CITY OF SHAKOPEE
Memorandum
TO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
SUBJECT: Draft 2008-2012 Capital Improvement Program for the
Public Works Department
DATE: July 9, 2007
Please find attached the Draft 2008-2012 Capital Improvement Program (CIP) for the
sanitary sewer, storm sewer and street improvement project areas for the City of
Shakopee, as prepared by the Public Works Department. The following is a list of
highlights of the 2008-2012 CIP for your information and attention:
I SANITARY SEWER PROGRAM I
1. The major project focus for 2008 will be the sanitary sewer extension for
Beckrich Park Estates and Krystal Estates.
2. Continuation ofthe cured-in-place pipe program of sanitary sewer main.
I STORM DRAINAGE I
1. Includes the improvements for the next five years for the Prior Lake-Spring Lake
Watershed District channel improvements in the City of Shakopee.
2. Additional drainage control system improvements in the area of C.R. 78 and C.R.
17.
3. Channel stabilization project on the channel from Beckrich Park Estates to
Patterson Drive in A.C.C. 2nd Addition.
I STREET IMPROVEMENTS I
1. Continuation of 2008 bituminous overlay or pavement preservation program for
residential streets and industrial streets.
l
,
2. Continuation of reconstruction of streets and in 2008 rural street reconstruction in
the area of Eaglewood, Norton Drive, Wood Duck Trail and Blue Heron Drive as
well as an overlay for Stonebrooke Drive.
3. Railroad crossing improvements at Atwood Street.
4. Possible 429 improvement project for OPUS on industrial property by C.R. 83
and Fourth Avenue.
5. C.R. 101 bridge improvement with funding dependent on bridge bonding bill.
I OTHER STREET IMPROVEMENT PROJECT HIGHLIGHTS FOR 2009-2012 I
1. CSAH 21 improvements, from CSAH 18 to CSAH 42. The County is projecting
higher costs with this improvement project, than previously shown, and has been
included in the 2009 CIP.
2. A number of projects are shown that are development driven, thus these projects
mayor may not occur in the years projected.
3. Council may review the years and project areas of future reconstruction projects
and provide direction.
4. CSAH 17 project, as shown in the year 2013, which is a current projection of
Scott County.
5. Old T.H. 300 turnback funding and improvements shown in 2011.
6. Pedestrian bridges for C.R. 77 and Dean Lake to Quarry Lake Park connection
shown in 2011 and 2012.
This concludes my memo on the Draft 2008-2012 CIP. as prepared by the Public Works
Department and if there are any questions, please feel free to contact me in my office.
k: Loney,
Public Work
BLlpmp
ENGR/2007PROJECTS/2007COUNCIL/CIP-SUMMARY
r;)
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer Annual Cured-in-Place Pipe Project $250,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
land & ROW
Construction 230,000 180,000 130,000 130,000
Improvements
En ineerin IAdmin. 20,000 20,000 20,000 20,000
Total 250,000 200 000 150,000 150,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk 250,000 200,000 150,000 150,000
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total 250,000 200,000 150,000 150,000 -
DescriDtion:
-- f Annual cured-in-place pipe project.
~ Justification:
Necessary to extend the life of existing sanitary sewer.
Other Comments:
Project area to be determined based on yearly televising.
ODeratina Costs:
PROJECT LOCATION
3
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer Sanitary sewer extension to Beckrich $600,000.00
Park Estates.
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 480,000
Improvements
En ineerin IAdmin. 120,000
Total 600,000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 50,000 (SPUC)
State Aid
Assessments 500,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk 50,000
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total 600,000 - - - -
Descriotion:
f Sanitary sewer and water extension to Beckrich Park Estates and Krystal
~E_
Justification:
Homeowners are requesting sewer service.
Other Comments:
Need coordination with SPUC on existing water system including the well. Trunk
sanitary sewer will be extended along CSAH 78 and trunk water over sizing will
be determined by SPUC.
Operatina Costs:
PROJECT LOCATION
Y
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce laney Sanitary Sewer Area JT-O $100,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 80,000
Improvements
En ineerin IAdmin. 20,000
Total - 100 000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk 100,000
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 100,000 - - -
f Description:
Extension of trunk sewer to serve area in MUSA.
~ Justification:
Sewer extension is part of City's sanitary sewer plan and is needed in order for
area to develop in the recent annexation area.
Other Comments:
Trunk sewer will be extended through developments. Revised Comp Sewer
Plan and Cost Sharing Agreement with Met Council is necessary for sewer to be
extended.
ODeratina Costs:
PROJECT LOCATION
5
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer East Shakopee Industrial Sewer $1,075,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 875,000
Improvements
En ineerin IAdmin. 200,000
Total - 1,075,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 1,075,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 1,075,000 - - -
Descriotion:
f Extension of sanitary sewer to serve large industrial lots in East Shakopee.
~ Justification:
. The age of existing on-site sewage treatment systems and the size of
developments warrant consideration of sanitary sewer extension.
Other Comments:
Property owners have shown interest in project. Area does have municipal
water, however, MUSA has not been extended to the area. This sewer line is no
longer a trunk sewer with the rerouting of the trunk sewer through the
South bridge development. A lift station will be necessary to serve area.
Ooeratin9 Costs:
PROJECT LOCATION
10
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce laney Sanitary Sewer 1st Avenue Sewer Ext. (Apgar) $140,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 110,000
Improvements
En ineerin IAdmin. 30,000
Total - 140,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 140,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 140,000 - - -
Descriotion:
+ =nr;:~on of sanitary sewer to serve an area without municipal sewer along 1st
Justification:
To replace existing on site systems which may be at the end of their life with
municipal sanitary sewer service.
Other Comments:
This project needs to be initiated by existing property owners, redevelopment, or
public health hazard concerns.
Ooeratina Costs:
PROJECT LOCATION
/
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer Area SE-C (Phase III) $250,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 200,000
Improvements
En ineerin IAdmin. 50,000
Total - - 250,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk 250,000
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 250,000 - -
Descriotion:
f Extension of trunk sewer to serve future development.
~ Justification:
Sewer extension is part of the City's sanitary sewer plan and is needed in order
for area to develop.
Other Comments:
ODeratina Costs:
PROJECT LOCA liON
~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Extend Sewer and Total Project Cost:
Bruce loney Sanitary Sewer Water to Serve Hilldale Road $450,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW 60,000
Construction 300,000
Improvements
En ineerin IAdmin. 90,000
Total - - 450,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 310,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 140,000
Total - - 450,000 - -
f DescriDtion:
Extension of sewer and water to serve the property adjacent to Hilldale Drive.
~ The project includes reconstructing Hilldale Drive wllh concrete curb and gutter.
Justification:
Homeowners may request sewer service due to failing septic systems.
Other Comments:
Project needs to be petitioned for by residents affected. Property to the west
must develop prior to the extension of sewer to Hilldale Road.
Ooeratina Costs:
PROJECT LOCA liON
C1
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer Trunk Sewer Extension South of $300,000.00
Valle View Rd. & W. of C.R. 83
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 240,000
Improvements
En ineerin IAdmin. 60,000
Total - - 300 000 - -
B. Fundin Source:
Genera' Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 100,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk 200,000
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 300,000 - -
DescriDtion:
f Extension of trunk sanitary sewer in developing areas south of Valley View Road
~ and west of County Road 83.
Justification:
Trunk sewer will be needed to serve this area with municipal services.
Other Comments:
Timing depends on MUSA allocation and property owners willing to develop.
Trunk sewer may be installed in conjunction with private developments.
ODeratina Costs:
PROJECT LOCATION
/0
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Extend Sewer and Total Project Cost:
Bruce loney Sanitary Sewer Water to Serve Hillside Estates $650,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 500,000
Improvements
En ineerin IAdmin. 150,000
Total - - - - 650 000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 440,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 210,000
Total - - - - 650,000
Descriotion:
f Extension of sewer and water to serve Hillside Estates. The project includes
~ reconstructing Hillside Drive with concrete curt> and gutter.
Justification:
Homewowners may request sewer service due to failing septic systems.
Other Comments:
Project needs to be petitioned for by the affected property owners. The costs
assume extending utilities from the property to the east after it develops.
Extending utilities to this area, prior to the property to the east developing, will
result in additional costs of $200,000.
Operatina Costs:
PROJECT LOCATION
f {
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer Sanitary Sewer Extension to $250,000.00
Hillwood Drive
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 200,000
Improvements
En ineerin IAdmin. 50,000
Total - - - - 250,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 250,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 250,000
Descriotion:
f Sanitary sewer and water extension to Hillwood Drive. Location of the utilities
~ may warrant street reconstruction.
Justification:
Other Comments:
Project needs to be petitioned for by residents affected.
Ooerating Costs:
PROJECT LOCATION
/d
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Sanitary Sewer CSAH 18 Sewer Extension $625,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 500,000
Improvements 125,000
En ineerin IAdmin.
Total - - - - 625,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk 625,000
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 625,000
Descriotion:
f Extend sanitary sewer to serve the Whispering Oaks development.
~ Justification:
To eliminate the existing lift station and eliminate flow into the Savage sewer
system.
Other Comments:
Maintenance trail construction may be included with project which could serve as
a trail along CSAH 18. County may participate in other trail segments.
Ooeratina Costs:
PROJECT LOCATION
13
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer PlSl Channel Improvements $1,061,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 290,000 230,000 90,000 80,000 75,000
Improvements
En ineerin /Admin. 60,000 45,000 10,000 5,000 5,000
Total 350,000 275,000 100,000 85,000 80,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 50,000 50,000 100,000 85,000 75,000
Storm Drainage Fund-Trunk 300,000 225,000
Tax Le
Total 350,000 275,000 100,000 85,000 75,000
Descriotion:
f Additional capacity and control structures in the Prior Lake/Spring Lake Channel
~ to handle increased run-off due to development.
Justification:
Existing agreement with Prior Lake/Spring Lake Watershed District (PLSLWD)
requires the City to maintain the channel upon the City utilizing the channel for
urban development. Increased runoff from development will require a larger
channel. This project is for the purchase of right-of-way for future construction of
the improved channel and for a segment of the channel construction and
maintenance to establish a bio-engineered channel.
Other Comments:
Prior Lake/Spring Lake has indicated a willingness to participate. in channel
oversizing for its needs. New Joint Powers Agreement is needed for cost
participation. Upgrade of channel can be built in phases to accommodate growth
and needs of PLSLWD, City's of Shakopee and Prior Lake and SMSC.
Ooeratina Costs:
$50,000 annually for 5 years, then $25,000 annually after channel is fully
PROJECT LOCATION established.
I~
City of Shakopee Capital Improvement Program 2007 -2011
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer Channel Stabilization $60,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 50,000
Improvements
En ineerin /Admin. 10,000
Total 60,000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk 60,000
Tax Le
Total 60,000 - - - -
DescriDtion:
f Stabilize the drainage channel east of ACC 2nd Addition.
+ Justification:
Channel may start to erode.
Other Comments:
ODeratina Costs:
PROJECT LOCA liON
(6
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer Drainage Control System $100,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW 45,000
Construction 40,000
Improvements
En ineerin /Admin. 15,000
Total 100,000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk 100,000
Tax Le
Total 100,000 - - - -
Descriotion:
f Construction of a drainage control system south of C.R. 78. The system will
+ utilize a combination of an outlet control structure and a pipe outlet
Justification:
Developing properties in the area will produce more storm water run-off requiring
outlets to be constructed from existing wetlands. Ultimately, the outlets will
reduce water running downstream to future developing properties It is
recommended as part of the City's Comprehensive Storm Water Management
Plan.
Other Comments:
Controlled outlets will better manage the storm water discharge rates and more
fully utilize the upstream storage available in existing wetlands.
Ooeratin9 Costs:
PROJECT LOCATION
Ib
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer Blue lake Watershed Improvements $250,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 200,000
Improvements
En ineerin /Admin. 50,000
Total - 250 000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk 250,000
Tax Le
Total - 250,000 - - -
f DescriDtion:
~ Construct drainage facility to provide positive outlet for developing area south of
CSAH 16 and west of Pike Lake Road.
Justification:
A trunk drainage system is needed in order for significant development to occur
in the Blue Lake Watershed.
Other Comments:
Coordination is needed between the City and Shakopee Mdewakanton Sioux
Community and Prior Lake - Spring Lake Watershed District. An EAW has been
done to determine the environmental impacts. Costs of channel may be shared
with Shakopee Mdewakanton Sioux Community if agreement can be reached.
Ooeratina Costs:
PROJECT LOCATION
\1
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer Shenandoah Buisness Park $185,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 150,000
Improvements
En ineerin /Admin. 35,000
Total - 185,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk 185,000
Tax Le
Total - 185,000 - - -
DescriDtion:
f Construction of a storm sewer outlet from the Shenandoah Bus. Park (Industrial
~ s~es) to the Minnesota River through Murphy's Landing.
Justification:
A storm sewer outlet is needed to prevent further erosion from occuring now and
to handle the increased volume from industrial development.
Other Comments:
Project is dependent on industrial development proceeding in this area. Will need
coordination with Three Rivers Park District.
Ooeratina Costs:
PROJECT LOCATION
J~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer Northern Shakopee Outlet $125,000.00
A. Ex enditure Items: 2008 2009 2010 2100 2012
Land & ROW
Construction 100,000
Improvements 25,000 ~
En ineerin /Admin.
Total - 125,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 125,000
Storm Drainage Fund-Trunk
Tax Le
Total - 125,000 - - -
DescriDtion:
f Storm Sewer and Ponding Improvements to meet existing and future
+ development needs in area west of County Road 83 and south of County Road
101.
Justification:
Upon full development of this area, an improved drainage system will be needed
to prevent flood damage to existing properties.
Other Comments:
Hydraulic study done indicates additional culverts are needed under railroad spur
lines in the Certainteed property. Need Certainteed drainage agreement.
ODeratina Costs:
PROJECT LOCATION
\C1
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Storm Sewer Harrison Street Pond $100,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW 5,000
Construction 80,000
Improvements
En ineerin /Admin. 15,000
Total - - 100,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 100,000
Storm Drainage Fund-Trunk
Tax Le
Total - - 100,000 - -
Descriotion:
f Construction of a pond and outlet structure in lot 8 and lot 9 of the Husman
~ -~~
Justification:
The pond and outlet will reduce discharge rates from existing development in to
the Minnesota river and improve water quality.
Other Comments:
A controlled outlet will better manage the storm water discharge rates and more
fully utilize the upstream area available for ponding.
ODeratina Costs:
PROJECT LOCATION
:Jb
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Storm Sewer Valley Park 6th Addition Outlet $300,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 250,000
Improvements
En ineerin /Admin. 50,000
Total - - - - 300,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 300,000
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 300,000
Descriotion:
f Construction of an outlet for Outlot A of Valley Park 6th Addition
~ Justification:
Developing properties in the area will produce more storm water run-off requiring
an outlet to be constructed from the existing pond located in Outlot A to North
Star Auto Auction pond.
Other Comments:
Feasibility study may change implementation schedule of this project.
Ooeratina Costs:
PROJECT LOCATION
J\
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer O'Dowd - Thole Control Structure $250,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 200,000
Improvements
En ineerin /Admin. 50,000
Total - - - - 250,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk 250,000
Tax Le
Total - - - - 250,000
f DescriDtion:
A permanent control structure to regulate flows from Lake O'Dowd and Thole
~ Lake for better storm water management
Justification:
Potential future development of area and increase flows to lakes may require
permanent structure to establish runout elevation and rate of flow.
Other Comments:
Area would need to be annexed and this may happen beyond 2010. Condition
with DNR and Scott County WMO is required.
ODeratina Costs:
PROJECT LOCATION
a;}
Page 10
City of Shakopee Capital 1m rovement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Storm Sewer O'Dowd - Thole Overflow Channel $200,000.00
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 150,000
Improvements
En ineerin /Admin. 50,000
Total - - - - 200 000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 200,000
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 200,000
f DescriDtion:
~ Improvements to O'DowdfThole overflow channel to handle future development
areas.
Justification:
Increase flows form development require improvements.
Other Comments:
Improvements can be coordinated with development along channel.
Ooeratina Costs:
PROJECT LOCATION
J3
CIP Projects 2007 - 2011+
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2008 Pavement Preservation $630,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 550,000
Improvements
En ineerin /Admin. 80,000
Total 630,000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 190,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax le 440,000
Total 630,000 - - - -
DescriDtion:
f Bituminous overlay of the following streets: Vierling Drive, from CSAH 16 to
~ Emerald Lane, Jade Circle, Jasper Road, Hauer Trail, Emerald Lane, Diamond
Court, Onyx Drive, Heritage Drive ( north of Onyx Drive), Murphy Drive, Murphy
Court, Eastview Circle and Prairie Street.
Justification:
Continuation of City's Pavement Preservation Program to improve paved
roadways.
Other Comments:
Bituminous overlays are much more cost effective than reconstructing
pavements.
ODeratina Costs:
PROJECT LOCATION
~~
CIP Projects 2003 - 2008+
City of Shakopee Capital Improvement Program 2008.2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2008 Bituminous Overlay $300,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 250,000
Improvements
En ineerin /Admin. 50,000
Total 300,000 - . - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 90,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 210,000
Total 300,000 - - - -
f DescriDtion:
~ Bituminous overlay of Industrial Boulevard North and Industrial Boulevard South.
Justification:
Continuation of the City's Pavement Preservation Program to improve paved
roadways.
Other Comments:
Bituminous overlays are much more cost effective than reconstructing
pavements.
ODeratina Costs:
-.
PROJECT LOCATION
f)G
CIP Projects 2003 - 2008+
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 200~avement Preservation $770,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 620,000
Improvements
En ineerin /Admin. 150,000
Total 770,000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 230,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 540,000
Total 770,000 - - - -
DescriDtion:
f Bituminous reclamation for Norton Drive, Sycamore Circle and Mulberry Circle in
~ Deerview Acres and the streets in Eagiewood Add.ions and the Timber Trails
Addition. And a bituminous overlay of Stonebrooke Drive.
Justification:
To rehabilitate bituminous street pavements that have severely deteriorated or
are in need of resurfacing.
Other Comments:
Sewer may be available to the Timber Trail Addition in the next 5 years. Staff
has not had any indication that the property owners are interested or are willing
to pay for the extension of sewer and water. The proposed project will add 15
years of life to the existing streets. The extension of utilities can be evaluated
again around 2023.
ODeratina Costs:
PROJECT LOCATION
96
CIP Projects 2007 - 2011 +
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Railroad Signalization $200,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 160,000
Improvements
En ineerin /Admin. 40,000
Total 200,000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 50,000
Park Reserve Fund
Grants (specify)
Donations (specify) 150,000 (MN/DOT)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total 200,000 - - - -
DescriDtion:
f At grade railroad crossings at Atwood Street will need crossing signal due to
~ traffic volumes at this intersection.
Justification:
Traffic volumes of vehicles crossing, increased number of trains and possible
increased speed of trains warrant the signal installation.
Other Comments:
Funding from the State of Minnesota is programmed for this intersection. City
cost is for 10% of signal cost and roadway realigned to place signals.
ODeratina Costs:
PROJECT LOCATION
[)1
CIP Projects 2003 - 2008+
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Opus Development $1,400,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,100,000
Improvements
En ineerin /Admin. 300,000
Total 1,400 000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 1,400,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total 1,400,000 - - - -
Descriotion:
f Extension of a road and utilities to aI/ow for further subdivision of property
~ located in the Industrial Park.
Justification:
Owner may petition the City for improvements.
Other Comments:
Ooeratina Costs:
PROJECT LOCATION
~~
CIP Projects 2007 - 2011+
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction C.R. 101 Bridge Improvements $160,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 130,000
Improvements
En ineerin /Admin. 30,000
Total 160 000 - - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 160,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total 160,000 - - - -
Descriotion:
f Bridge enhancements along 1 st Avenue with the County's reconstruction of the
+ existing bridge over Mill Pond on C.R. 101.
Justification:
Entry way to Downtown area and Council has indicated a desire to enhance
bridge with lighting, abutment treatments, colored concrete and texture, and
ornamental railing.
Other Comments:
Scott County will pay for bridge replacement and City would pay the extra costs
for enhancements to bridge.
Ooeratina Costs:
$1000/yr
PROJECT LOCATION
9/1
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction CSAH 21 - CSAH 18 to CSAH 42 $16,600,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 9,500,000 5,100,000
Improvements
En ineerin /Admin. 1,000,000 1,000,000
Total - 10500,000 6,100000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund 500,000 250,000
Park Reserve Fund
Grants (specify)
Donations (specify) 9,500,000 5,600,000 (County)
State Aid 500,000 250,000
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 10,500,000 6,100,000 - -
f Descriotion:
Extension of CSAH 21 from CSAH 18 to CSAH 42.
~ Justification:
Scott County traffic will warrant the construction of CSAH 21.
Other Comments:
City costs will be for a bituminous trail, a traffic signal, storm sewer, and curb &
gutter. Construction of a rural section would significantly reduce the City's costs.
Scott County has received Federal Grants for 2009 and 2010 construction.
Ooeratina Costs:
PROJECT LOCATION
!f)
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction 2009 Pavement Preservation $210,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 160,000
Improvements
En ineerin /Admin. 50,000
Total - 210,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 50,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 160,000
Total - 210,000 - - -
Descriotion:
f Bituminous overlay. Shenandoah Drive, from Hwy. 101 to Eastway Avenue.
~ Justification:
Continue maintenance of the City's Pavement Preservation Program and
improved storm drainage system for area.
Other Comments:
Bituminous overlays are much more cost effective than reconstructing
pavements.
Ooeratino Costs:
PROJECT LOCATION
3)
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Bituminous Overlay of 4th Ave. from $250,000
Shenandoah Drive to CSAH 83
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 210,000
Improvements
En ineerin /Admin. 40,000
Total - 250,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 75,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 175,000
Total - 250,000 - - -
f DescriDtion:
Overlay 4th Avenue from Shenandoah Drive to CSAH 83.
~ Justification:
Traffic levels from development do not warrant construction of a three lane
roadway.
Other Comments:
Bituminous overlays are much more cost effective than reconstructing
pavements.
Ooeratina Costs:
PROJECT LOCATION
~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2009 Pavement Preservation $310,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 250,000
Improvements
En ineerin /Admin. 60,000
Total - 310,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 93,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 217,000
Total - 310,000 - - -
DescriDtion:
I Bituminous mill and overlay of Boiling Springs Road from Stagecoach Road to
900' north of Preservation Trail and Stagecoach Road from Preserve Trail to
+ 600' south of 13th Avenue.
Justification:
Continue maintenance of the City's Pavement Preservation Program and
improved storm drainage system for area.
Other Comments:
Ooeratin9 Costs:
PROJECT LOCATION
33
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2009 Street Reconstruction Program $1,350,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,150,000
Improvements
En ineerin /Admin. 200,000
Total - 1 350 000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 190,000 (SPUC)
State Aid
Assessments 270,000
Sanitary Sewer Fund-Base 200,000
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 70,000
Storm Drainage Fund-Trunk
Tax Le 620,000
Total - 1,350,000 - - -
Descriotion:
f Street, sanitary sewer & watermain reconstruction. Pierce Street, from 6th
+ Avenue to 10th Avenue. Clay Street, from Pierce Street to south of 10th Avenue.
Spencer Street, from 10th Avenue to Shakopee Avenue and Park Ridge Drive.
Justification:
To continue with the rehabilitation of the City's infrastructure in the older sections
of the community.
Other Comments:
SPUC has not determined the extent of the watermain improvements.
Ooeratin9 Costs:
-
PROJECT LOCATION
3t
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Traffic control signal or round-a- $650,000
bout for C.R. 79 and Vierlin Dr.
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 500,000
Improvements
En ineerin /Admin. 150,000
Total - 650,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 150,000
Park Reserve Fund
Grants (specify)
Donations (specify) 500,000 (County)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 650,000 - - -
Descriotion:
f New traffic control signal or round-a-about at County Road 79 and Vierling
~ i~~oo.
Justification:
Sufficient traffic movements may warrant the signal system. A warrant study will
need to be done to justify the signal.
Other Comments:
Relocation of High School to the south will change traffic patterns and may justify
a signal or round-a-bout at this time. Scott County has jurisdiction over the
intersection.
Ooeratina Costs:
PROJECT LOCATION $2,400/year for operating and maintenance costs if a signal is installed.
?:P
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Pike lake Road South of CR 16 $850,000
A. Ex enditure Items: 2D08 2009 2010 2011 2012
Land & ROW 100,000
Construction 600,000
Improvements
En ineerin /Admin. 150,000
Total - 850,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 150,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 650,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk 50,000
Tax Le
Total - 850,000 - - -
f DescriDtion:
~ Collector street construction on Pike Lake Road south of C.R. 1610 City Limits.
Includes sanitary sewer and watermain extension.
Justification:
Collector street needs to be improved as adjacent property develops.
Other Comments:
A portion of Pike Lake Road is in the City of Prior Lake as well as Shakopee.
ODerating Costs:
PROJECT LOCATION
Db
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 4th Ave. and C.R. 83 Intersection $435,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 350,000
Improvements
En ineerin /Admin. 85,000
Total - 435 000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 115,000
Park Reserve Fund
Grants (specify)
Donations (specify) 200,000 (County)
State Aid
Assessments 120,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 435,000 - - -
f Descriotion:
This intersection will need improvements such as a right turn lane on 4th Avenue
~ to C.R. 83 and a possible traffIC control signal at this intersection.
Justification:
Continued growth of the industrial area as indicated in the AUAR for
Shenandoah Business Park and Minnesota Valley West will require
improvements to the intersection.
Other Comments:
Signal will need to be justified by traffic warrants. Improvements are dependent
on development activity.
Ooeratin9 Costs:
.,
.,
PROJECT LOCATION
31
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction 17th Avenue, from C.R. 69 to CSAH $2,300,000
15
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,900,000
Improvements
En ineerin /Admin. 400,000
Total - 2,300 000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 460,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 1,840,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 2,300,000 - - -
f Descriotion:
Extension of 17th Avenue from County Rd 69 to CSAH 15
~ Justification:
l1!l Development of this area may warrant the extension of 17th Avenue. Council
recently annexed 340 acres in this area.
Other Comments:
If determined to be a County road, then the County participates in cost of project.
ODeratina Costs:
PROJECT LOCATION
?Ji
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction Valley View Road from Pike lake $860,000
Road to 1/2 mile W.
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 660,000
Improvements
En ineerin IAdmin. 200,000
Total - 860 000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund 200,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 660,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 860,000 - - -
Description:
f Collector street construction on Valley View Road, from Pike Lake Road to 1/2
~ mile west.
Justification:
Collector street should be extendeded to provide access to developing
properties.
Other Comments:
ODeratina Costs:
PROJECT LOCATION
SCf
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Shenandoah Business Park $500,000
1m rovements
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 400,000
Improvements
En ineerin /Admin. 100,000
Total - 500,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 500,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 500,000 - - -
f Descriotion:
~ Infrastructure for Industrial Property east of Shenandoah Drive and North of
Fourth Avenue.
Justification:
Sanitary sewer, watermain, storm sewer and streets are needed to serve this
development.
Other Comments:
Depends of developer's request for 429 Special Assessment Public
Improvement Project. Developer may want to request assistance from City due
to the subsurface conditions and to allow sanitary sewer and storm sewer lift
stations to develop the site.
Operatin9 Costs:
PROJECT LOCATION
~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Hansen Avenue from Crossings Blvd. $625,000
To CSAH 18
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 500,000
Improvements
En ineerin /Admin. 125,000
Total - 625,000 - - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 625,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - 625,000 - - -
f DescriDtion:
Extension of Hansen Avenue to CSAH 18 from Crossings Blvd. to serve
~ Shakopee Crossings East development and improved access to CSAH 18.
Project includes acceleration and deceleration lanes on CSAH 18.
Justification:
Developer would petition the City for a 429 Special Assessment project to
construct Hansen Avenue to improve traffic circulation for commercial area
development.
Other Comments:
Scott County would need to allow access to CSAH 18 in order for project to
proceed.
Ooeratin9 Costs:
PROJECT LOCATION
l}\
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2010 Pavement Preservation $700,000
Pro ram
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 600,000
Improvements
En ineerin /Admin. 100,000
Total - - 700,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 165,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 40,000
Storm Drainage Fund-Trunk
Tax Le 495,000
Total - - 700,000 - -
"" f Descriotion:
Bituminous overlay. Streets have not been determined.
~ Justification:
Continue maintenance of the City's Pavement Preservation Program and
improved storm drainage system for area.
Other Comments:
Streets will be evaluated each year and may be moved up or moved back in the
CIP.
Ooeratina Costs:
PROJECT LOCATION
> Lf~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction 2010 Street Reconstruction $1,750,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1 ,400,000
Improvements
En ineerin /Admin. 350,000
Total - - 1,750,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 330,000 (SPUC)
State Aid
Assessments 300,000
Sanitary Sewer Fund-Base 225,000
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 80,000
Storm Drainage Fund-Trunk
Tax Le 815,000
Total - - 1,750,000 - -
DescriDtion:
f Sanitary sewer, storm sewer, watermain and street reconstruction of 7th and 8th
~ Avenue, from Mar1<et Street to east of Dakota Street and Minnesota Street and
Dakota Street, from 7th Avenue to Shakopee Avenue.
Justification:
Continue with the rehabilitation of the City's infrastructure in the older sections of
the City.
Other Comments:
Streets will be evaluated each year and may be moved up or moved back in the
CIP.
Ooeratin9 Costs:
PROJECT LOCATION
~3
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction Railroad Signalization $400,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 320,000
Improvements
En ineerin /Admin. 80,000
Total - - 400 000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund 100,000
Park Reserve Fund
Grants (specify)
Donations (specify) 300,000 (MN/DOT)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 400,000 - -
Descriotion:
f At grade railroad crossings at Scott Street and Apgar Street will need crossing
+ signal due to traffic volumes at these intersections.
Justification:
Traffic volumes of vehicles crossing, increased number of trains and possible
increased speed of trains warrant the signal installation.
Other Comments:
Funding from the State of Minnesota is programmed for these intersections. City
cost is for 10% of signal cost and roadway realigned to place signals.
ODeratin9 Costs:
-
PROJECT LOCATION
t+~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction Vierling Drive - C.R. 69 to Taylor St. $670,000
A. Ex enditure Items: 2D08 2009 2010 2011 2012
Land & ROW 100,000
Construction 450,000
Improvements
En ineerin /Admin. 120,000
Total - - 670 000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid 170,000
Assessments 500,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 670,000 - -
f Description:
~ The constnJction of street, utility. sidewalk and trail system from County Road 69
to Taylor Street.
Justification:
Vierling Drive completion is needed to provide access to commercial property
south of Shakopee Town Square and North of the Shakopee By-Pass while
completing this east-west collector system.
Other Comments:
This project is dependent on a commercial development proposal adjacent to this
street.
Ooeratin9 Costs:
PROJECT LOCATION
~6
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Traffic Control Signal at Vierling $250,000
Drive and C.R. 69
A. Ex enditure Items: 2D08 2009 2010 2011 2012
Land & ROW
Construction 200,000
Improvements
En ineerin /Admin. 50,000
Total - - 250,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund 125,000
Park Reserve Fund
Grants (specify)
Donations (specify) 125,000 (County)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 250,000 - -
f Descriotion:
New traffic control signal at Vierling Drive and County Road 69 intersection.
+ Justification,
Sufficient traffic movements may warrant the signal system. A warrant study will
need to be done to justify the signal. Revelopment of commercial district is
needed to generate traffic for signal system.
Other Comments:
Will need to coordinate funding and signal justification with the County.
Ooeratin9 Costs:
PROJECT LOCATION $2000/year for power
4Jo
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction Valley View Road from McKenna Rd. $860,000
to 1/2 Mile E.
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 660,000
Improvements
En ineerin /Admin. 200,000
Total - - 860,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund 200,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 660,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 860,000 - -
Descriotion:
f Collector street construction on Valley View Road, from McKenna Road to 1/2
t mile east
Justification:
Collector street needs to be installed to provide access to developer's properties.
Other Comments:
Project is dependent on development proposals in this area.
ODeratina Costs:
PROJECT LOCATION
41
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Independence Dr. 1/8 Mile South of $310,000
Valle View Rd.
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 250,000
Improvements
En ineerin /Admin. 60,000
Total - - 310000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund 93,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 217,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 310,000 - -
Descriotion:
f Collector street construction on Independence Drive for a 1/8 mile south of
~ Valley View Road. Includes sanitary sewer and watormain extensions.
Justification:
Collector street needs to be installed to provide access to developer's properties
south of Valley View Road.
Other Comments:
Project is very much dependent on development.
ODeratina Costs:
PROJECT LOCATION
l{~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction T.H. 101 Trail Extension $50,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 40,000
Improvements
En ineerin /Admin. 10,000
Total - - 50,000 - -
B. Fundin Source:
General Fund
Capital Improvement Fund 50,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - 50,000 - -
Descriotion:
I Construction of a bituminous trail on the south side of C.R. 101, from Sarazin
~ Street to the bridge over the Mill Pond.
Justification:
Pedestrian traffic in the area may warrant construction of this trail.
Other Comments:
Ooeratina Costs:
PROJECT LOCATION
LtC1
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2011 Pavement Preservation $570,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 500,000
Improvements
En ineerin /Admin. 70,000
Total - - - 570 000 -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid 150,000
Assessments 150,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 50,000
Storm Drainage Fund-Trunk
Tax Le 220,000
Total - - - 570,000 -
f Descriotion:
Bituminous Overlay. 4th Avenue from Gorman Street to Scott Street and
~ Spencer Street from 4th Avenue to Shakopee Avenue.
Justification:
Continuation of the City's Pavement Preservation Program to improve paved
roadways.
Other Comments:
Bituminous overlays are much more cost effective than reconstructing
pavements. Streets will be evaluated each year and may be moved up or moved
back in the CIP.
ODeratin9 Costs:
PROJECT LOCATION
60
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: 2011 Bit. Overlay Total Project Cost:
Bruce loney Street Construction Vierling Drive from C.R. 79 to CSAH $525,000
16
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW 425,000
Construction
Improvements
En ineerin /Admin. 100,000
Total - - - 525,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid 250,000
Assessments 130,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le 145,000
Total - - - 525,000 -
f Descriotion:
Bituminous Overlay. Vierling Drive, from C.R. 79 to Emerald Lane.
~ Justification:
Continuation of the City's Pavement Preservation Program to improve paved
roadways.
Other Comments:
Bituminous overlays are much more cost effective than reconstructing
pavements. Vierling Drive will be evaluated each year and may be moved up or
moved back in the CIP.
Operatinq Costs:
PROJECT LOCATION
61
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2011 Reconstruction Project $2,100,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,900,000
Improvements
En ineerin /Admin. 200,000
Total - - - 2 100,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 270,000 (SPUC)
State Aid
Assessments 450,000
Sanitary Sewer Fund-Base 230,000
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 100,000
Storm Drainage Fund-Trunk
Tax Le 1,050,000
Total - - - 2,100,000 -
f Descriotion:
Street, sanitary sewer and watermain reconstruction.
~ Justification:
To continue with the rehabilitation of the City's infrastructure in the older sections
of the City.
Other Comments:
SPUC has not determined the extent of the watermain improvements. Streets
will be evaluated each year and may be moved up or moved back in the CIP.
Ooeratin9 Costs:
PROJECT LOCATION
6;)
City of Shakopee Capital Improvement Program 2008.2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction Trail Extension along CSAH 18 $100,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 80,000
Improvements
En ineerin /Admin. 20,000
Total - - - 100,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund 100,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 100,000 -
f Description:
Construction of a bituminous trail along CSAH 18 from Glacier Estates to
~ Southbridge Parkway.
Justification:
Pedestrian traffic in the area may warrant construction of this trail segment.
Other Comments:
Ooeratin9 Costs:
PROJECT LOCATION
6S
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Independence Drive, 5/8 Mile South $625,000
of Valle View Road
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 500,000
Improvements
En ineerin /Admin. 125,000
Total - - - 625,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund 200,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments 425,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 625,000 -
f Descriotion:
~ Collector street construction on Independence Drive for 518 mile south of Va/ley
View Road. Includes sanitary sewer and watermain extension.
Justification:
Collector street needs to be installed to provide access to adjacent properties
along Independence Drive.
Other Comments:
Project is dependant on properties developing.
ODeratina Costs:
PROJECT LOCATION
6*
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction TH300 Reconstruction $1,200,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,000,000
Improvements
En ineerin /Admin. 200,000
Total - - - 1 200 000 -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 250,000 (SPUC)
State Aid 550,000 (State Turnback Funds)
Assessments 200,000
Sanitary Sewer Fund-Base 200,000
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 1,200,000 -
f Descriotion:
T.H. 300 -10th Avenue to Adams Street
~ Justification:
To continue with the rehabilitation of the City's infrastructure in the older sections
of the community.
Other Comments:
City does qualify for State Turnback funds for improving Old T.H. 300, which has
been turnbacked to the City.
Ooeratina Costs:
PROJECT LOCATION
66
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction TH 300 Realignment $465,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 375,000
Improvements
En ineerin IAdmin. 90,000
Total - - - 465,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 400,000 (State Turnback Funds)
State Aid
Assessments 65,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 465,000 -
f Description:
TH 300 realignment of intersection and reconstruction of street to 10th Ave. due
~ to redevelopment of mal/.
Justification:
TH 300 reconstruction will provide a safer intersection and expansion of mall will
require better traffic circulation. Scheduling depends upon plans of Shakopee
Town Square; turnback funds can be utilized by 2013.
Other Comments:
TH 300 has been turned back to the City and State turnback funds can be
utilized for the reconstruction of the street. In order to apply for State turnback
funds, the City will need to prepare plans for the improvements listed. The State
has programmed
Ooeratina Costs:
-
PROJECT LOCATION
rJo
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction Shenandoah Drive Extension $1,450,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW 200,000
Construction 1,000,000
Improvements
En ineerin /Admin. 250,000
Total - - - 1,450,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund 250,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid 300,000
Assessments 900,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 1,450,000 -
f Descriotion:
Shenandoah Drive extension from Eastway Avenue to CSAH 16.
~ Justification:
This roadway would serve as a local collector and provide access to nearby
property. This project is very much developer driven.
Other Comments:
Construction of this roadway may be accelerated if racino is built.
Ooeratin9 Costs:
PROJECT LOCATION
61
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 12th Avenue Trail $200,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 160,000
Improvements
En ineerin /Admin. 40,000
Total - - - 200,000
B. Fundin Source:
General Fund
Capital Improvement Fund 200,000
Park Reserve Fund
Grants (specify)
Donations (specify)
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 200,000 -
Descriotion:
f Construct a bituminous trail from CSAH 83 to Quarry Lake Park.
~ Justification:
Other Comments:
Ooeratina Costs:
PROJECT LOCATION
66
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction T.H.169 Pedestrian Bridges $3,300,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 3,000,000
Improvements
En ineerin /Admin. 300,000
Total - - - 3,300,000 -
B. Fundin Source:
General Fund
Capital Improvement Fund 300,000
Park Reserve Fund
Grants (specify)
Donations (specify) 3,000,000
State Aid
Assessments
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - 3,300,000 -
Descriotion:
I The bridge at C.R. 77 is not wide enough to handle pedestrian/bicycles. An
~ additional pedestrian bridge east of C.R. 83 over T.H. 169 along PLSLWD
channel is needed to complete trail connections. Project is to widen existing
bridges or build new pedestrian bridges utilizing Federal Aid Highway Funds.
Justification :
For pedestrians or bicyclists to cross T.H. 169. Improvements are needed
especially with the growth of development.
Other Comments:
Coordination meetings are needed with Mn/DOT and Scott County for this
project to obtain funding a project is dependent upon receiving Federal funds.
ODerating Costs:
PROJECT LOCATION
6Cf
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 3rd Avenue Street Reconstruction $1,320,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,070,000
Improvements
En ineerin IAdmin. 250,000
Total - - - - 1,320,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 260,000 (SPUC)
State Aid
Assessments 240,000
Sanitary Sewer Fund-Base 210,000
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 50,000
Storm Drainage Fund-Trunk
Tax Le 560,000
Total - - - - 1,320,000
tI' Descriotion:
~ Street, sanitary sewer, storm sewer and watermain reconstruction on 3rd
~ Avenue, from CSAH 17 to Spencer Street.
Justification:
Continuation of City's Pavement Preservation Program to improve paved
roadways.
Other Comments:
3rd Avenue will be evaluated on a yearly basis and may be moved up or moved
back in the CIP.
Ooeratinp Costs:
PROJ ECT LOCATION
(06
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 2012 Street Reconstruction Program $2,400,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 2,200,000
Improvements
En ineerin /Admin. 200,000
Total - - - - 2,400 000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 380,000 (SPUC)
State Aid
Assessments 900,000
Sanitary Sewer Fund-Base 290,000
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base 100,000
Storm Drainage Fund-Trunk
Tax Le 730,000
Total - - - - 2,400,000
Descriotion:
f Street, Sanitary Sewer, Storm Sewer, and watermain reconstruction:
+ Bluff Avenue from Main Street to Marschall Road
Main Street and Prairie Street from Bluff Avenue to 1st Avenue
Dakota Street from Bluff Avenue to 2nd Ave
Naumkeag Street from 1 st Avenue to Bluff Avenue
Minnesota Street from Bluff Avenue to 3rd Avenue
Scott Street and Atwood Street from Levee Drive to 1 st Avenue
Levee Drive from Scott Street to Holmes Street
Justification:
To continue with the rehabilitation of the City's infrastructure in the older sections
of the community.
Other Comments:
Reconstruction of streets should be done in conjunction with redevelopment of
the area. SPUC has not determined the extent of the watermain improvements.
Ooeratin9 Costs:
PROJECT LOCATION
~r
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction CSAH 15 - T.H. 169 to 17th Ave. $1,300,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 1,000,000
Improvements
En ineerin /Admin. 300,000
Total - - - - 1 300,000
B. Fundin Source:
General Fund
Capital Improvement Fund 100,000
Park Reserve Fund
Grants (specify)
Donations (specify) 550,000 (County)
State Aid
Assessments 650,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 1,300,000
Descriotion:
f County road expanded to four lanes to meet growing traffic due to commercial
~ development along CSAH 15.
Justification:
County road needs to be upgraded to provide for increased traffic due to future
commercial development.
Other Comments:
Dependent upon rate of commercial development in the area and County
approval.
Ooeratina Costs:
PROJECT LOCATION
{p~
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce Loney Street Construction Extension of Valley View & Control $1,000,000
Si nal at CSAH 17 & Valle View
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 800,000
Improvements
En ineerin /Admin. 200,000
Total - - - - 1,000,000
B. Fundin Source:
General Fund
Capital Improvement Fund 260,000
Park Reserve Fund
Grants (specify)
Donations (specify) 100,000 (County)
State Aid
Assessments 640,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 1,000,000
f DescriDtion:
Extension of Valley View Road to Sarazin Street and construction of a new traffic
~ control signal at the Valley View Road and CSAH 17 intersection.
Justification:
Growth in the area and traffic will warrant construction of this roadway. Sufficient
traffic movements may warrant the signal system. A warrant study will need to
be done to justify the signal.
Other Comments:
Will need to coordinate the project with the County.
Ooeratin9 Costs:
PROJECT LOCATION
(03
City of Shakopee Capital Improvement Program 2008-2012
Project Manager: Project Type: Project Title: Total Project Cost:
Bruce loney Street Construction 12th Ave. Widening (W. of CSAH 83) $185,000
A. Ex enditure Items: 2008 2009 2010 2011 2012
Land & ROW
Construction 150,000
Improvements
En ineerin /Admin. 35,000
Total - - - - 185,000
B. Fundin Source:
General Fund
Capital Improvement Fund
Park Reserve Fund
Grants (specify)
Donations (specify) 60,000 (State)
State Aid
Assessments 125,000
Sanitary Sewer Fund-Base
Sanitary Sewer Fund-Trunk
Storm Drainage Fund-Base
Storm Drainage Fund-Trunk
Tax Le
Total - - - - 185,000
f DescriDtion:
~ Collector street construction on 12th Avenue for a 1/4 mile to widen 12th Avenue
to handle future traffic for future racino.
Justification:
Collector street needs to be widened to handle the additional traffic.
Other Comments:
Dependent upon Canterbury Park development in this area and State approval of
racino. State has indicated in their proposal to provide Shakopee with funds.
Project will likely be combined with a CSAH 83 widening project.
Operatina Costs:
PROJECT LOCATION