TO: Mayor and City Council
Mark McNeill, City Administrator
FROM: Bruce Loney, Public Works Director
DATE: 04/15/2014
SUBJECT: Approve Trail Extension Quarry Lake to Gateway Drive Consultant Contract, Project
No. 2014 -7 (E)
Action Sought
Authorize the appropriate City officials to execute the Consultant Contract with WSB &
Associates, Inc. for the Trail Extension Engineering Services from Quarry Lake to Gateway
Drive.
Background
Earlier this year, the City was awarded a $100,000.00 grant from the Shakopee Mdewakanton
Sioux Community (SMSC) for a trail connection from Quarry Lake to Gateway Drive. This trail
extension will be a continuation of a trail designed with the Valley Park Business Center Project.
Staff has obtained a proposal from WSB & Associates, Inc. for the trail design and construction
surveying services. Staff is not available to design the trail and the cost can be included as a cost
to be reimbursed by the SMSC grant.
Attached to this memo is the proposal detail services and costs and a map showing the location of
the trail. The location of this trail design will be through Outlots A & B Valley Park 13th
Addition. The City has a Drainage & Utility Easement over the entire Outlots and is working with
the land owner to secure a trail easement once the design is done.
Recommendation
Staff recommends to execute the Extension Agreement with WSB & Associates, Inc. as City staff
is not available.
Budget Impact
Expenditures such as on bids to construct the trail and engineering services may be used with the
$100,000.00 SMSC grant. Potentially, it could affect the Capital Improvement Fund if project
costs go over $100,000.00.
Relationship to Vision
This supports Goals D: Maintain, improve and create strong partnerships with other public and
private sector entities; and E: Deliver effective and efficient public services by a staff of
well - trained, caring, and professional employees.
Requested Action
Authorize the appropriate City officials to execute the Consultant Contract with WSB &
Associates, Inc. for the trail extension engineering services from Quarry Lake to Gateway Drive.
Attachments: Map Location and Contract
March 17, 2014
Mr. Bruce Loney, PE
City of Shakopee
129 S. Holmes Street
Shakopee, MN 55379
Re: Quarry Lake Park Trail Improvements
Estimate of Cost to Provide:
• Topographic Survey Services
• Design Services
• Construction Staking and Record Drawing Services
Dear Mr. Loney:
We propose to provide our services for this project, as described below, on an hourly cost - reimbursable
basis in accordance with our current fee breakdown (attached). The areas for this work are shown in red
on the attached figure and will be coordinated with the areas shown in yellow and blue:
• Red trail area: Proposed construction
• Yellow trail area: Trail to be completed with Valley Park Business Center Project
• Blue trail area: Future trail for access to bridge overpass across HWY 169
Scope and Project Understanding:
Topographic Survey:
• WSB will complete a topographical survey of the project area.
• Survey will include all shots necessary to prepare a set of construction plans including:
1. Shots at all match in points
2. Shots to establish existing vertical and horizontal alignment
3. Property irons to establish existing right -of -way
4. Cross sections
5. Public and private utilities including pipe and structures.
6. Boring locations (coordinate with Geotechnical company)
7. Small utilities (have utilities located through Gopher State One Call and maps
of small utilities in the area).
• Proposed fee: $2,622
Project Management:
• Management and administration of the WSB project team
• Coordination and communication with City and other project stake holders (i.e. property owners,
utilities, permitting agencies)
• Proposed fee: $588
Design Services:
• Construction plans
o Title sheet
o Miscellaneous Details
• Trail plans and profiles
• Erosion Control and Turf Establishment
• Specifications and Quantities
K:\Shakopee \Quarry Lake Trail 2014\LTR Prop Quarry Lake Trail 3- 17- 14.doe
WSB
Infrastructure ■ Engineering ■ Planning ■ Construction
701 Xenia Avenue South
& Assocfnlcs. 11W.
Suite #300
Minneapolis, MN 55416
Tel: 763 541 -4800
Fax: 763 541 -1700
March 17, 2014
Mr. Bruce Loney, PE
City of Shakopee
129 S. Holmes Street
Shakopee, MN 55379
Re: Quarry Lake Park Trail Improvements
Estimate of Cost to Provide:
• Topographic Survey Services
• Design Services
• Construction Staking and Record Drawing Services
Dear Mr. Loney:
We propose to provide our services for this project, as described below, on an hourly cost - reimbursable
basis in accordance with our current fee breakdown (attached). The areas for this work are shown in red
on the attached figure and will be coordinated with the areas shown in yellow and blue:
• Red trail area: Proposed construction
• Yellow trail area: Trail to be completed with Valley Park Business Center Project
• Blue trail area: Future trail for access to bridge overpass across HWY 169
Scope and Project Understanding:
Topographic Survey:
• WSB will complete a topographical survey of the project area.
• Survey will include all shots necessary to prepare a set of construction plans including:
1. Shots at all match in points
2. Shots to establish existing vertical and horizontal alignment
3. Property irons to establish existing right -of -way
4. Cross sections
5. Public and private utilities including pipe and structures.
6. Boring locations (coordinate with Geotechnical company)
7. Small utilities (have utilities located through Gopher State One Call and maps
of small utilities in the area).
• Proposed fee: $2,622
Project Management:
• Management and administration of the WSB project team
• Coordination and communication with City and other project stake holders (i.e. property owners,
utilities, permitting agencies)
• Proposed fee: $588
Design Services:
• Construction plans
o Title sheet
o Miscellaneous Details
• Trail plans and profiles
• Erosion Control and Turf Establishment
• Specifications and Quantities
K:\Shakopee \Quarry Lake Trail 2014\LTR Prop Quarry Lake Trail 3- 17- 14.doe
Mr. Bruce Loney, PE
City of Shakopee
March 17, 2014
Page 2 of 2
Bidding quote administration
Permit Applications (all permit fees would be paid for by the City)
o MPCA NPDES Permit
• Shakopee Grading Permit
• Lower Minnesota Watershed District Permit (if necessary)
Proposed fee: $9,434
Construction Staking:
• Construction staking for the items shown in the construction plans
• Proposed Fee: $2,622
As- builts /Record Drawings:
• Survey field- constructed improvements
• Revise the construction plans to reflect the field- constructed conditions
• Provide record drawing documents in PDF format for use by the City
• Provide CAD file of record drawings in a digital format.
• Proposed Fee: $777
Project Total Fee:
• Our hourly billing rates and hours for each task are shown on the attached cost breakdown.
• Proposed Design and Topographic Survey Fee: $12,644
• Proposed Construction Staking and As -built Fee: $3,399
• Proposed Project Total Fee: $16,043
This letter represents our understanding of the requested services. If you are in agreement, please sign
on the space provided and return one original signed copy to us for our records.
If you have any questions concerning this letter or fee as discussed herein, please feel free to contact me
at 763 - 287 -7189. We greatly appreciate the opportunity to assist you and the City of Shakopee in the
completion of this project.
Sincerely,
WSB & Associates, Inc.
,'-A2)r-
Don Sterna, P.E.
Principal
I hereby authorize WSB & Associates, Inc. to proceed with the above - referenced Scope of Work in
accordance with WSB's current fee schedule.
City of Shakopee Authorized Representative
City of Shakopee Mayor
City of Shakopee City Administrator
Date
Date
Date
K:\Shakopee \Quarry Lake Trail 2014\LTR Prop Quarry Lake Trail 3- 17- 14.doe
Date Printed: 3/17/2014
WSB Filename: K: \Personal \Chuck Kochmann \Quarry Lake Park \Project Area Map.dgn
Quarry lake Park Trail Improvements
SHAKOPEE City of Shakopee, Minnesota
Project Area Map
A
WSB
QUARRY LAKE PARK TRAIL EXTENSION
CITY of SHAKOPEE, MINNESOTA
Date 3/17/14
DETAIL DESIGN
Estimated Hours
Cost
Project
Manager
Project
Engineer/
Supervisor
Design
Engineer/
Tech
CADD
Tech V
2- Person
Survey
Crew
Clerical
Total
Hours
Task No. Description
1 TOPOGRAHPIC SURVEY
4
14
18
$ 2,622.00
A. Survey/ Base Mapping
1
2
4
14
18
$ 2,622.00
2 PROJECT MANAGEMENT
1
4
1 14
1
18
$ 3,399.00
A. Management
4
JHourly Costs
4
$ 588.00
3 TRAIL DESIGN
Total Labor and Expenses
$452.00 1 $2,170.00 1
J$ 3,399.00
A. Title Sheet/ Misc. Details
4
8
12
$ 1,416.00
B. Trail Plans and Profiles
6
16
4
26
$ 3,028.00
C. Erosion Control/ Turf Plans
4
8
4
16
$ 1,868.00
D. Specifications/ Quantities
2
8
4
14
$ 1,446.00
E. Quote Administration
4
2
6
$ 844.00
F. Permits
1 2
4
2
8
Is 832.00
Total Hours
10
1 18
44
12
1 14
1 6
1 104
is 12,644.00
Hourl Costs
147.00 1 128.00
113.00
113.00 1 155.00
1 62.00
Total Labor and Expenses
1 $1,470.00 1 $2,304.00
$4,972.00
$1,356.00 1 $2,170.00
1 $372.001
1 $ 12,644.00
CONSTRUCTION SERVICES
Estimated Hours
Cost
Project
Manager
Project
Engineer/
Supervisor
Design
Engineer/
Tech
CADD
Tech V
2- Person
Survey
Crew
Clerical
Total
Hours
Task No. Description
4 Construction Staking
4
14
18
$ 2,622.00
5 As-built/Record Drawings
1
2
1
2
6
1 $ 777.00
Total Hours
1
4
1 14
1
18
$ 3,399.00
F-
JHourly Costs
147.00
128.00
113.00 113.00 155.00 1 62.00
Total Labor and Expenses
$452.00 1 $2,170.00 1
J$ 3,399.00
Shakopee Quarry Lake Trail Extension design estimate 3- 17- 14.xls 3/17/2014