HomeMy WebLinkAbout15.C.1. Consider Awarding a Contract for the Dean Lake Outlet Control Structure, Project No. 2005-7-Res. No. 6328 CITY OF SHAKOPEE 15, c. J ., Memorandum TO: Mayor & City Council Mark McNeill, City Administrator FROM: Bruce Loney, Public Works Director SUBJECT: Consider A warding a Contract for the Dean Lake Outlet Control Structure, Project No. 2005-7 DATE: November 15, 2005 INTRODUCTION: Attached is Resolution No. 6328, which accepts the bids and awards a contract for the Dean Lake Outlet Control Structure, Project No. 2005-7. BACKGROUND: On October 4, 2005, City Council adopted Resolution No. 6309, which approved the plans and specifications and authorized staff to advertise for bids for the Dean Lake Outlet Control Structure, Project No. 2005-7. The project includes construction of a permanent control structure for the outlet of Dean Lake On November 8, 2005, a bid opening was held on the Dean Lake Outlet Control Structure Project, in which there were six bids opened for this improvement project. The bids are summarized in the attached resolution. From the bid opening, the apparent low bidder is Sheryl's Construction, Inc. with a Base Bid - $88,630.00 plus Alternate A - $50,000.00 totaling $138,630.00 or Jay Bros., Inc. with a Base Bid - $68,640.00 plus Alternate B - $40,766.00 totaling $109,406.00. The Engineer's estimate for this project is $190,000.00 for Alternate A and $135,000.00 for Alternate B. The 2005 CIP contained a construction cost estimate of approximately $160,000,00 and a project cost estimate of approximately $205,000.00. In review of the bids and the alternates, the Prior Lake - Spring Lake Watershed District (PLSLWD) would prefer the concrete structure (Alternate A), This project would be considered part of the Prior Lake Channel upgrade and eligible to be paid by the PLSLWD, Cities of Prior Lake and Shakopee and the Shakopee Mdewakanton Sioux Community (SMSC) once an agreement is signed. Currently, the draft JP A would have this structure paid as follows: Cityof Shakopee 37.3% PLSLWD 36.9% City of Prior Lake 14.0% SMSC 11.9% If a total project cost of $182,000.00 is utilized, which will be construction cost for Alternate A, 5% contingency and 25% indirect costs, then Shakopee's share would be $67,886.00. The amount budgeted in the CIF was $170,000.00. Attached also is a recommendation from Todd Hubmer, of WSB & Associates, Inc., on the bids and low bidder. Staff's recommendation would be for Alternate A to be awarded, as the structure. will be a focal point for pedestrians and residents in the area. If Council awards the contract, staff is also requesting a contingency amount equal to 5% of the contract to cover minor change orders and quantity adjustments that may occur on the project. Also, an extension agreement with WSB & Associates, Inc. is necessary to provide for the surveying and construction engineering assistance, as needed for this proj ect. ALTERNATIVES: 1. Accept the low bid of Sheryl's Construction, Inc. and adopt Resolution No. 6328. 2. Accept the low bid of Jay Bros., Inc. and adopt a revised Resolution No. 6328. 3. Reject the low bidder and award to another bidder. 4. Reject all bids and rebid. 5, Approve a 5% contingency amount on this project for use by the City Engineer in authorizing change orders or quantity adjustments on this project. 6. Authorize the appropriate City officials to execute an extension agreement with WSB & Associates, Inc. to provide for the surveying and construction engineering assistance, as needed for this project. 7. Table for additional information. RECOMMENDATION: Staff recommends Alternative No.'s 1,5 and 6 in order for this project to commence. If Council wants to proceed with the project using Alternate B, then Alternative No.2 should be selected. ACTION REQUESTED: 1. Offer Resolution No. 6328, A Resolution Accepting Bids on the Dean Lake Outlet Control Structure, Project No. 2005-7 and move its adoption. 2. Approve a 5% contingency amount on this project for use by the City Engineer in authorizing change orders or quantity adjustments on this project. 3. Authorize the appropriate City officials to execute an extension agreement with WSB & Associates, Inc. to provide surveying and construction engineering assistance, as needed for this Project~~ Public Works irector BUpmp ENGR/2004PROJECT/DEANLAKECONTROLSTRUCTURE/WORDIMEM6328 RESOLUTION NO. 6328 A Resolution Accepting Bids For For The Dean Lake Outlet Control Structure Project No. 2005-7 WHEREAS, pursuant to an advertisement for bids for the Dean Lake Outlet Control Structure, Project No. 2005-7, bids were received, opened on November 8, 2005, and tabulated according to law, and the following bids were received complying with the advertisement: Bidder Base Bid Alternate A Alternate B Sheryl's Const., Inc. $ 88,630.00 $50,000.00 $40,600.00 Jay Bros., Inc. $ 68,640.00 $87,443.00 $40,766.00 Veit Co., Inc. $ 82,250.00 $94,909.00 $33,466.60 Sunram Const., Inc. $117,958.00 $83,000.00 $49,592.50 Carl Bolander & Sons $121,051.00 $99,000.00 $49,345.00 Park Const., mc. $138,034.00 $98,000.00 $41,693.70 WHEREAS, it appears that Sheryl's Construction, Inc., 19821 Parvey Line Rd" Finlayson, MN 55735 is the lowest responsible bidder for the Dean Lake Outlet Control Structure if Alternate A is the preferred alternate for this project, plus the base bid; or NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SHAKOPEE, MINNESOTA: 1. The appropriate City officials are hereby authorized and directed to enter into a contract with Sheryl's Construction, mc. in the name of the City of Shakopee for the Dean Lake Outlet Control Structure Project according to the plans and specifications therefore approved by the City Council and on file in the office of the City Clerk. Adopted in session of the City Council of the City of Shakopee, Minnesota, held this day of ,2005. Mayor of the City of Shako pee ATTEST: City Clerk November 9, 2005 Bruce Loney, P.E. City of Shakopee 129 Holmes Street South Shakopee,~ 55379 Re: Bid Opening for Dean Lake Outlet Control Structure City of Shakopee Project No. 2005-7 WSB Project No. 1281-88 Dear Mr. Loney: On Tuesday, November 8th bids were opened for the Dean Lake Outlet Control Structure (City Project No. 2005-7). The City received a total of six bids for completion of this of this work. The Dean Lake Outlet Control Structure project was bid as two alternates: Alternate A - concrete outlet control structure; and Alternate B -steel sheetpile outlet control structure. Attached, please find photographs of typical concrete and steel sheetpile outlet control structures. The apparent low bidders for the project are: Alternate A - Concrete outlet control structure - Sheryl's Construction, Finlayson,~, with a bid of$138,630.00. Alternate B - Steel sheetpile outlet structure - Jay Brother's Construction, Forest Lake~, with abid of$109,406.00. Based on previous conversations with the Prior Lake Spring Lake Watershed District and the City of Shakopee's Environmental Advisory Committee, there was a preference that the City give consideration to construction ofthe concrete outlet control structure, which will provide for a more appealing aesthetic improvement. Appearance ofthe structure was a concern due to the outlet structure being located adjacent to a future trail. Should the City Council desire to construct Alternate A (the concrete outlet control structure), we would recommend award of the bid to Sheryl's Construction in the amount of $138,630.00. However, should the City Council desire to construct Alternate B (the steel sheetpile weir), we would recommend awarding the contract to Jay Brothers Construction in the amount of$109,406.00. If you have any questions regarding the bids or the project, please call me at 763-287-7182. Sincerely, Todd E. Humber, P.E. Project Manager Attachments kw K:\OI281-88\AdminIDocsILTRemai/.. bloney-lJ0905,doc A WSB & Associates, Inc. November 10,2005 Mr. Bruce Loney, P.E. City of Shakopee 129 Holmes Street South Shakopee,~ 55379 Re: Extension Agreement to Provide Survey and Construction Services Related to the Dean Lake Outlet Control Structure Project City of Shakopee Project No. 2005-7 WSB Project No. 1281-88 Dear Mr. Loney: According to our agreement for professional services with the City of Shakopee in Section I-C-2 (Major Projects), this extension agreement is written to provide professional services for the above referenced project. WSB proposes to provide construction staking and contract administration as necessary to complete the installation of the Dean Lake Outlet Control Structure. The tasks are anticipated to include the following: I. Construction Staking WSB survey crews will provide location and elevation staking for the berm and the outlet control structure as necessary to complete the project. Anticipated cost to complete this task: $1,500- $1,800. II. Construction Management WSB proposes to provide shop drawing review, and as needed construction observation and provide pay voucher and payment recommendations and track change orders on the project. Anticipated cost to complete this task: $2,400 - $3,400. ID. Record Plans WSB will provide a record survey and plans for the Dean Lake Outlet Control Structure. Anticipated cost to complete this task: $800 - $1,200. K:\01281-88!Adminl[)ocsILTR - bloney- 11 lOOS.doc Mr. Bruce Loney, P.E. November 10, 2005 Page 2 WSB proposes to complete the construction phase of the Dean Lake Outlet Control Structure for an estimated cost of $4,700 - $6,400. The City of Shako pee agrees to reimburse WSB & Associates, Inc. for the services in accordance with Section V of the Agreement of Professional Services. Ifthis agreement meets with your approval, please sign below and return one copy to our office. Sincerely, WSB & Associates, Inc. /~E :7P--- Todd E. Humber, P.E. Project Manager cc: Peter R. Willenbring, WSB & Associates, Inc. Bret A. Weiss, WSB & Associates, Inc. kw City Administrator Date City Clerk Date Mayor Date K: !OJ28J.88'AdminlDocsILTR. bloney - I I IOOS.doc BOYS 7TH GRADE BLACK Coach: Tammy & Rich. Carlson 445-9164 Dee 4 Dee 5 Dee 6 Dee 7 Dee 8 Dee 9 Dee 10 Eden Prairie 6:30 PM - 7:45 PM 6:00 PM - 7:30 PM Minnetonka Minnetonka Tournement 7b Community 7b Jr. High 2 Tournament Tournament Center Dee 11 Dee 12 Dee 13 Dee 14 Dee 15 Dee 16 Dee 17 Minnetonka 7:30 PM 7b Jr. High 8:00 PM - 9:00 PM Tournament Cafeteria 7b Pearson 8:00 PM - 9:00 PM 7b Jr.High 1 Dee 18 Dee 19 Dee 20 Dee 21 Dee 22 Dee 23 Dee 24 6:00 PM - 7:30 PM 8:00 PM - 9:00 PM 7b Jr. High 2 7b Jr.High 1 Dee 25 Dee 26 Dee 27 Dee 28 Dee 29 Dee 30 Dee 31 Jan 1 Jan2 Jan3 Jan4 Jan5 Jan6 Jan 7 8:00 PM - 9:00 PM 6:00 PM - 7:30 PM 7b St. Louis Park 7b St. Louis Park 7b Red Oak 7b Sun Path Tournament Tournament Jan8 Jan9 Jan 10 Jan 11 Jan 12 Jan 13 Jan 14 7b St. Louis Park 6:00 PM - 7:30 PM Tournament 7b Jr. High 2 Call your coach if you need to miss a practice. Do not arrive more than 10 minutes before your start time. After practice leave promptly ~ .)< Leaend Future Trail Aerial Photo t A. Dean Lake Outlet Final Design WSB Scott County, MN 0 125 250 500 ,Feet & A.';sociates, Inc. Leaend \ ... Future Trail Aerial Photo t ... Dean Lake Outlet Final Design WSB Scott County, MN 0 125 250 500 . Feet & As.wciates. Inc. Page 1 of 1 Judy Cox <<~..... m" "'''''''''''''"'',''',, "" """"""""'"'" From: Tracy J. Schaefer [schaefer@bradleyguzzetta.com] Sent: Thursday, November 10, 200510:50 AM To: Judy Cox; Lori Hensen Cc: Mark McNeill; Stephen J. Guzzetta Subject: 394 Transfer City Council Agenda Documents Importance: High Judy/Lori, Attached are the documents for the 394 Comcast/Time Warner item on the City Council agenda. To save on time and money, only City Council, public packet, Mark, TW and Comcast packets need to have all of the attachments. For the department heads and other packets, the November 10,2005 cover memo is sufficient. Also, Judy, please include ALL of these documents in the 394 transfer file. The majority of the documents have changes, so it is important to include them all. Document Order 1. November 10, 2005 Cover Memo from B&G 2. Nov. 2, 2005 Memo from Tracy 3. Oct. 17/18 Memo from Steve & Tracy 4. Oct. 3/4 Memo from Tracy '- 5. Resolution No. 6303 - REDLlNE VERSION I 6. Resolution NO. 6303 - CLEAN VERSION 7. Sept. 28, 2005 Report on the Transfer (about 30 pages) .3 8. Attachment 1 -Resolution No. 6303 (it has been updated with the Nov. 15 date) 1 9. Attachment 2 - Resolution No. 6303 -Denial (it has been updated with the Nov. 15 date) 10. Attachment 3 - Comcast Resolution 11. Attachment N - list of all documents from the Sept. 28, 2005 Report. I will be in the office today, so please let me know if you have any questions/comments. Also, I am also emailing the same information to staff at Comcast and Time Warner. Thanks, Tracy J. Schaefer Bradley & Guzzetta, LLC 950 Piper Jaffray Plaza 444 Cedar Street St. Paul, MN 55101 651-379-0900 x. 4 651-379-0999 - fax schaefer@bradleyguzzetta.com www.bradleyguzzetta.com ' 11/10/2005