HomeMy WebLinkAbout13.A.1. Consider Awarding a Contract for, Project No. 2006-2-Res. No. 6413
CITY OF SHAKOPEE J 3.11. J#
Memorandum
TO: Mayor & City Council
Mark McNeill, City Administrator
FROM: Jeff Weyandt, Assistant City Engineer
Mark Themig, Parks, Recreation and Facilities Director
SUBJECT: Consider A warding a Contract for the
2006 Street Reconstruction and Tahpah Park Improvements,
Project No.2006-2
DATE: May 2,2006
INTRODUCTION:
Attached is Resolution No. 6413, which accepts the bids and awards a contract for the 2006 Street.
Reconstruction and Tahpah Park Improvements, Project No. 2006-2.
BACKGROUND:
On March 21, 2006, City Council adopted Resolution No. 6386, which approved the plans and
specifications and authorized staff to advertise for bids for the 2006 Street Reconstruction and
Tahpah Park Improvements, Project No. 2006-2. The project includes reconstruction of Tahpah
Park; 4th A venue, from Scott Street to Cass. Street; 5th A venue, from Scott Street to Webster Street;
6th Avenue, from Scott Street to Webster Street; Webster Street, from 5th Avenue to 6th Avenue; Cass
Street, from 4th A venue to 6th A venue; Clay Street, from 4th A venue to 6th A venue; and Pierce Street,
from 4th Avenue to 6th Avenue.
On April 25, 2006, a bid opening was held on the 2006 Street Reconstruction and Tahpah Park
Improvements Project, in which there were three bids opened for this improvement project. The
bids are summarized in the attached resolution. From the bid opening, the apparent low bidder is
S.M. Hentges & Sons, Inc. with a total bid of $3,611,611.15 ($2,275,596.47 Street
Reconstruction and $1,336,014.68 Tahpah Park Improvements). The Engineer's estimate for this
project is $3,680,000.00.
Street Reconstruction
The feasibility study for the 2006 Street Reconstruction Improvements contained a construction
cost estimate of approximately $2,406,780.42 and a project cost estimate of approximately
$3,008,475.54. Adding a 5% contingency and 25% project costs to the actual low bid the
projected project cost is approximately $2,986,720.37, which is below the estimated project cost
in the feasibility study for the 2006 Street Reconstruction Improvements.
Tahpah Park
Tahpah Park work contains both work that would be funded from the sale of bonds through a 429
project, as well as work funded from the park reserve fund.
429 Project Costs
The feasibility study cost estimate for the 429 portion of the project includes the main parking lot
reconstruction, the north lot addition, all storm water systems, and the playground equipment.
This estimate was $982,000. The actual bid for this work came in at $780.610.78; however, the
bid did not include the playground at $75,000. We are bidding the playground and installation
separately at a to-not-exceed cost of $75,000 in order to eliminate general contractor mark-up.
The general contractor is responsible for all the site preparation for the playground, and the 429
bid includes rubber surfacing material similar to what was installed at the Huber Community
Built Playground. The unit cost for the surfacing material seems a little high, so we are verifying
thiscost. If deemed excessive, this unit quantity item could be deleted and added to the
playground work.
In addition to the work in the feasibility study, the 429 section of the bid also includes the cost to
install the irrigation well, $62,985.76. This cost includes the well drilling, pump, electrical, and
reconfiguring the existing piping.
The total costs for the 429 work (parking, storm water, irrigation well, and playground) is
$918,596.54. Factoring in a 5% contingency at $45,930 and an estimated 15% indirect costs at
$137,789.48 is still within the bond capacity, according to the city's bond attorney.
Park Reserve Bid Results and Funding
The park improvement section of the bid came in at$492,418.l4. This bid includes several items
that were optional upgrades, such as installation of conduit for future fiber (a request of the
Telecommunications Commission), replacing back stops, and new foul poles.
Park Reserve CIPallocation for this work was $455,250. In addition, the Jaycees recently made a
contribution to the project of $25,000, Women's Softball is making a contribution tonight of
$6,142.15 for lighting, and Men's softball will be making a contribution of approximately $8,000
for lighting; and Co-Rec softball will be making a contribution of approximately $3,600.
In order to meet the budget, there are several adjustments that would be made to the unit quantity
bid amounts. The table below shows the costs and funding with a 5% contingency, an anticipated
5% in indirect costs, project adjustments, and Public Works willingness to assist in removing
backstops on fields 1 & 4 and salvaging outfield fences on fields 2-4:
Costs and Funding Amount
Bid Amount for Park Work -492,418.14
5% contingency . ,.' -24,620.91
5% indirect costs -24,620.91
Park Reserve CIP 455,250
Jaycees Donation . 25,000
Women's Softball Lighting Fund Donation 6,142.15
Men's/Co Rec Softball Lighting Fund Donation 11,600
Sub Total -43,668
Adjustments
Telecom Funding for Fiber Conduit (or eliminate) 5,870
Public Works Removes Backstops (1 & 4) 8,340
Retain Current Backstops (2 & 3) 19,166
Public Works Remove Outfield Fences (2-4) 5,240
Delete New Foul Poles (1-3) 8,130
Delete Out of Play Poles (2-3) 2;781
Sub Total 49,527
Balance 5,859.20
By awarding the bid, most of the major work would becompletM With this contract, including
extending fields 1-3, reconstructing field 4, and lighting fields I and 4. The adjustments would be
made as unit quantity reductions and could be completed at another time, if desired, or possibly
even with the project using any remaining funds. We would monitor the costs closely throughout
the project to determine whether the adjustments could be included in the work with the available
funding.
Contingency
If Council awards the contract, staff is also requesting a contingency amount equal to 5% of the
contract to cover minor change orders and quantity adjustments that may occur on the project.
ALTERNATIVES:
1. Accept the low bid of S.M. Hentges & Sons, Inc. and adopt Resolution No. 6413.
2. Reject the low bidder and award to another bidder.
3. Reject all bids and rebid.
4. Approve a 5% contingency amount on this project for use by the City Engineer in
authorizing change orders or quantity adjustments on this project.
5. Authorize the appropriate City officials to execute an extension agreement with. WSB &
Associates, Inc. to perform construction staking services on the 2006 Street
Reconstruction Improvements.
6. Table for additional information.
RECOMMENDATION:
Staff recommends Alternative No.1, No.4 and No.5 in order for this project to be constructed in
2006.
ACTION REOUESTED:
1. Offer Resolution No. 6413, A Resolution Accepting Bids on the 2006 Street
Reconstruction and Tahpah Park Improvements, Project No. 2006-2 and move its
adoption.
2. Approve a 5% contingency amount on this project for use by the City Engineer in
authorizing change orders or quantity adjustments on this project.
3. Authorize the appropriate City officials to execute an extension agreement with WSB &
Associates, Inc. to perform construction . staking services on the 2006 Street
Reconstruction Improvements.
RESOLUTION NO. 6413
A Resolution Accepting Bids For
For The 2006 Street Reconstruction
And Tahpah Park Improvements
Project No. 2006-2
WHEREAS, pursuant to an advertisement for bids for the 2006 Street Reconstruction and
Tahpah Park hnprovements, Project No. 2006-2, bids were received, opened on Apri125, 2006, and
tabulated according to law, and the following bids were received complying with the advertisement:
Bidder Amount
S.M. Hentges & Sons, me, $3,611,611.15
Barbarossa & Sons, Inc. $4,154,253.20
Three River, mc. $4,389,618.50
WHEREAS, it appears that S.M. Hentges & Sons,mc., P.O. Box 69, Jordan, MN 55352 is
the lowest responsible bidder for the 2006 Street Reconstruction and Tahpah Park hnprovements.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SHAKOPEE, MINNESOTA:
1. The appropriate City officials are hereby authorized and directed to enter into a
contract with S. M. Hentges & Sons, mc. in the name of the City of Shakopee for the 2006 Street
Reconstruction and Tahpah Park hnprovements Project according to the plans and specifications
therefore approved by the City Council and on file in the office of the City Clerk.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders
the deposits made with their bids, except that the deposits of the successful bidder and the next
lowest bidder shall be retained until a contract has been signed.
Adopted in session of the City Council of the City of Shakopee,
Minnesota, held this day of , 2006.
Mayor of the City of Shakopee
ATTEST:
City Clerk
~
WSB
& Associates, Inc. Infrastructure I Engineering I Planning I Construction 701 Xenia Avenue South
Suite 300.
Minneapolis, rviN 55416
April 25, 2006 Tel: 763-541-4800
Fax: 763-541-1700
Mr. Jeff Weyandt, P.E.
Assistant City Engineer
City of Shakopee
129 Holmes Street South
Shakopee,~ 55379-1376
Re: Extension Agreement to Provide Construction Surveying Services
2006 Street Reconstruction Project
Dear Mr. Weyandt:
According to our Agreement for Professional Services within the City of Shakopee and Section
I-C-2 (Major Projects), this extension agreement is written to provide construction surveying
services for the above-referenced project.
It is our understanding that this project consists of approximately 11,000 linear feet of street and
utility reconstruction on eleven (11) blocks of urban streets in the older sections of the City. Our
proposal to complete this work is as follows:
WSB will provide the construction staking required for this project on an hourly basis, as
necessary, in accordance with our current fee schedule, with a not-to-exceed fee of $55,000. This
includes all costs, including mileage, hubs, lathe, miscellaneous supplies and final as-built survey
data for the City to use in the preparation of the record drawings.
It is our understanding that the City will provide the AutoCAD files for WSB to use in the
preparation of the~take-out data needed for the construction aiigiunents and profiles.
Weare available to start this work as soon as it is authorized and look forward to the opportunity
to serve you. It is our understanding that the construction is to begin the week of May 8 or the
week of May 15, 2006.
Thank you for considering WSB for your surveying services. We look forward to working with
you and greatly appreciate the opportunity to assist you and your staff in the completion of this
project.
Minneapolis I St. Cloud
Equal Opportunity EITlp.~!lX~ER PROPOSALS\Shakopee\042506extltl'.doc
Mr. Jeff Weyandt, P.E.
City of Shakopee
April 25, 2006
Page 2
If this agreement meets with your approval, please sign below and return one copy to our office.
If you have any questions regarding this extension agreement, please contact me at 763-287-
7181.
Sincerely,
WSB & Associates, Inc.
:>~(j~J~
Steven V. Ische, RLS
Survey Group Manager
lh
Authorized City Representative
Signature
Date
P:\LErTER PROPOSALS\SjlJlkopee\0425(J6,~xtJtr.d()c