230,.4??.. . .................... ......................... ............. ....................... . AT}~~?... ..... Mg.y'.~.dto.~q9.!..fro!)1.200~................... .... ....... . .................. .... ...... ...... ............. ........................ .......................................
32 Glacier Estates Neighborhood Park Dev. DeSign and Construction 110.000 By Developer 110,000 Andrea Moved to 2007 from 2006
33 Construction Administration 2,750 Park Reserve 2,750
34 .~:Clia~b..P.99..A~~!!:.........:::.:.:....... ....::::::::.::::.::::::::..:: D~.~!gii':a~~...r?~:;;eiop'l1}~:~(....:. .. :..... :..... ............. ...!5,qOq.. l?!?n?tions .: ':::":..:.'. .. ...:'::::'::::. .":: .....::::::j~,OOO... .::::::::.::::::::::::':':::' ":.:::::::::':::::::: .:.: :::::::::::... .. .. ............ ...................... .... .......... '. .:::::::::::::::.... .: .::::::.::::.::::.:. :".:.::::'::::" .::.:::::....::::.::::::. "::::::::::::::::. '.:::':::::::::::::':"
35 .F..a.rk Si.9r.!.?\l~.. ......... ........ ............ ........... l.nsta,1I F.~~..~!.9n?9~..... ........ ... .. .......... ............ ......!O,OO~.. .t:.~.~. ~eserve . ........ ....... ........... ...... .....~q,OOO.. ..... .....??...OOO .............. . ........... .... ... ...... . ....... ...................... .... ................ .... ................. .......... ....... ...... . .................. ..................
36 .F.rovide.!l2!,:!y'y.estc~.~.~!~~ Park .l?~'y!,:lop'.!l}~f.l!. l?es!9~..an.d g!?n:>l~21!o!). ...... ... .... ............ . ..............1.,0.?7.50Q.. .F.~!.~..Reserve .......... ......... ......... ........~.,,Q.~7,5Q.0...... ............ . ......... .... ... .. ....... ...... ........ ...................... ... ............ .... .............. ......... ........... . .................. ...... .......... . ...
37 G.reenfi~ld/Park Meac!ows Park Dev .... D~sl9!)..and GOT}:>.lructlon .... . ... 1.231.250 Park. ~eserve 1,231,250 .. .. ...
42 O":''?!?~~ .Lak~..f'l'!:~ Iml?!:l?'y.~!!!ents ... ...............p~~'gn..?D.9. C!?D.~!.!l!ctlC?.!:1... .................. ........... .... ~.!.~,.?QO .Park..~.~.~~.~e .. ................. ...... ......... ............. 412.?9~. .................... . ......... ......... ............... . .................... ......... ......... .............. .. ....... ............. ................ ...............
43 C~..?~. T.rai! t~ Q.powd ~~~~..F.ark. ......................!?eslgn..!!!).9..~o':l~!.r~ct!C?n .................. ......... ... ~.??,.?.99 Park R.~.~~!y'e.. ..................... .......... ................ 25!,,?OQ.. ...... .......... ......... ....... .............. ................. .. ......... .. .......... ................ ................ ................ . ................
38 Pre!)1!~r!.t"!or!;lO..t!.~I.ghts E~~.De,!.~.!QP'.men~ DeSign and Construction .... ........ ..........7..10,99.9. Pa~..~~s~I'{~.... ........... ................... .............. .......................... ..........~.1.q,q,Q9.. ............ . ........... ........ ........ ........ . .......... . ............ ........... .. ............. ............ ....................
39 .~lyerslc!.e.B.I~.!!~ P<!.~J~~:>! Dea.~.h!!:K~L ..... l?e~lgl)..~nd y.!?r.!:>t.l"\!21ion ...... ... .. ......... .............~.~3,?W Par,k.Rese~e.... .. ........ .... .............. .... ..... .............. . ..........99;3,750.. ............. ..... ..... . ................... . ............. ...... ...... ...... ........... ........ ... ............. . ....................... ...........
40 ~.!~!!s.l'!:t.Ma.r.Y.:>.lown .......... ... .......... ....... Deslgn..and G!?D.~!.rlJctIOI)............. .. ............. ..... .......?.9..0,00~.. ~.Y...P.~veloper ...... .. ....... .. ................. ....... ............... . ....i?99,000 . ........ ........ ..... ....... Ne~.!n..2007 ............. ........................ ...... ..... ........... .. .... ........ ..... .......... ................ ..................... .......
40 K.!!!!:!:!1.~y.!-i1I!.~..P.a.rkD~y.~!Ol?m~nt ....................l?e.sI9~..?!)~...C'?!1:>!ructlC?D... ....... ................. ..... .........~.?.!,500..t:.?E.~..~.~serve ........... .. ........... ............ ........... ....~3!,500 ........ ............ MQv.~.~.t02009f~0!!)..2q1O.. ................ . .......... ................ ................... .. ............ ............ .................... ...
41.Pr~!rleV!II?.9.~..P?r.~ ............. ..................... ~an.d~29U1S~I!?!1/Con~.!".\!~I!?':l .... ............. ..............3~.!.500 ~.~.r.~..~~serve............ ..................... .... ........ ......... ........ ...}37,500....... .. ........ ............. f..~~r.~..... .............. ........... ..................... .................................... .............._. ........ .......... ............... .....
44 .PI!.SL C~?n.T}~I. ~r~eny!~.y'..gomdg.r............. ...... Deslg~ .?nd ggD.~r~~lon ...... ........ ........ ........! 5?,500 P~rK..~~.~~~e.... ...... ........ ................. . ... ....... . ..... . . ............ .... .... ~.?2,500....... ................ F~~~r.~..... ..... ... ............. ...... .... . ..................... ... ....... ... ..... ...... .. ..... .. ........... ........ . ................ .... .. . .. ..
46 .Bly.el"!l.~."'!.~.?E.~.Pa~k!!)9...~g! .................... F:'a!:kI~9. L!l! G!?D.~ructlon.......... ... ....... ...........,78,??9. Pa.~..~es~!Y.~........... ........... ..... .............. . ............... .... ........... ....... ........ ...........J8,7?,Q..... ............... F~~~r~.. . ................. .. ....... .. ................... .......... ........ ..... .............. ............ ............... . .........
45 Shutrol? Pa~k Develop'ment ........ .. q.e~!gn .?D~..90nst~'?!!gD.... ... ......... ....... ........ ...... .......... t:.ark Res~':Y.!l. .................. .............. .. ...... ..._.. ........ ........... .. ..... ....... ... . . ........ ..... Deferrec!..!'?..?911 ... ................. . ............... .................. ......... . ............ .. .. .............. ... ....... ... ...... . ...............
47 .ColT!.mu!:!!!Y.F.ark..~I?!J!:!~.Cor.!'}I?!~x .. ......... !?~.~i9.n ?ng.gonstl"\!~!Q.!:1. ............. ................. 1,0.?9.,Q9.~...t:~~..R~~~!Y~ .... ............. ..... ......... ................ .................. .... . .. ...... .... .E?~~~rred tC?2011 ...................... ................... .. ......... .................. .... ................. .......... ................ ........... .....................
48 .!:ii9.h Sy!:!!?o!..Flel(L~i9.htll)9..... ..... ...... .... .. ... 11T!P.!9v!'ll1}'!!'r.!!~....... ............ .. .... ...... .. ..... ..... 409.,.o~Q.. Ea.rk F3.~~~.':Y.e. ... . . .. ..... ............ . ......... .. ............... . . ................... .
48 ~n:!~!"kI)}~~yernE!..r.!!..!:i,r<?i~.... m\l1J f2..~~!..~.. ,..... . .. .... 12Q,,Q.Q9... t:',~~~~~..!Y~ __ __.........W;..?..O.,O~~ 2~~Q.Q.... 20,Q9..Q.. ..~OO,Q Im-_..........
52ufJ lifl1ifia:iIAAl a llik:_4W Z *1!!1!1, Elna!ilwfJ,5l! ,a a 1,824.000 p.I!!i!liie "~alllll '1IIf Ii! I!llli~ ~ ,00 !!Q9iDOIif ,j! w
53 Total 22,134,522 I 4,651,357 5,419,915 5,032.250 3,091,250 I
55 Revenue/Credits Descri tion Estimate 6/30/2006 1/1/2007 1/1/2008 1/1/2009
56 Park Reserve Fund Balance 2,163,550.00 493,033 1,304,402 1,382,677
57 P~:!E::g~~iC~!!2~' Fe~~. t:.ii?li.ciio~s .. ':.::::.:::::'" :::::: ..... . . ::::.. ..:......::.. .. . ..:: ::.:. :.::::::::" . :..:. ":::::::::.. . :::::::::..::.......::. : .:'''::::::.:''':'' "':::.:::::::: ::..:::: :::':..: ':':. ':::.::::..::::.. .. . ...... ...... . .:..:::':.::::: $..:::::~09 ,.qQ,Q . .. ~rC?ji.9!ed r~y~~u~ :;Vou'!<(r.i.g~!r.~'E?~~:~~~)~atic?~}r.2!!i:'19~.!9.!~:~!:2905 ~.i.~:!~~iio.n' ~~~::~ie: ':.::::::::::::': ":':::::.:::. ...:::::::::::::::::::
58........... . .........Rive~.Y.!!:!!~.Y. ~state~..@9~). ... ... ........~O..~!.r.!.gl~..f.?mll.Y...~D.it~..... ............... ................?~7,qOQ. . ....... ............... .......... .. . .......... . ............. .... ........ ............... ..... ......... ~~9~iv!l.9.:'!!.~.?............ . ............ ... ....................................... ................... ......_.... ... ......... ............... ........................
59 .... ............ ... ........ ......~id9~..Y.!~~ Fa.!!D.~..@q~)... .. ..... 5~ ~!.r.!91.e fami!.Y...~I).tt.~ .... ......... .. ..............??.8,36q. .. ................ ....... . . .~~M60 . .................... ........ ............ ........ ..... ............... ... ...... .......... .. F.ID.?I pl.a!. !!)..!~Y.!~Y.!""'" .. ........ . ..... ................ ............ .... .... ..... ............ .. .. ...... ........ ............... . ...........
60 ................ ..... ........... K~n.slr.!.9!!?~ Est~!~.~. @.O~). .... ..... ... .. 8 ..~.i.!:1gle fa~!.IY...~~~~ ..... ............ . ........... ~?,700. ................... . ............. ... ......~~'.!.OO . .... ............... .. ......... ..... . ............ .... ......... ...... f..I!).!!.! p'la! ~P'.P'.!p'.y~~... ........... .. ..... .................. .... ................ . .............. .. ......... .......... ..... ............. ... .........
61 ............... ........... ...YI~r.!!D9. E~~at~:>..(:?9.0?2.. ..... . ........... 7.~...~.t!a~h.~~.~~!~.. .... ........... .........;315..950. .................. .... ....... ............ ......~1~,!!?0 ..... ....... .............. ............. ........ .......... ... F..~!).?!p.lats I!)..r.~view,.bg.!!:!..~.~an.~ ~~2Q.nd add~!c?I).. .............. ...... ...... .................. .............. ............... .... ....... ....
62..... ..... .. ... ...I-;>tate .I.~~king (20~~:?.9Q?.L ...... ...... 5q.l'!:9.r.!l.s <?.omr.n.~.r.9.!al...... ............... . ............153,('0.9 _............. . ................ .... ....J.?:!?,.85.q ......~?,425 $.........88,425 .... ...... ..... ............. Prehmina'Y.l?lat in review Assumes ~9% i!l..~.rst p.~~~~.TID.al..l?!a!............... ................. ....... . ............. . ................ ...... .....
63........... _. .........~!Jut~.~.~c!.g.~..fl~.!9.s @.96-.~Q08) . ......... ..1.Q..!lcres <:<?n:!~.rcla!.. ......... ............ ...69,qqQ...... ......... .!!,.?5,Q..... ..... ..~4,50q... ..~.... 17,25Q... ..... ......... .. .......... Antlclp..~!~Q~o h?v~..?O.~.~nal.p.!.?!!:.~.c! in 20.0.!?, ~T}9.qq:'&..i.!).2QO?':............... . ... .......... .... .............. ................. ..............
64 ............. ....... ..M.a.r.Y.S!~~!! Yi)la9.e (~QQ?:~?9.08) 7l?~~c~.~g.:..:?.sin9.I~..f.~.!l:!i1y'.. ~4a9..~~!!), . ......... 4?.1 ,821.. .......... ... . ... .... ....... .. ...... ... .............334.8.9.!... ..~..... ~7,9.:?Q... ....... ....... .......... .......... . ......... ... ....... . .......... .. ........ Prehm..I?!~! in. !"E!,!!.~.~.:..~esidentl!!:! .?.907, cc?r.!'}!!).~.rc!a!"~Q.Q8:.. . ................. . ..... . ......... ......... ....................... ........
65..... ...... ........... ............ Hauer.J?'Q07~2998) .. ~q..~!n9Ie.f?r.!'}!!'y',..:??.~..~.l!~c~ed (~~!!1).at~) .. . .. ....1,19~,69.9........ ... ...................... . .... ............ ........ 596,3qQ.....$.. 59.~..~QQ........... .. ..... ........... .......... .................. .. . .. ......... ... ........ 80-acr~ ~!l!!:c~f!c!..~g.~~i~9. MUS~.~.xtens!'?!)..~p.p.rove~....!:'~ssumes n.C?..I?.a,~..!and ~~.~.lcatIO.r.!...... ............ .......... ... ..
66 ......... ...... ....... Sh.~r!?l?.Sou!h (2qOX-.29q8} . .~.QO..u!1lt~.Jestlma~~..??~ a~.c.~.~~} ... ........ ....2.: 136,90Q ... . ............... . .. ....................... ..... 1,068.900 . J.1.,968,OOp..... . .. ......... ..... . ........ ..... ........ ... .......... ............ ... ....... .~o.r~ .!!~~!y'.a 20q?:.p..r.QJ~.9.l, .ac.c'?r.~!n9. t~ th~..9.evelop~r........ . ..... ........ ................. . .............
67. ......... ........... ....... ........ ~C?~~~k!':.{P~!!~H~9.0~). .... ..~.2q. sil).9.!~Jamily 1!.D.!!~.(estim~.!~L. . ........... . .6.~7,.?QQ...... . ........... ............ ........ ....... ..~. ..~~!..oqO... ..... .. ..... . . ............ .. ........... ... ........ ............. ..... .............. Re9.':!!.~!ng/rezomn9..~.r.!Q..~~~~..~.l?1?r.9.y.ed .Assum~~..~9:Y.o p'arK ~~.~!.~51~ion n:!~.!~ro~gh..!.<!.~.~.:.... .......... .
68 ............. ........~!.~f.fs .a!..~~!Y~town @.Q!' -29~ 0). q.1 .~!.~9Ie ~.!!)i.~,...?~.?...~~~h~.~, 1 O..!!:c c'?m .... ....... .1 ,8?M?Q.. ............. .... ....... . .. .. ....... . ... ..... ..~... ...~72.1 ?'.Q... ..~... 472, 1.~Q... ..$. 4?~,.~.?.Q.... $. ... ~7?,.~.?9... . $ ........ . - .. ......... ........... '?ev~!!?I?!!).~nt un!!~..~.?~~d on ~.~Y.!!..1?r.9jectIQn 4::Y~~.r..!?.I!.!I.c! !?~....?.Q.~..C?f l?arK..~~.~.I9.?!!~.n r.n~!.!.~..I.and .d~.g.!9.!!.tion .........
69 ............ ... ........ .. ......... A.CC..~9.~~ (290?:2. .... ... ... . ......... ? ............ . ... . . ............. ........... ..... . ....... ........... .. ... ........... ......... ......... ... ..................... ........... ........ ............ ." ..... .............. .................. . ............ ... ....... .. ..... ............ .... ............. ................. ....... ... ... ........... ..................................
70
71 ):;~p.g~~~:.S~j.~..~U~:arcei~.....::::::.... ........:.::..:::::.:.::::. ..::::::.:.:.. .::::::::.::::........::...:::::.::...:........ ....::.::....::.. '::::.:::::" ::..:..... ....::::::::::::..:::.:.... . .:::::::.....:...::.... ....:. :::::::::. ......... ':.::::::::::". .....:.::.:::....:... . .:: ::..::.::.:...... . .::::::::....:. .. .............._...... .......... ................. .... ::.::::::::::... . ':::':::::::.. :.::::::.:.::.....: .: '~::::::::.. .... ...::..::::::.... ... ::::'. "::'.:':'::::.: ..:: .. . .. '::'::':::.:.' ~...' :::.: ::.:: .:::...... .:.::.:::::::.::.... ..:.:::.:::::..: . ::.. .
72 Grants 20,000 326,500 2,230,500 280,000
73 :t~x ieiiY.'::" .....: ... ..:::::::::'.:.:... .... .::::::::::... .. .::.:: ":. :....:...::::.. ..:...:::::.:..........:. .:::.:::: .. :::.::::::: ... ......:::::.:.:::::::::::.::.... "::... ::::: ..::: 1 ,056;~?\i::' ':..:. ..:....:..:..:::...:.::::: ..:.:: .:..' :.::::::::::: ..::::. .....:::. ::.:::::::::.::....:.: ........ ......... . ............ ... ... ... ... . ..:.::::.::::..:.:... .: .:::::::::. ... ......::.::::::.::..:... ..:::::::::::::::..: ........:: ::::::::... .: :.::::::::.. '"::':::.::::.:''' ........ . . ..:.::.::: .
74 Assessments 204,870
75 Xcli!..~g.r~:~rii~~!."::::::::..::: '::.:.::::::::::":..::::':':": '::"::":.: .::'::."::..::'_ ~..::.::.~:.Y.ea~:~:ii~e~me~L::..::::::. .....::..::.:. '::':".:... ....:::::::::::::=.. .::::::::::::::::::::.:...... :::::::::. .: :.........:.:: ::::::...: 4~Q;?'Q:9" ":. ~Q';~99 . ......... ..... :~~~~!yed 20Q~::~ayij,le~t..~~::~ay. 1'5 .:.:::..:::::....... :.::::::::'" .... '::'..:::.:" . ..:::::::::' "':":':::':. .:.... . .....::::::::.... ..::::.::.::.::::.::::::::....:..
76 Donations 84,340 287,858 100,000
77..~~.~,~~ii!,ip.~~..~....Dev~Q.P..e.rs...=.._.~.~....~...,:~~...~.............. ................ .............. ..~:............ ........................................~:.~....,..=_. ....... 9?,g"Q~~:.:~.;~fJ.9,Qoo 1h'W. _ ..~=~ ................... .. ................................... ................... ~~~
78 n~n,~ffWlQ l<illffu ~ iliffi m *"",,,, lillMWtS ~ ;; % % ~ b ~ _ :~:$'*'~~OOQl 1m M8t:" " " :/11%m
79 Total Revenue/Credits I 5,144,390 6,724,317 6,414,927
80 I
81 Park Reserve Fund Expenditures 2.511,627 4,490,687 2,701,750
82
83 Total Expenditures I I (5,419,915) I (5,032,250) I I
~: 12/31 Ending Park Reserve Balance I I 1.304,402\ 1.382'6771 I
86 8.1806
,
. b
r>N { ~ hi e.
2007 Recreation Fund
-Work Plan
-Operating Budget Request
2007-2011 Parks CIP
2007 Government Building
Operating Budget Request
SHAKOPEE
CoMMUNlTY l'RmESINCr 1857
Services Provided
Recreation Fund Government Buildings
. Recreation Programs . Budget provides funding for
. Aquatics City Hall, Library, 200 Levee
. Ice Arena Operations Drive (Senior Activity Space)
· Community Center Operations . Also maintain Police
Department, Fire Departments,
. Park Services and portions of Public
. Teen Center Works/Engineering.
. Park Development Departments fund these costs.
. Natural Resources
. Development Review
1
.
2006 Projects
Projects Underway/Completed Potential Projects to Begin Still in 2006
. Natural Resource. Corridor Map and Design Standards . Online Recreation Software
. Park and Open Space Boundary Marking Program . Adult Sports Agreements
. Evenin9 and Weekend Program Expansion . Ice Arena Resurfacer Replacement
. SACEC Facility Use Agreement . Park and Recreation Planning Initiatives
. Community Center Video Surveillance System . Facility Scheduling Policy
Community Center Chiller Replacement . Valley Creek Crossing Park
2008 State Amature Baseball Tournament Planning . RFP for Mechanical Contractors
Committee (ongoing) . RFP for Vending Services
. Shakopee on Skateboards Team Facility Management Software Implementation
. Huber Park 200 Levee Drive Buildin9 Analysis
. Tahpah Park
. Countryside Parks (3)
Greenfield Park
. Church Addition Park
17" Avenue Sports Compiex Buildin9
Aquatic Park Building
Southbridge Savanna Oaks Park
Stans Park ADA Improvements
. Glacier Estates/Riverside Fields Trail Connection
Archery Range Relocation
Minnesota River Boat Landin9 Relocation
City Hall Carpet Replacement
. Youth Building Carpet Replacement
Building System Inventory
2007 Work Plan
. Focus resources
. Complete 2006 projects
. Limited new projects
2
.
,
2007 Work Plan
Recreation Online Registration Continued
Programs 2008 State Baseball Continued
Tournament Planning
School District Use Agreement New
Revisions
Natural Resources Natural Resource Design Continued
Standards
Storm Water Pond Planting New
Program
Park and Open Space New
Management Progam
Natural Resource Inventory New
Update
Facilities Community Center Water Continued
(Includes both Government Infiltration
Buildings and Building Inventory Continued
Recreation Facilities) City Hall NC Replacement New
Preventative Maintenance New
Program
2007 Work Plan
Parks and Park Huber Park and Riverfront Work Continued
Development Aquatic Park Building Continued"
Construction
17th Avenue Sports Complex Continued"
Building Construction
Glacier Estates Park Deferred to 2007
Dean Lakes/Southbridge Trail Deferred to 2007
Connection
Off-Leash Dog Area . Deferred to 2007
Park Signage Deferred to 2007
Quarry Park Design Deferred to 2007
Westchester Park New
Southbridge Park and Trail New
Development
Tahpah Baseball Field New
Lions Park 2nd Rink New
3
.
2007 Work Plan
Subdivision Riverside Bluffs (80 acres) Continued
Development Ridge View Estates (35 acres) Continued
Marystown Village (40 acres) Continued
Ridge Creek (80 acres) New (new application)
Shutrop South (120 acres) New
Premier Development (80 acres) New
Bluffs at Marystown (340 acres) New
ACC (CR17/CR78) (40 acres) New
Hauer Property (80 acres) New
Administration Comprehensive Park Plan, Fe~ Continued'
Study, Community Center
Future and Service
Prioritization Study
Planning Processes and Studies
. Three Components
- Comprehensive Park Plan
. Analysis of future land and resource needs
. Determine locations for future parks
. Identify replacement costs and funding mechanisms
. $20,000
- Fee and Cost Recovery Study
. Cost of service determination for recreation programs and facilities
. Fee analysis for cost recovery policy decisions
. Would tie into City development fee study
. $10,000-$15,000
- Community Center Future and Prioritization of Services
. Service study
. Community Center future
. $5.000
. All are somewhat connected, so proposed to conduct
simultaneously
. Possibly begin in late 2006, complete in 2007
. PRAB lead planning processes, with citizen input from sub-
committee participation, open houses, etc.
. Funding from Recreation Fund and Planning. Potential funding
for park plan update from park reserve and Blue Cross.
4
.
.
2007 Recreation Fund Operating Budget
. Revenue ($936,620)
- Increase $49,780 (5.18%)
. Expenditures ($2,258,290)
- Increase $9,340 (0.42%)
. General Fund Transfer ($1 ,246,670)
- Decrease $40,440 (-3.14%)
2007 Recreation Fund Operating Budget
Revenue
. Projections reflect increased revenue from Community Center
health care reimbursement programs and Aquatic Park
attendance
Staffing
. No additional staff being requested
. Eliminate part-time Teen Center coordinator (position not filled)
. Retains funding for vacant part-time Accessibility Coordinator and
Recreation Superintendent
. Budget assumes charging Director and Landscape Architect time
to projects at multiplier of 1.3
Supplies/Services
. Samellevel of service with only minor modifications based on past
history
5
.
.
2007 Recreation Fund Operating Budget
Township Fees
· $13,500
2007 Recreation Fund Operating Budget
Budget Improvement Packages
· Huber Park Performances* $14,000 (net impact)
- Sf; Louis Park: $18,000 (plus staffing costs)
- Eden Prairie: $41,965
· Planning Initiatives* $40,000
· Security Camera Additions $10,000
· Community Center Painting $55,000
· Aquatic Park Improvements $58,000
*Recommended improvement packages.
6
.
.
2007 Recreation Fund Operating Budget
Parks and Recreation Advisory Board Review
. Discussed primary components of budget request at July meeting,
but didn't have detailed version.
. PRAB strongly supports filling Recreation Superintendent position,
and requested that we move forward. Job description would come
to Council pending budget review.
2007 Recreation Fund Operating Budget
Questions and Direction
7
.
.
2007-2011 Parks CIP Overview
· Establishes timelines and funding for major park
improvement projects
· Cost estimates based on best available information at
thetime
· Most projects include 25% Design/Engineering and
Construction Administration Factor
· Actual projectcosts would be determined through
detailed design process with community involvement
· Ability to implement projects identified in the CIP will
be contingent on park dedication revenue
2007-2011 CIP Overview
· Funding
- Projected December 31 balance through 2011:
. --~
2006 2007 2008 2009 2010 2011
493.033 1,304.402 1.382,677 664,457 954,737 -2,315,263
8
.
2007-2011 CIP Overview
'00' 2007 2006 200. -c-
GreenfieldWestPark X X X
QU8IT)'Cl/lanup Quarry{)esign Q\IaIlYConstJuction QuarryConstruclion
LionsPtlI'klmprovmenls L10l1$ Park Rink X X
ChurehAdditiOnPerk X X X
Phase 1: Huber Park and Riwtfronl Phase 1: HuberandRiverfront Phase 2: Riwr Bank StabilizatiOn X
Dewlopll1ent ..............
AroheryRange X X . X
Tahpahlmprovements BMeballField X X
Soccer Complex Building SoecerCOmplexBuilding X X
Coontr)'side Parks (3) X X X
Southbridga Savanna Oaks Park. SouthbridgalDean Lake Trail X X
Cambridg$lWhitehallTrail
SouthbridgeParceI 75 (Actiw and Passiw
......,
ValleyCreekCroesingParK X X X
X GlacierEstalesPark X X
X Off.L_h Dog Area X X
X PerkSignage ParkSignage X
X Westcl'lElsWPerk X X
X X Greenfield East Park X
X X O'OowdPar1o;mprollll18nts X
X X O'DowdlCR78 Trail Connection X
X X X PremierfHori:wnHeights PariI
X X X Riwrsidw Bluff's ParK
X X X Bluffs and Marystown Pat1<.(s)
X X X KilarneyHIIIsP<<k
2007 -2011 Parks CIP Projects
2006 Projects
Finalize Greenfield West Park
- Turf Establishment
Complete Church Addition Park
- By Developer
. Start QuarrySite Cleanup
.- Public Works
- Continues into 2007
. Lions Park Improvements
- Bocce Ball and Shuffleboard
- Volunteers
. Phase 1 : Huber Park and Related Riverfront Improvements
- Park redevelopment, boat landing, parking. roadways. utilities
- Continues into 2007
. Archery Range Installation
. Tahpah Park Improvements
. 17th Avenue Sports Complex Building Construction
- Continues into 2007
. Complete Countryside Development (3 parks)
- By Developer
. Valley Creek Crossing Park
- By Developer
. Aquatic Park Building Construction
- Continues into 2007
9
.
2007-2011 Parks CIP Projects
· CIP does not reflect recent School Board
discussion regarding hockey team rooms
· Funding for Community Center water
infiltration work requested to be carried over
to 2007
2007-2011 Parks CIP Projects
Tahpah Park
Improvements
- 2007: Baseball field
construction, $195,500
(contingent on grant)
- 2011: Lighting softball fields
7&8
10
.
.
2007-2011 CIP Projects
Huber Park and Riverfront
Redevelopment
- 2007: Completion of Phase 1
- 2008: Phase 2, River Bank
Stabilization, $2,000,000
(contingent on funding)
2007 -2011 CIP Projects
17th Avenue Sports
Complex
- 2007: Completion of building
construction, $267,500
- .2011: Field . lighting for fields
1-3, $300,000
11
.
.
2007-2011 Parks CIP Projects
Quarry Lake Park
- 2006: Site cleanup, $10,000
'- 2007: Site cleanup and
design, $24,000
- 2008: Access, roadway,
parking; and trails, $600,000
- 2009: Other improvements,
$474,000
- 2010: Other Improvements
· $210,000 in grants
secured
· Additional donation from
Bituminous Roadways
possible
2007 -2011 Parks CIP Projects
Lions Park Improvements
- 2007: Second ice rink, ADA
improvements to restrooms,
$231 ,250
- 2010: Picnic shelter,
$50,000
- 2011: Indoor tennis facility,
$500,000
12
.
,
2007-2011 Parks CIP Projects
South bridge Park and Trail
Development
- 2006: Savanna Oaks Park,
$147,000
- 2007: CambridgelWhitehall
Trail, $81,060
- 2007: Active Park, $387,500
(moved up from 2008)
- 2007: MNDOT Parcel Trail
and Enhancements,
$573,750 (moved up from
2010)
- 2008: Fishing Pier, $20,000
2007-2011 Parks CIP Projects
Dean Lakes/Southbridge Trail and
Bridge, $230,475
- Deferred from 2006
13
.
'"
2007-2011 Parks CIP Projects
Glacier Estates Neighborhood
Park
- 2007: Park Construction,
$112,750 (deferred from 2006)
2007-2011 ParksCIP Projects
Off-Leash Dog Area
- 2007: Location to be
determined
- $15,000
- Deferred from 2006
14
.
2007 -2011 Parks CI P Projects
Park Signage
- 2007-2008
- $70,000
- Deferred from 2006
2007 -2011 Parks CI P Projects
Westchester/Providence
Point Park
- 2007: Park development,
$1,087,500
- Active park
(Westchester/Providence Point park
dedication was $78,812. Remainder
in land.)
15
.
.
2007 -2011 Parks CI P Projects
Greenfield East/Park
Meadows Park
- 2008: Park development,
$1,231,250
- Active park
- Deferred to 2008
(Greenfield/Park Meadows park
dedication was $192,805.
Remainder in land dedication.)
2007-2011 Parks CIP Projects
O'Dowd Park Improvements
- 2008: Park Improvements, $412,500
- Moved up from2010
16
.
.
2007-2011 Parks CIP Projects
CR 79 Trail Construction
- 2008: Trail Construction,
$257,500
- Moved up from 2010
2007 -2011 Parks CIP Projects
Premier/Horizon Heights
Park
- 2009: Park development,
$210,000
- Deferred to 2009
17
.
..
2007-2011 Parks CIP Projects
Riverside Bluffs
- 2009: Park development,
$993,750
- Active park serving east
Shakopee
2007-2011 Parks CIP Projects
Bluffs at Marystown
- 2009: Park(s) development,
$500,000
- By developer
18
2007-2011 Parks CIP Projects
Kilarney Hills Park
- 2009: Park development,
$437,500
2007-2011 Parks CIP Projects
2010
- Prairie Village, $337,500
- Prior Lake/Spring Lake Greenway Corridor, $152,500
- Riverview Park Parking Lot, $78,750
2011
- Shutrop Community Park, $1,250,000
- Community Sports Complex, $1,050,000
- High School Field Lighting, $400,000
19
..
,
2007-2011 Parks CIP Projects
Small Improvement
Projects
- 2006-2011
- $20,000 per year
2007-2011 Parks CIP Projects
Aquatic Park Improvements
- 2007: Completion of building.
$540,000
- 2008: Waterslide replacement,
$100,000
- Building Fund
20
.
2007-2011 Parks CIP Projects
Questions and Direction
2007 Government Buildings Operating Budget
. Expenditures ($670,150)
- Increase $88,730 (15.3%)
- Primary increase in staffing and rent (see below)
. Staffing
- No increase in staffing proposed
- Increase in budget reflects staffing costs not being budgeted in
respective building budgets. Costs would be charged to building
budgets.
. Supplies/Services
- Primary increase in rent ($22,000) for lease payments of Levee Drive
Building for City's contribution toward CAP Agency program
- Joan Lynch from CAP Agency was not able to attend tonight's
meeting. Would request work session in thenear future.
21
.
.
2007 Government Buildings Operating Budget
Budget Improvement Packages
· City Hall Multi-Zone rooftop HV AC Unit $110,000
· 200 Levee Drive Air Exchanger $ 3,400
2007 Government Buildings Operating Budget
Questions and Direction
22